- Continued business justification
- The principle that a PRINCE2 project must have a documented, valid reason to continue, reviewed at stage boundaries; if justification is lost, the project is stopped.
- Manage by exception
- A principle where authority is delegated within agreed tolerances for time, cost, scope, quality, risk and benefits; forecasts outside tolerance are escalated to the next management level.
- Focus on products
- A principle requiring the project to define and agree products, their quality criteria and product descriptions before work starts, so outputs are clear and measurable.
- Tailor to suit
- A principle requiring PRINCE2 to be adapted to the project's context-scale, complexity, risk, culture and governance-while all seven principles remain applied.
- Manage by stages
- A principle that divides the project into management stages for planning, monitoring and control; a minimum of two stages is required: initiation and the remaining project work.
- Learn from experience
- A principle that requires lessons to be sought, recorded, shared and acted upon throughout the project and across the organization, not only at closure.
- People element
- In PRINCE2 7, people is an integrated element recognizing that projects are delivered by people; it covers leadership, communication, motivation, team development, culture and conflict.
- Emotional intelligence
- The ability to recognize, understand and manage one's own emotions and those of others; components include self-awareness, self-regulation, motivation, empathy and social skills.
- Tuckman team stages
- A model of team development with stages forming, storming, norming, performing and adjourning; teams may move back and forth as membership or goals change.
- Thomas-Kilmann conflict modes
- Five conflict-handling approaches: competing, collaborating, compromising, avoiding and accommodating; each suits different situations depending on importance and relationship.
- Communication management approach
- A PRINCE2 document describing how the project will communicate with stakeholders, including purpose, audience, channels, timing, responsibilities and feedback mechanisms.
- Leadership versus management
- Leadership sets direction, aligns and inspires people; management plans, organizes, controls and coordinates resources to deliver agreed objectives within constraints.
- Business case practice
- A PRINCE2 practice that establishes and reviews the business justification; outputs include the business case and benefits management approach, reviewed at stage boundaries.
- Benefits management approach
- A PRINCE2 document defining how benefits will be measured, reported and reviewed after the project, including roles, timing and baseline measures.
- Organizing practice
- A PRINCE2 practice that defines the project management team structure, roles, responsibilities and relationships, including project board, project manager, assurance, support and change authority.
- Product-based planning
- A PRINCE2 planning technique using a product breakdown structure, product descriptions and a product flow diagram to define products and their dependencies before scheduling activities.
- Quality register
- A PRINCE2 record of quality activities and results, including planned quality controls, product acceptance and quality assurance actions, used to monitor quality throughout the project.
- Risk register
- A PRINCE2 record of identified risks, including cause, event, effect, probability, impact, proximity, risk owner, response and status, reviewed regularly.
- Issue register
- A PRINCE2 record of issues and changes, including type, severity, owner, status, actions and decisions; it supports issue and change control throughout the project.
- Starting up a Project
- The first PRINCE2 process; it creates the project brief, project approach and outline business case, appoints key roles and requests authorization to initiate the project.
- Directing a Project
- The PRINCE2 process for the project board; it authorizes initiation, the project, stage or exception plans, ad hoc direction and project closure.
- Initiating a Project
- The PRINCE2 process that establishes the project's baseline by creating the project initiation documentation, project plan, benefits management approach and controls.
- Controlling a Stage
- The PRINCE2 process where the project manager authorizes work packages, monitors progress, manages issues and risks, and reports to the project board.
- Managing Product Delivery
- The PRINCE2 process where the team manager accepts, executes and delivers work packages, ensuring products meet quality criteria and reporting progress.
- Managing a Stage Boundary
- The PRINCE2 process at stage end that prepares the next stage plan, updates the project plan and business case, and reports stage completion to the board.
- Closing a Project
- The PRINCE2 process that confirms product acceptance, hands over products, evaluates the project and recommends closure; it also covers premature closure.
- Tailoring
- Adapting PRINCE2's principles, practices, processes, roles and documents to the project's context while ensuring all seven principles are still applied.
- Project context
- The specific circumstances affecting tailoring, such as scale, complexity, risk, duration, team maturity, governance, regulation, commercial arrangements, geography and culture.
- Tailoring in PID
- The project initiation documentation records tailoring decisions, explaining how PRINCE2 elements will be applied, scaled or combined for the project.
- Small project tailoring
- In small projects, roles may be combined and documents simplified, but management stages, tolerances and the seven principles must still be applied.
- Agile with PRINCE2
- PRINCE2 can be tailored for agile delivery by using timeboxes, iterative product development and frequent reviews while retaining principles, governance and stage boundaries.
- Multi-organization project
- A project spanning several organizations requires clear role agreements, project board representation and supplier and customer responsibilities, often documented in contracts and the PID.