HEO Crawler Crane NC III study materials
HEO Crawler Crane NC III study resources

HEO Crawler Crane NC III: Site preparation, rigging, and load handling planning

HEO Crawler Crane NC III · Work through your exam, one topic at a time.

All guide sections

Site preparation, rigging, and load handling planning

Site preparation, rigging, and load handling planning

This domain tests the planning done before the crane moves: ground conditions, access, clearances, and the rigging that connects the load to the hook.

Ground and site

  • Estimate ground bearing pressure: crane weight + counterweight + load + dynamic allowance, divided over the track contact area; compare with soil capacity and add steel mats or cribbing where needed. Watch for backfilled trenches, vaults, basements and buried utilities.
  • The crane must sit level within the manufacturer's tolerance (often 1% or 0.5°); level is a precondition of the load chart.
  • Plan swing clearance for counterweight and boom, and keep the whole swing path clear of stock, excavations and people.
  • Respect approach distances to energized lines; commonly cited ASME B30.5 minimums are 3.0 m up to 50 kV, 4.6 m for 50–200 kV and 6.1 m for 200–350 kV, plus a spotter or de-energization.

Rigging

Confirm load weight from documents or a scale, not guesswork. Identify the centre of gravity, select slings by working load limit at the actual sling angle, protect sharp edges, and plan tag lines. Multi-leg slings lose capacity as the legs flatten toward horizontal.

Worked example

A 4 t load on a two-leg sling with 60° between the legs: each leg tension = 4 / (2 × cos 30°) = 2.31 t. A 2 t vertical-rated sling per leg is therefore not acceptable, because 2.31 t exceeds its WLL at that angle.

Traps

Using the vertical WLL for angled legs; measuring the included angle instead of the angle from horizontal; accepting "it looks solid" ground; forgetting the weight of spreader beams, slings and shackles in the plan.