PMI CD-P: Business Problem Framing and Discovery

PMI CD-P · Work through your exam, one topic at a time.

All guide sections

Business Problem Framing and Discovery

Domain 1 - Business Problem Framing and Discovery

This domain tests whether you can decide what to build before touching a platform: how to frame a business problem, quantify it and scope a citizen-development solution the business and IT can both live with. Expect questions on process discovery, value hypotheses, requirements elicitation and build/no-build decisions.

Start with the process, not the tool

  • Map the current-state process end to end: steps, owners, handoffs, wait time, rework loops and exception paths.
  • Separate symptom from cause. Late invoices may be an approval bottleneck, not a data-entry problem; use 5 Whys or a fishbone before proposing an app.
  • Quantify a baseline: volume, cycle time, error rate, cost per transaction. Without a baseline you cannot prove value later.

Scope and requirements

  • Write a one-sentence problem statement and a measurable outcome, such as reducing exception handling from 30 to 10 minutes.
  • Define in-scope, out-of-scope and definition of done; agree acceptance criteria with the process owner.
  • Confirm data feasibility early: does the data exist, who owns it, is it clean, may you legally use it?
  • Identify sponsor, process owner, end users, IT partner and any compliance stakeholder.

Worked example

Accounts payable rekeys 40 exception invoices weekly at 6 minutes each - about 16 hours a month - with an 8% keying error rate. The proposed app captures the invoice, validates vendor and purchase order, and routes exceptions. The team explicitly excludes ERP write-back and instead requests read-only vendor data from IT. Benefit is quantified as hours saved plus reduced rework, and the scope fits a two-week thin slice.

Traps that cost marks

  • Solution-first thinking instead of problem framing.
  • Unquantified benefits and no baseline.
  • Ignoring exception paths, which are usually where the real work sits.
  • Skipping data feasibility or stakeholder sign-off, then discovering the data is unusable.