HEO Crawler Crane NC III flashcards
HEO Crawler Crane NC III · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Rated capacity definition
- The maximum load the crane may lift at a given radius, boom length, and configuration; it is the lower of the structural limit and the stability limit.
- Radius measurement point
- Horizontal distance from the crane's center of rotation to the center of the hoist line, measured with the load suspended, not to the boom tip.
- Net capacity calculation
- Gross chart capacity minus the weight of everything below the boom tip: hook block, slings, shackles, spreader beam, and any auxiliary equipment.
- Percent of capacity formula
- Total load including rigging divided by net chart capacity, multiplied by 100; lift plans commonly require extra review above a defined threshold such as 75 percent.
- Anti-two-block device
- A switch and weight on the boom tip that stops hoisting and boom lowering before the hook block contacts the boom tip sheave, preventing rope and structural damage.
- Load moment indicator
- An instrument that senses boom angle, length, and load to display radius, capacity, and percent of capacity, and that stops operations when the rating is exceeded.
- Wire rope removal criteria
- Conditions requiring rope replacement include broken wires, diameter reduction, corrosion, kinking, crushing, bird-caging, and damaged end attachments, per the applicable standard.
- Sheave groove wear
- A worn sheave groove pinches and abrades the rope, accelerating fatigue; inspect groove diameter and flange condition and replace sheaves beyond manufacturer limits.
- Track shoe wear limit
- Shoe and grouser height are measured against the manufacturer's limit; shoes worn past limit, cracked, or with loose grousers must be replaced before operation.
- Ground bearing pressure
- The crane and load reaction divided by the effective mat area; it must stay below the soil's allowable bearing capacity to prevent settlement or tipping.
- Sling leg tension formula
- Tension per leg equals load divided by the number of legs times the sine of the angle from horizontal; flatter angles greatly increase tension in each leg.
- Center of gravity rule
- The hoist line must be directly above the load's center of gravity; otherwise the load tilts, swings, and may rotate uncontrollably once lifted.
- Exclusion zone definition
- A barricaded area covering the full swing radius including counterweight tail swing, where no personnel may stand during slewing or lifting operations.
- Rigging rejection criteria
- Reject slings with cuts, burns, knots, or missing tags; reject hooks with throats spread beyond 15 percent or missing latches, and shackles with worn pins.
- Carbody leveling tolerance
- The crane must be set level within the manufacturer's tolerance, commonly about one degree, before the boom is extended or any load is lifted.
- Counterweight chart matching
- The installed counterweight must match the load chart for the boom and jib configuration; any change alters capacity and must follow the chart.
- Boom backstop function
- A structural stop that prevents the boom from being raised past its maximum angle; the boom hoist limiter must stop raising before contact.
- Trial lift purpose
- After assembly, lift a known weight slightly off the ground to confirm stability, brake holding, and correct load moment indicator readings before production lifting.
- Side load effect
- Load charts assume vertical loading; side pull from dragging or booming reduces capacity and can buckle the boom lattice, so it must be avoided.
- Tag line use
- Ropes attached to the load to control rotation and swing; handlers stay outside the fall zone and clear of the swing path while keeping lines taut.
- Pick-and-carry restriction
- Travel with a suspended load is permitted only where the load chart allows it, with reduced capacity, low boom, load trailing, and firm level ground.
- Standard stop signal
- A hand signal or verbal command halting all crane motion; any person on site may give an emergency stop, not only the designated signal person.
- Signal person designation
- Only one designated signal person directs the operator at a time; if communication is lost, the operator stops and holds until contact is restored.
- Power line clearance
- The crane must maintain the required minimum distance from energized lines for the voltage class; otherwise de-energize and ground the line and use a spotter.
- Wind speed limit
- The manufacturer specifies maximum wind speed for each boom and load configuration; operations stop when it is exceeded or the load becomes uncontrollable.
- Brake drift condition
- A swing or travel brake that does not hold the load is a stop-work condition; the crane is tagged out until the brake is adjusted or repaired.
- LMI recalibration trigger
- Recalibrate the load moment indicator after any boom change, rope change, or sensor replacement, and record the date and technician identification.
- Daily inspection record
- A checklist recording date, machine serial number, hour meter, items checked, defects found, and the inspector's name and signature for each shift.
- Lift plan contents
- A document stating load and rigging weights, crane configuration, radius, boom length and angle, chart capacity, percent of capacity, ground condition, and approvals.
- Defect escalation rule
- Any defect affecting a safety device such as the LMI, anti-two-block, or brakes must be recorded, the crane tagged out, and the defect escalated to the responsible person.
- Near-miss reporting
- An unplanned event that did not cause injury or damage is recorded with time, location, sequence, and corrective action, with the same rigor as an incident.
- Shutdown sequence steps
- Land the load, lower the boom to rest, set swing and travel brakes, chock tracks on slopes, shut down, lock the cab, and record hours and faults.
- Boom configuration limits
- Boom and jib sections must match the permitted chart combinations; exceeding the maximum boom plus jib length invalidates the load chart for that setup.