PMI PMOCP study plan
PMI PMOCP · Give each week a clear focus.
8 weeks · About 6 hours per week
PMO setup and design
Distinguish the common PMO operating models (supportive, controlling, directive, enterprise, hybrid) by listing decision rights, reporting lines, and typical services for each
Draft a PMO charter stating mandate, in-scope and out-of-scope boundaries, funding model, and three success criteria for a mid-size organization
Map sponsor, governance board, delivery leaders, and functional heads onto an influence/interest grid and note the engagement implication for each quadrant
Select a PMO model for three contrasting organizational scenarios and justify each selection in two sentences using constraints
Your checkpoint
One-page PMO charter plus a five-row PMO operating-model comparison table with a justified selection for three scenarios
PMO setup and design & PMO assessment
Define a service catalog of eight PMO services and assign a service owner, primary customer, and service level to each
Construct a RACI matrix covering governance board, PMO lead, project managers, and functional managers across the eight services
Design the assessment approach by choosing a capability framework, defining a 1-5 scoring rubric with behavioral anchors, and listing data sources
Sequence a PMO implementation roadmap into 90-day, 6-month, and 12-month horizons with entry and exit conditions
Your checkpoint
Service catalog with an 8-service x 4-role RACI matrix and a phased 12-month implementation roadmap
PMO assessment
Write 25 assessment questions mapped to five capability areas: governance, delivery support, resource management, performance reporting, and benefits
Apply the assessment to a fictional organization, scoring each capability on the 1-5 scale with a one-line evidence note per score
Analyze the scorecard to isolate the five largest capability gaps and state a plausible root cause for each
Prioritize remediation actions on an impact-versus-effort 2x2 and sequence the top quartile
Your checkpoint
Completed assessment scorecard for a fictional organization plus a 10-item prioritized gap register with owners
PMO assessment & PMO management
Convert each priority gap into a change initiative with an owner, dependency, and target completion horizon
Compare chargeback, funded-center, and value-based funding models for PMO sustainability and select one for a stated context
Describe the recurring operational processes a PMO runs monthly and quarterly: demand intake, prioritization, reporting, and portfolio reviews
Complete a timed 60-question practice set on domains 1 and 2 and log a root cause for every missed item
Your checkpoint
Gap-to-roadmap conversion sheet plus a scored practice log with root-cause notes for every incorrect answer
PMO management
Define eight PMO performance indicators, each with formula, data source, target, and reporting frequency
Design a monthly portfolio review cadence including agenda, required inputs, pre-reads, and decision rights
Build a PMO staffing model covering roles, required competencies, and capacity allocation for a three-person team
Draft a stakeholder engagement plan with tailored messages and channels for the sponsor, delivery leads, and functional heads
Your checkpoint
KPI definition sheet with eight fully specified metrics and a one-page portfolio review agenda with decision rights
PMO management & PMO improvement and value orientation
Diagnose three stakeholder resistance scenarios and select a specific influence tactic and escalation path for each
Construct a benefits realization register linking each outcome to a metric, baseline, target, measurement owner, and review point
Evaluate PMO value through three lenses: delivery performance, stakeholder perception, and cost efficiency, and note the evidence each lens requires
Complete a timed 60-question practice set on domains 3 and 4 and summarize recurring error patterns
Your checkpoint
Benefits realization register with 10 benefits plus a domains 3-4 practice log and error-pattern summary
PMO improvement and value orientation
Design a PMO maturity improvement initiative with a baseline score, target score, initiative list, and a 90-day checkpoint
Build a business case for expanding one PMO service, covering cost, expected benefit, risk, and a go/no-go recommendation
Apply benefit mapping to trace three PMO services through to stated strategic objectives
Assemble the evidence set needed to counter a 'PMO is overhead' objection in an executive review
Your checkpoint
Two-page PMO value improvement proposal containing baseline, target, initiatives, business case, and success metrics
PMO setup and design & PMO assessment & PMO management & PMO improvement and value orientation
Consolidate the four domain summary sheets into a single exam-day reference of decision rules and definitions
Complete two full-length timed practice exams and record section-level scores
Rework every question missed across weeks 1-7 into a corrected concept note stating why the right answer is right
Rehearse scenario-question reasoning: extract the governing constraint, eliminate two options, and justify the survivor
Your checkpoint
Two full-length mock scores at or above 80% with a corrected concept note for every missed item across the whole plan
Milestones
Week 2: PMO charter, service catalog, and RACI matrix complete; can explain the trade-offs between PMO operating models without notes
Week 4: Timed 60-question practice on domains 1-2 scored at or above 70%, with every missed item traced to a root cause
Week 6: Domains 3-4 practice scored at or above 70% and a written list of your three weakest sub-topics with a remediation action for each
Week 8: Two full-length mocks at or above 80% overall with no single domain below 70%