PECB Certified Lead Disaster Recovery Manager: Risk Assessment and Business Impact Analysis for Disaster Recovery

PECB Certified Lead Disaster Recovery Manager · Work through your exam, one topic at a time.

All guide sections

Risk Assessment and Business Impact Analysis for Disaster Recovery

What the exam tests

This domain tests whether you can connect risk assessment and BIA outputs to recovery priorities, RTOs, RPOs, and resource requirements.

Core rules

  • Risk assessment identifies threats, vulnerabilities, likelihood, and impact, then evaluates treatment options. It informs scenario selection; it does not replace the BIA.
  • The BIA identifies critical activities, dependencies, impact over time, MTPD, RTO, RPO, and minimum resources: people, systems, data, suppliers, and facilities.
  • RTO must not exceed MTPD. The gap between them is the time available for detection, assessment, declaration, and mobilization.
  • Capture interdependencies: an activity may depend on identity, network, payment, or a single supplier. Cumulative impact can exceed the sum of individual outages.
  • Validate BIA data with activity owners and walkthroughs; document assumptions.

Worked example

Payroll has an MTPD of 3 days, RTO of 2 days, and RPO of 1 day. It depends on the HR system, time capture, and banking files. Reasoning: a 2-day RTO leaves one day before MTPD; daily data extraction meets the 1-day RPO. The strategy must restore HR data, time capture, and bank-file production, not just the payroll application. A single identity service supporting all three becomes a priority dependency.

Traps

Running a BIA as an IT asset inventory; interviewing only senior managers; accepting vendor RTOs without validating dependencies; ignoring manual workarounds; and setting RTO equal to MTPD with no assessment time.