Question 1PMO setup and design
Which PMO type gives project managers the greatest autonomy by providing templates, coaching, and best practices without enforcing compliance?
- Directive
- Controlling
- Enterprise
- Supportive Correct answer.
Explanation
PMO types are commonly classified by the degree of control they exercise. A supportive PMO supplies guidance, templates, and coaching as a consultative service while project managers retain full authority for delivery.
Question 2PMO setup and design
Which content is essential in a PMO charter?
- A detailed schedule of every project the organization will run in the coming year
- The organization's full financial statements and most recent audit history
- The PMO's mandate, scope of services, level of authority, and success measures Correct answer.
- The résumés of all project managers who will be assigned to the PMO
Explanation
A PMO charter is the founding document that authorizes the PMO and sets its boundaries. It must state why the PMO exists, what it will deliver, how much authority it holds, and how success will be judged.
Question 3PMO setup and design
A PMO service catalog primarily documents which of the following?
- The services the PMO offers, who they are for, and how they are delivered Correct answer.
- The audit findings from the previous fiscal year and their remediation status
- The list of vendors approved for purchasing project management software
- The career paths of the PMO's staff over the next five years
Explanation
The service catalog is the PMO's public statement of what it provides to the organization. It defines each service, its intended consumers, and the manner and level of delivery so that demand and expectations are managed.
Question 4PMO setup and design
During PMO design, stakeholder analysis is performed mainly to do what?
- Determine which projects in the portfolio should be cancelled this quarter
- Understand each stakeholder's influence and interest so engagement can be planned Correct answer.
- Rank employees by performance so that staffing decisions can be made
- Calculate the cost of each service in the PMO's offering
Explanation
Stakeholder analysis maps who is affected by and can affect the PMO, along with their relative influence and interest. Its purpose is to shape an engagement approach that secures sponsorship and reduces resistance during design and launch.
Question 5PMO setup and design
How is a PMO maturity model most appropriately used at setup?
- As a certification exam for PMO staff
- To benchmark competitors' project budgets
- To baseline current capability and plan a progression path over time Correct answer.
- To replace the PMO charter with a numeric score
Explanation
Maturity models describe staged levels of capability and are used diagnostically. At setup they establish a current-state baseline so the PMO can define a realistic, sequenced improvement roadmap rather than attempting full maturity immediately.
Question 6PMO setup and design
Which pair correctly describes the two most common PMO funding approaches?
- Central corporate funding and chargeback to business units Correct answer.
- Crowdfunding and grant funding
- Equity funding and debt funding
- Fixed-price funding and cost-plus funding
Explanation
PMO funding is typically either centralized, where the enterprise bears the cost as overhead, or recovered through chargebacks to the business units that consume PMO services. Each choice affects demand behavior and how visible the PMO's cost is to its customers.
Question 7PMO setup and design
Where is a PMO typically positioned to be most effective?
- Inside a single functional department such as finance, with no other access
- At a level with direct access to the executives who set strategy and approve investments Correct answer.
- As a sub-team inside one project's delivery group
- Outside the organization, as an external contractor to the enterprise
Explanation
A PMO's ability to influence prioritization and investment decisions depends on proximity to the decision-making level it serves. Positioning it with direct executive access lets it escalate issues, align work to strategy, and maintain credibility across the organization.
Question 8PMO setup and design
Which responsibility best fits a PMO analyst?
- Maintaining portfolio data, producing reports, and supporting planning processes Correct answer.
- Approving the annual corporate budget on behalf of the executive committee
- Owning the delivery of every project in the enterprise portfolio
- Sponsoring the organization's largest and most visible portfolio of projects
Explanation
Analyst roles are oriented toward information quality and process support. The analyst keeps portfolio data accurate, generates performance reporting, and helps run planning and governance processes.
Question 9PMO setup and design
A PMO is being designed for a highly decentralized organization in which business units operate autonomously. Which design approach best fits this context?
- Offer a modular service catalog that business units opt into, with standards set collaboratively Correct answer.
- Mandate a single directive PMO that takes ownership of all business unit projects
- Limit the PMO to a shared tool and standard templates only
- Place the PMO under one business unit and give it authority over the others
Explanation
PMO design must fit the organizational context, and in decentralized settings authority is distributed by default. Offering opt-in, modular services lets units take what they value while collaborative standard-setting builds commitment rather than triggering resistance.
Question 10PMO setup and design
A PMO is designing its intake process so that requests for project work are assessed consistently. Which design element matters most?
- Approving every request quickly so as to avoid conflict with requesters
- A single intake point with defined criteria, an evaluation step, and a documented decision Correct answer.
- Letting each requester choose which reviewers will see the request
- Reviewing requests only after the work has already started
Explanation
Effective demand management depends on a consistent, transparent path from request to decision. A single entry point, published evaluation criteria, and a recorded decision make prioritization defensible and comparable across requesters.
Question 11PMO setup and design
Which measure is the strongest choice for a PMO dashboard in its first year?
- The total headcount of the PMO
- The number of templates stored in the repository
- The percentage of projects meeting their committed benefit targets Correct answer.
- The number of emails the PMO sends each week
Explanation
Good PMO measures reflect outcomes the PMO can influence and that stakeholders care about. Benefit attainment connects PMO activity to organizational value, whereas volume and activity counts say nothing about results.
Question 12PMO setup and design
A PMO is asked to support benefits realization across the portfolio. Which setup is most appropriate?
- The PMO defines measures and baselines, then facilitates reviews with benefit owners Correct answer.
- The PMO takes ownership of all benefit targets away from the business owners
- Benefits are tracked only at project closure and are not reviewed afterwards
- The PMO leaves all benefit tracking to finance and takes no role in it
Explanation
Benefits are owned by the business, while the PMO provides the discipline that makes realization visible. Defining metrics and baselines and then facilitating reviews keeps accountability with owners while giving the PMO a genuine assurance role.
Question 13PMO setup and design
Early in its life a new PMO meets resistance from long-tenured project managers. Which response is most effective?
- Escalate to have the resisters removed from their roles
- Publish a directive requiring immediate compliance with all new processes
- Delay all engagement until the processes are fully mature
- Engage them early, involve them in designing services, and demonstrate quick wins Correct answer.
Explanation
Adoption of a PMO is a change management problem as much as a process design problem. Involving experienced practitioners in service design builds ownership and surfaces practical constraints, while early wins build credibility for the PMO.
Question 14PMO setup and design
A PMO must serve projects that range from small internal improvements to large regulated programs. Which design decision reflects good tailoring?
- Exempt small projects from any PMO involvement
- Define service tiers with proportionate governance based on size, risk, and complexity Correct answer.
- Apply one identical process and the same governance rigor to every project regardless of its size or risk
- Serve only the largest projects and ignore the smaller ones
Explanation
Tailoring means scaling governance and support to the risk and complexity actually present. Tiered services give heavy oversight where exposure is high while keeping light-weight paths for low-risk work, which protects both control and speed.
Question 15PMO setup and design
A PMO must build capability in benefits management. Which action best follows a competency-based staffing approach?
- Outsource the entire PMO function permanently to an external provider
- Assign the work to whichever staff member currently has the lightest workload
- Raise the certification requirement for every staff member regardless of role
- Assess the required competencies, then close gaps through hire, train, or partner Correct answer.
Explanation
A competency-based approach starts from the skills the service requires and compares them with current capability. Gaps are then closed deliberately through recruiting, development, or partnering rather than by improvisation.
Question 16PMO setup and design
When selecting a PPM tool to support PMO operations, which criterion should carry the most weight?
- Whether it is the tool a competitor uses
- Whether it has the largest number of features overall
- Whether it is the newest product on the market
- How well it supports the PMO's defined processes and integrates with existing systems Correct answer.
Explanation
Tools should enable the operating model rather than dictate it. Fit with the PMO's designed processes and interoperability with existing enterprise systems determine whether the tool will actually be adopted and sustained.
Question 17PMO setup and design
An organization's culture strongly rewards individual autonomy. How should this shape PMO design?
- Favor lightweight guidance, coaching, and voluntary standards over mandated control Correct answer.
- Wait to launch the PMO until the culture has changed to support it
- Ignore culture, because processes and culture are independent of each other
- Emphasize standardized processes and strict compliance checks across all teams
Explanation
PMO design has to fit the culture it operates in, or resistance will neutralize even well-built processes. In autonomy-oriented cultures, guidance and coaching achieve adoption that mandated control would not.
Question 18PMO setup and design
For a PMO in its first year, which approach best sequences capability building?
- Start with no services at all and add them only after two full years of operation
- Build all reporting dashboards before defining any process or service
- Start with high-value, low-risk services, then expand based on measured results Correct answer.
- Launch the full service catalog for all business units on the first day of operation
Explanation
A phased roadmap lets the PMO earn credibility before taking on higher-risk responsibilities. Delivering a narrow set of valued services well creates evidence that supports expansion and further investment.
Question 19PMO setup and design
Which is the strongest way for a PMO to articulate its value proposition?
- Linking its services to specific business outcomes and the problems they address Correct answer.
- Asserting that PMOs are a recognized industry best practice
- Listing the number of meetings it facilitates each month and the volume of reports it distributes
- Stating that the PMO is required by the organization's policies
Explanation
A value proposition answers why the PMO should exist in business terms. Tying services to outcomes and to concrete organizational problems makes the case testable and distinguishes the PMO from administrative overhead.
Question 20PMO setup and design
When designing governance gates for a portfolio, which principle should the PMO apply?
- Gates should be identical for every project regardless of its context or risk profile
- Gates should be tailored to risk and size, with clear criteria and named decision makers Correct answer.
- Gates should be added at every status meeting so that decisions are made quickly
- Gates should remain optional so that delivery teams are not constrained by governance
Explanation
Governance exists to support decisions, so each gate needs explicit entry criteria and an identifiable decision authority. Scaling the number and depth of gates to the risk and size of the initiative keeps control proportionate.
Question 21PMO setup and design
A PMO is chartered to improve enterprise-wide investment decisions, but it reports to a delivery director whose projects it must evaluate. What is the primary design problem?
- The PMO lacks a documented service catalog and service-level agreements
- The PMO's tooling is outdated relative to other departments in the organization
- The PMO has too many staff relative to the size of the portfolio
- The reporting line creates a conflict between oversight duties and delivery incentives Correct answer.
Explanation
An oversight body must be independent of the work it assesses, or its judgments will be perceived as self-serving. Reporting to a delivery leader whose projects are subject to review compromises both the reality and the appearance of objectivity.
Question 22PMO setup and design
A PMO funded partly by chargeback finds that business units exclude it from early planning to avoid incurring charges. Which redesign best addresses this behavior?
- Increase chargeback rates across all business units to fully recover the PMO's fixed costs each year
- Move to full cost recovery by billing each business unit per meeting attended
- Remove the service catalog from view so that business units stop questioning the charges
- Fund core services centrally and charge back only for optional, discretionary services Correct answer.
Explanation
Chargeback makes consumption visible, but applying it to core services creates an incentive to avoid the PMO precisely when it should be engaged. Funding the mandatory baseline centrally and charging only for discretionary work preserves the consumption signal without distorting early engagement.
Question 23PMO setup and design
A PMO's prioritization scoring ranks projects on financial return only, and the organization increasingly underfunds mandatory compliance and capability-building initiatives. What design change is most appropriate?
- Fund projects strictly in the order in which requests arrive
- Weight criteria to reflect the full set of strategic objectives, including mandatory and capability-building work Correct answer.
- Score only the projects that carry the largest budgets
- Remove all scoring criteria and prioritize projects according to the seniority of the sponsoring executive and the size of the requesting department
Explanation
Prioritization criteria are a design choice that determines which work the portfolio can contain. When criteria cover only one dimension of value, the portfolio drifts away from strategy, so the scoring model must reflect all strategic objectives including mandatory and enabling work.
Question 24PMO setup and design
After several years, a PMO's reporting services are largely automated and also duplicated by a new enterprise tool. What is the most appropriate design response?
- Add more reports and dashboards to demonstrate the value of the existing headcount
- Reassess stakeholder needs and shift the PMO toward higher-value decision support and benefits work Correct answer.
- Continue delivering the same services to preserve the PMO's visibility and headcount
- Close the PMO immediately without any transition plan or transfer of its remaining services
Explanation
A PMO's service portfolio should evolve as the organization's needs and tooling change. Where a service has become commoditized, the PMO protects its relevance by repositioning toward work that still requires judgment, such as decision support and benefits realization.
Question 25PMO setup and design
An enterprise wants consistent standards across the organization while keeping business-unit responsiveness. Which PMO structure best balances these aims?
- A hub-and-spoke model with a central PMO setting standards and business-unit PMOs tailoring delivery Correct answer.
- Fully independent business-unit PMOs with no enterprise coordination
- No formal PMO, relying on informal communities of practice
- A single centralized PMO that keeps all staff in one location and controls the delivery of every project in the enterprise
Explanation
A hub-and-spoke design allocates enterprise-level standards, method ownership, and portfolio reporting to the center while permitting local tailoring of delivery support. This separates the consistency goal from the responsiveness goal so that neither is sacrificed.
Question 26PMO setup and design
A PMO provides templates, coaching, and best-practice guidance that project teams may adopt voluntarily. Which PMO control type does this describe?
- Supportive Correct answer.
- Controlling
- Directive
- Governance board
Explanation
PMO control models range from supportive, where adoption is advisory, through controlling, where compliance with standards is required, to directive, where the PMO manages projects directly. Voluntary adoption of advisory services is the defining characteristic of the supportive model.
Question 27PMO setup and design
Which element is essential to include in a PMO charter?
- The names of every project manager currently employed
- The marketing budget the PMO will spend on promotion
- The mandate, scope, and decision authority of the PMO Correct answer.
- The detailed schedule for the PMO's first assigned project
Explanation
A charter establishes the PMO's reason for existing, what is in and out of scope, what decisions it may take, and how success will be judged. Schedules, staff lists, and promotional spend are operating details rather than the foundation of its authority.
Question 28PMO setup and design
Which role in a PMO is typically accountable for the PMO's strategy and for its relationship with executive leadership?
- PMO director Correct answer.
- Risk coordinator
- Project scheduler
- PMO analyst
Explanation
The PMO director or lead owns the service portfolio, the strategy, and the executive relationships that give the PMO its mandate. Analyst, scheduler, and coordinator roles are delivery and support positions with narrower accountabilities.
Question 29PMO setup and design
What is the primary purpose of a PMO service catalog?
- To document the PMO's reporting lines and headcount
- To list the job descriptions of every PMO staff member
- To define the services the PMO offers and their expected outcomes Correct answer.
- To record the results of the PMO's annual financial audit
Explanation
A service catalog states what the PMO offers, to whom, and what outcome each service is meant to produce, so consumers can select services and the PMO can be measured against them. It is a service offer rather than an HR, structural, or financial record.
Question 30PMO setup and design
What is a PMO maturity assessment primarily used for during design?
- To establish a baseline of current capability and a target future state Correct answer.
- To rank individual PMO staff for promotion and reward
- To determine the annual project budget for the organization
- To replace the PMO charter as the governing document
Explanation
Maturity assessments show where capability currently sits so that design choices aim at a realistic and sequenced future state. They inform design decisions about services and processes; they are not appraisal or budgeting instruments.
Question 31PMO setup and design
When a PMO publishes methodology guidance, what does tailoring mean?
- Allowing each project manager to invent a personal methodology
- Outsourcing methodology design to an external consulting vendor
- Applying every defined process step to every project regardless of size
- Adapting rigor and artifacts to project size, risk, and complexity Correct answer.
Explanation
Tailoring scales the rigor, documentation, and control of a methodology to the characteristics of the work so governance adds value rather than overhead. Uniform application of every step is the opposite of tailoring, and per-manager methods fragment standards.
Question 32PMO setup and design
What is the typical purpose of a PMO steering committee?
- To approve individual project timesheets each week
- To give senior direction, resolve escalated issues, and approve portfolio decisions Correct answer.
- To conduct annual performance reviews of project staff
- To write and execute the test scripts for major projects
Explanation
A steering committee provides senior sponsorship, resolves issues escalated beyond project level, and approves the decisions within its delegated authority. It is a direction-setting body and does not perform transactional or delivery tasks.
Question 33PMO setup and design
Which statement best describes a centralized PMO staffing model?
- PMO staff sit inside business units and take direction only from local managers
- PMO staff are contractors directed by an external vendor
- The PMO has no dedicated staff and publishes templates only
- PMO staff report to the PMO and are deployed across the organization Correct answer.
Explanation
In a centralized model, staff report into the PMO and are assigned to initiatives across the enterprise, which supports consistent standards, shared practices, and career development. Local direction of embedded staff describes a decentralized alternative.
Question 34PMO setup and design
A PMO is clarifying which decisions it makes, which it recommends, and which it is only informed about. Which artifact best captures this?
- A resource histogram
- A lessons-learned log
- A risk register
- A decision-rights matrix Correct answer.
Explanation
A decision-rights matrix, such as a RACI or similar model, records who decides, who recommends, who is consulted, and who is informed for each decision type. This removes both gaps and duplicated authority in the governance design.
Question 35PMO setup and design
A new PMO keeps absorbing new work because stakeholders add requests at every meeting. Which design element best guards against scope creep?
- A larger operating budget approved by the steering committee
- A monthly newsletter publicizing the PMO's achievements
- Additional analysts hired to absorb the incoming requests
- A charter scope statement listing services and explicit exclusions Correct answer.
Explanation
Approved scope with explicitly stated exclusions gives the PMO a defensible basis for declining or deferring out-of-scope requests. Money and headcount increase capacity but do not bound what the PMO has agreed to do.
Question 36PMO setup and design
Before finalizing its service design, a new PMO maps stakeholders by influence and interest. What is the main design benefit of this analysis?
- It shows which stakeholders need which services and at what engagement level Correct answer.
- It sets the chargeback rate applied to business units
- It determines how many software licences to purchase
- It removes the need for a formal PMO charter
Explanation
Stakeholder analysis shapes both the service portfolio and the engagement approach by revealing who needs what and how much involvement is required. It complements chartering rather than replacing it, and does not by itself set licence or charging decisions.
Question 37PMO setup and design
A PMO is designing its escalation process. Which design choice makes escalation most effective?
- Removing formal escalation and relying on email to senior managers
- Requiring all escalations to be routed to the PMO director
- Defining tiered thresholds, named owners, and timeframes at each level Correct answer.
- Allowing project managers to escalate to whichever executive they prefer
Explanation
Effective escalation design specifies the thresholds that trigger escalation, who owns the decision at each level, and how quickly a response is required. Clear routes move issues to the level holding the authority to resolve them.
Question 38PMO setup and design
A PMO is drafting a service-level agreement with the business units it supports. Which content belongs in that agreement?
- The organization's marketing and communications calendar
- The chief executive's annual performance objectives
- The services, response times, quality criteria, and responsibilities of both parties Correct answer.
- The salary bands and bonus structure of PMO staff
Explanation
A service-level agreement records what is being delivered, to what standard and timeliness, and what each party must provide for that to happen. It is a mutual commitment about service, not a repository for HR or corporate planning data.
Question 39PMO setup and design
A PMO must decide which activities it performs itself and which it leaves to project teams. Which principle should guide that split?
- The PMO performs work needing enterprise-wide consistency or specialist skill, while teams own delivery work Correct answer.
- Project teams perform all work and the PMO only observes and records
- The PMO performs every activity so that all projects are handled identically
- The split is reviewed annually and set by the PMO's software vendor
Explanation
Activities that require cross-portfolio consistency or scarce specialist capability belong in the PMO, while delivery work stays with the teams closest to it. This principle keeps the PMO lean and prevents duplicated effort.
Question 40PMO setup and design
A PMO design team is choosing between launching all services at once and rolling them out in phases. Which consideration most strongly favors the phased approach?
- The organization's limited change capacity and the unproven quality of new services Correct answer.
- The number of staff who will work in the PMO office
- The availability of a large multi-year operating budget
- The desire for maximum visibility in the first quarter
Explanation
Phased rollout matches the pace of adoption to what the organization can absorb and lets each service be proven before the next is added. Launching everything simultaneously multiplies risk when capacity and service quality are not yet demonstrated.
Question 41PMO setup and design
Which design choice best positions a PMO to advise on resource capacity across the portfolio?
- Delegating all capacity decisions to individual project managers
- Tracking only the approved budget for each project
- Maintaining a consolidated view of resource supply, allocation, and demand Correct answer.
- Collecting timesheets quarterly for cost allocation
Explanation
Capacity advice depends on seeing supply, current commitments, and forward demand together, which is the only way to reveal conflicts between projects. Project-level or cost-only views cannot expose cross-portfolio contention for the same scarce people.
Question 42PMO setup and design
Which design element most directly builds organizational learning into a PMO?
- An annual stakeholder satisfaction survey
- A document library without a named owner
- A register of certified project managers
- A lessons-learned process with reviews at defined points and reuse in future planning Correct answer.
Explanation
Learning becomes part of the operating model when lessons are captured at defined points and deliberately applied to later planning and decision gates. Passive storage or periodic measurement rarely changes how future work is done.
Question 43PMO setup and design
An enterprise already runs a mature PMO for IT delivery and now wants to add an enterprise-wide PMO. Which design issue should be resolved first?
- The authority boundaries and interfaces between the two PMOs Correct answer.
- The number of governance meetings each PMO will hold
- Which branding and logo the combined PMO will use
- The physical office location of the enterprise PMO team
Explanation
Where two PMOs coexist, the greatest design risk is duplicated services, conflicting standards, and disputes over ownership. Defining boundaries and interfaces first prevents that overlap from becoming entrenched.
Question 44PMO setup and design
What should a PMO business case primarily establish?
- The list of projects the PMO will manage in year one
- The PMO's organizational chart and reporting lines
- The preferred software vendor and licence count
- The expected value, cost, and risk of the PMO with measurable outcomes Correct answer.
Explanation
A business case justifies the PMO as an investment by setting out the value it is expected to create, what it will cost, and the risks involved, expressed in measurable terms. Structural and procurement details are implementation choices that follow from the case.
Question 45PMO setup and design
How should a PMO design its governance services for teams that deliver with agile methods?
- Require full document-based stage gates for every increment
- Mandate a single delivery framework for the whole organization
- Remove all governance so that teams are entirely self-directing
- Tailor governance to lightweight flow-based checkpoints and offer services teams find valuable Correct answer.
Explanation
Agile delivery needs governance that fits iterative flow: light checkpoints, outcome-based reporting, and services that help teams rather than slow them. Both heavy documentation mandates and the absence of governance undermine the PMO's purpose.
Question 46PMO setup and design
A PMO is accountable for portfolio prioritization, but funding decisions sit entirely with finance. What is the most appropriate design response?
- Publish the prioritization rankings without engaging finance in the process
- Establish a documented decision-rights agreement that links PMO recommendations to the finance funding process Correct answer.
- Decline to perform prioritization until funding authority is transferred
- Escalate to the chief executive to transfer all budget authority to the PMO
Explanation
Where accountability and authority are split, the design fix is a documented agreement that connects the PMO's recommendations to the body that controls funding. Requesting total control, withdrawing, or acting unilaterally all damage the relationship and leave the gap unresolved.
Question 47PMO setup and design
A PMO's catalog lists 30 services, only six are used regularly, and quality is uneven across them. Which design decision is most sound?
- Outsource the entire catalog to an external provider
- Retain all services and reduce staffing to control cost
- Add further services so that every possible stakeholder need is covered
- Rationalize the catalog to the highest-value services and set quality standards before expanding again Correct answer.
Explanation
Breadth without quality erodes confidence, and each additional service consumes scarce PMO capacity. Narrowing to high-value services and stabilizing quality first creates the credibility needed to expand later.
Question 48PMO setup and design
A PMO's mandate is to improve delivery predictability, but business units are rewarded purely on speed to market. What design tension must the PMO address?
- Selecting a portfolio tool that reports speed metrics accurately
- Aligning PMO measures and business-unit incentives so that predictability is valued Correct answer.
- Mandating slower delivery so that quality is protected
- Ignoring the reward system and reporting predictability alone
Explanation
A PMO's measures only change behaviour when they connect to how the business is actually rewarded. Design must reconcile predictability goals with incentive structures, because reporting alone cannot overcome a conflicting reward system.
Question 49PMO setup and design
A PMO reports to the chief information officer, but most of the change in its portfolio is business-led. What is the most significant design risk arising from that reporting line?
- Overinvestment in portfolio management tooling
- Too many analyst roles reporting into the PMO
- Perceived bias toward IT and reduced credibility with business sponsors Correct answer.
- Excessive staffing levels within the PMO
Explanation
A PMO seen as an IT instrument loses credibility with the business sponsors whose change it governs, which undermines adoption and compliance. The design fix is usually shared or business-side sponsorship rather than a purely functional reporting line.
Question 50PMO setup and design
A new PMO is told its mandate is to ensure that all projects succeed. Which charter revision makes the mandate designable and measurable?
- Limit the PMO's remit to status reporting for senior management
- Define specific accountabilities, decision rights, and shared success measures with sponsors Correct answer.
- Commit the PMO to a target of zero project failures
- Adopt the mandate as written and request additional headcount to cover it
Explanation
An unbounded mandate has to be translated into named accountabilities, defined decision rights, and measures shared with sponsors and delivery leads before it can be designed against. Success is co-owned rather than something a PMO can guarantee.