PEPT flashcards
PEPT · Build recall with a focused review session.
34 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Paramountcy of public welfare
- The ethical duty that public safety, health, and welfare outrank obligations to clients and employers when the two conflict, justifying refusal or escalation.
- Conflict of interest
- A situation where a personal, financial, or other interest could improperly influence professional judgement; it must be disclosed and, where necessary, the engineer must withdraw.
- Seal and signature
- A personal attestation that the engineer prepared or directly supervised the work and reviewed it; applying it to unverified work is misconduct.
- Standard of care
- The degree of skill and diligence an ordinary competent engineer would exercise in similar circumstances; falling below it can establish negligence.
- Negligence elements
- A successful claim requires a duty of care owed, a breach of the standard of care, causation of the loss, and damage of a recognised kind.
- Limitation period
- The statutory time limit within which a claim must be brought, running from the breach or from when the damage should reasonably have been discovered.
- Liability cap
- A contract clause limiting the maximum damages payable; it must be reasonable and cannot exclude liability for fraud or statutory safety duties.
- Professional indemnity insurance
- Cover for claims arising from negligent acts, errors, or omissions in professional services; it typically excludes deliberate acts, warranties, and liquidated damages.
- Joint and several liability
- A rule letting a claimant recover the full loss from any one contributing party, who may then seek contributions from the others.
- Net present value
- The sum of future cash flows discounted at the required rate of return, minus the initial investment; a positive result supports proceeding.
- Internal rate of return
- The discount rate at which a project's net present value equals zero; compare it with the hurdle rate, but use NPV to rank mutually exclusive options.
- Payback period
- The time needed for cumulative cash inflows to recover the initial outlay; it ignores the time value of money and all later cash flows.
- Whole-life costing
- Totalling capital, operating, maintenance, energy, and disposal costs over the asset's life so that options are compared on total cost, not first cost.
- Critical path
- The longest duration sequence of dependent activities through the network; it determines the shortest possible project duration and carries zero total float.
- Total float
- The amount an activity can be delayed without delaying the project completion date, calculated as late start minus early start.
- Cost performance index
- Earned value divided by actual cost; a value below one means the work is costing more than budgeted for the value delivered.
- Estimate at completion
- The forecast final project cost; when current cost performance continues, it equals budget at completion divided by the cost performance index.
- Hierarchy of controls
- Risk control ranked from most to least effective: eliminate the hazard, substitute it, engineer controls, apply administrative controls, then use personal protective equipment.
- ALARP principle
- Risk should be reduced so far as is reasonably practicable, balancing the cost and difficulty of further controls against the reduction in harm achieved.
- Permit to work
- A formal written authorisation controlling high-risk activities such as hot work, confined-space entry, or energised work, specifying precautions and validity limits.
- Waste hierarchy
- A priority order for materials: prevent, reuse, recycle, recover energy, and dispose; disposal carries the greatest environmental and regulatory burden.
- Quality assurance versus control
- Quality assurance is preventive and process-focused, verifying that procedures are followed; quality control is detective and product-focused, checking outputs against criteria.
- Non-conformance report
- A record of work failing a requirement, stating the location, the requirement breached, the disposition chosen, the corrective action, and the verification of the fix.
- Hold point
- A stage in an inspection and test plan where work must stop until the nominated inspector releases it in writing; work cannot proceed without that release.
- Calibration traceability
- An unbroken chain of comparisons linking an instrument's readings to a national metrology standard, evidenced by certificates retained in the quality records.
- Notice of claim
- A formal written notification of a claim event, given within the contract's stated time and form; late or informal notice can forfeit the entitlement.
- Variation versus instruction
- A variation changes scope, quality, or time and adjusts the price; an instruction directs how existing scope is carried out without changing it.
- Contemporaneous records
- Documents created at the time of the event, such as site diaries, photographs, and dated correspondence, which carry more evidential weight than later reconstructions.
- Scope 1, 2 and 3 emissions
- Direct emissions from owned sources, indirect emissions from purchased energy, and all other supply-chain and use-phase emissions; scope 3 usually dominates.
- Embodied carbon
- Greenhouse gas emissions associated with extracting, manufacturing, transporting, installing, and eventually disposing of materials, fixed largely at design stage.
- Circular design
- Designing for disassembly, reuse, and material recovery so that components re-enter the economy rather than becoming waste at end of life.
- Tuckman team stages
- The sequence forming, storming, norming, performing, and adjourning; conflict during storming is normal and should be managed rather than suppressed.
- Digital twin
- A live digital model of an asset fed by sensor data; its value depends on calibration, data governance, and a clearly defined decision use.
- Human oversight of AI
- The principle that automated or AI-generated engineering outputs must be verified by a competent person, who remains accountable for the checked result.