PRINCE2 Foundation (PRINCE2) key terms
PRINCE2 Foundation · Get comfortable with the vocabulary.
- Continued business justification
- Related: Business case, Manage by exception
The principle that a project must have a valid reason to exist before it starts, and that this reason must be reviewed and remain sound throughout; if it fails, the project is changed or stopped.
- Learn from experience
- Related: Lessons log, Lessons report
The principle that a project team should deliberately seek out lessons from previous work and from its own progress, then act on them instead of simply recording them.
- Defined roles and responsibilities
- Related: Project board, Project manager
The principle that a project needs an explicit, agreed structure showing who does what, with clear accountability and authority understood by everyone involved.
- Manage by stages
- Related: End stage report, Manage by exception
The principle of splitting the project into manageable chunks, each with its own plan and decision point, so that commitment grows only as detail and confidence grow.
- Manage by exception
- Related: Tolerance, Exception
The principle that a higher level sets boundaries for delegated work and intervenes only when those boundaries are forecast to be exceeded, freeing managers from constant reporting.
- Focus on products
- Related: Product description, Acceptance criteria
The principle that a project should first agree what outputs it will create and the quality they must meet, and only then decide the activities needed to create them.
- Tailor to suit the project environment
The principle that PRINCE2 must be adapted in depth, rigour and terminology to fit the project's size, complexity, risk, delivery approach and the organisation's existing ways of working.
- Stakeholder
- Related: Stakeholder engagement, Communication management approach
Any individual, group or organisation that can affect, be affected by, or reasonably perceive itself to be affected by the project, its outputs or its outcomes.
- Stakeholder engagement
- Related: Stakeholder, Communication management approach
The continuing work of identifying the people with an interest in the project, judging their influence and interest, and deciding how to involve and communicate with them.
- Communication management approach
- Related: Stakeholder engagement
A document setting out how the project will keep people informed: which audiences need which information, in what format, how often and who is responsible for sending it.
- Business case
- Related: Benefit, Continued business justification
The documented justification for the project, covering the reasons for it, expected benefits, costs, timescales and key risks, and reviewed at each stage boundary to confirm it still holds.
- Benefit
- Related: Outcome, Business case
A measurable improvement created by an outcome that one or more stakeholders judge to be an advantage; benefits are usually realised after the project has closed.
- Outcome
- Related: Benefit, Business case
The changed situation that results once the project's outputs are put to use by the organisation; the project influences it but does not fully control it.
- Project board
- Related: Executive, Senior user, Project manager
The group accountable for the project, made up of an executive, senior users and senior suppliers, which directs the work and takes the key decisions within its authority.
- Executive
- Related: Project board, Business case
The single person ultimately accountable for the project, who owns the business case, chairs the project board on behalf of the business and judges whether the project remains worthwhile.
- Senior user
- Related: Project board, Benefit
The project board role representing the people who will use or gain from the outputs; this person specifies user needs and later confirms that the expected benefits are achieved.
- Project manager
- Related: Project board, Tolerance
The person who runs the project day to day within the limits set by the project board, delivering the agreed products at the required quality and escalating when limits are threatened.
- Tolerance
- Related: Exception, Manage by exception
The amount of deviation allowed from a plan's target in time, cost, scope, quality, benefit or risk before the matter must be referred to the next level of management.
- Exception
- Related: Tolerance, Exception plan
A forecast that an agreed tolerance will be exceeded, which must be reported upwards so that the level above can decide how the project should respond.
- Risk
- Related: Risk register, Risk appetite
An uncertain event that, if it happens, will affect the project's objectives; it is described through its cause, the event itself and the effect it would have.
- Risk appetite
- Related: Risk, Risk register
The degree of uncertainty an organisation or individual is prepared to accept in pursuit of objectives, which guides how much risk is tolerated and how risks are handled.
- Risk register
- Related: Risk, Risk appetite
A working record of the project's risks, showing how each is assessed, who owns it and what response is planned, kept up to date as the project proceeds.
- Issue
- Related: Off-specification, Project manager
An event that has already happened, was not planned and needs management action; examples include a request for change, a problem, or a product forecast to fail its requirements.
- Off-specification
- Related: Issue, Product description
A situation where a product is expected not to meet one or more of its agreed requirements, which must be raised as an issue and handled through change control.
- Product description
- Related: Acceptance criteria, Quality control
A statement of what a product must be like: its purpose, composition, quality criteria, the method used to check quality, and who produces and approves it.
- Acceptance criteria
- Related: Product description
The measurable conditions a product must satisfy before the customer will accept it; for the whole project these are set out in the project product description.
- Quality control
- Related: Acceptance criteria, Product description
Checking that products actually meet their agreed quality criteria, for example through reviews, inspections or tests, and recording the outcome of each check.
- Project mandate
- Related: Project brief
The trigger that starts a project: a brief statement from the commissioning organisation giving enough information to justify doing initial start-up work.
- Project brief
- Related: Project mandate, Project initiation documentation (PID)
A document created while starting up the project that outlines purpose, scope, objectives and an initial business case, giving the basis for planning the initiation work.
- Project initiation documentation (PID)
- Related: Business case, Project brief
The collection of documents produced during initiation that sets out the project's rationale, governance, plans, controls and business case, and forms the basis for the board's authorisation.
- Directing a project
- Related: Project board, Tolerance
The project board's process for making decisions at key points: authorising initiation, authorising the project, each stage or exception plan, giving ad hoc direction, and authorising closure.
- Managing product delivery
- Related: Work package, Checkpoint report
The process in which the team manager accepts a work package, carries out the work, keeps progress visible and returns the finished products for approval.
- Work package
- Related: Managing product delivery, Product description
The description of a piece of work given to a team, covering the products to be produced, time, cost, tolerances, constraints and the reporting expected while the work runs.
- Checkpoint report
- Related: Work package, Highlight report
A regular report from the team manager to the project manager giving progress, status of the assigned work and any issues arising during the reporting period.
- Highlight report
- Related: Checkpoint report, Tolerance
A progress report from the project manager to the project board at agreed intervals, summarising stage status and flagging any forecast deviation from agreed tolerances.
- End stage report
- Related: Manage by stages
A report written at the close of a management stage that summarises performance so far and gives the project board what it needs to decide how to proceed.
- End project report
- Related: Business case, Closing a project
A report produced when the project is closed, reviewing performance against the plan and the business case and confirming whether the project's objectives were met.
- Lessons log
- Related: Learn from experience, Lessons report
A running record of lessons identified during the project, together with what should be done differently, used to improve the work as it continues.
- Lessons report
- Related: Lessons log, Learn from experience
A report produced at the end of a stage or of the project that summarises the lessons found and recommends improvements for future projects and the wider organisation.
- Closing a project
- Related: End project report, Lessons report
The process of confirming that products are accepted, reviewing benefits and lessons, and handing over ongoing responsibilities so the project can be ended in a controlled way.