HVAC System Fundamentals and Psychrometrics & Test Instruments, Calibration, and Measurement Uncertainty
Define dry-bulb, wet-bulb, dew point, humidity ratio, and enthalpy from memory, then sketch a psychrometric chart labeling each axis
Plot five air-state points on a psychrometric chart and compute sensible heat ratio and mixed-air condition for two of them
List the psychrometric processes (sensible heating/cooling, humidification, dehumidification, evaporative cooling) and match each to a coil or device type
Distinguish the instrument classes used in TAB work (anemometer types, manometers, hygrometers, tachometers) and state the measurement principle of each
Your checkpoint
A one-page psychrometric cheat sheet plus three worked mixed-air problems with answers checked to within 2 percent
Test Instruments, Calibration, and Measurement Uncertainty
Compute combined uncertainty for a differential-pressure airflow reading using instrument accuracy, resolution, and repeatability terms
Explain calibration traceability and identify which instruments require field verification versus factory calibration
Apply correction factors for air density, temperature, and barometric pressure to a velocity-pressure reading
Calculate a tolerance band for a measured airflow given the design value and instrument uncertainty
Your checkpoint
A spreadsheet uncertainty budget for three instruments showing combined and expanded uncertainty at 95 percent confidence
Air Flow Measurement and Balancing Procedures
Describe the traverse method for duct airflow and state minimum traverse point spacing and reading counts
Compute average velocity pressure from a pitot-tube traverse and convert it to cfm using area and density correction
Explain the proportional balancing method and sequence it step by step for a supply system with terminal boxes
Identify acceptable balancing tolerances for supply, return, exhaust, and outside air under common industry practice
Diagnose three common airflow problems (duct leakage, damper authority, fan curve shift) and state the field test that confirms each
Your checkpoint
A completed mock duct traverse worksheet with 16 readings, averaged velocity pressure, corrected cfm, and a pass/fail call against a stated tolerance
Air Flow Measurement and Balancing Procedures & Hydronic System Balancing and Pump/Fluid Measurement
Read a pump curve and system curve together and identify the operating point, then predict the shift when a balance valve is throttled
Explain the difference between balancing valves, circuit setters, and pressure-independent control valves and when each is used
Compute flow from a differential-pressure measurement across a known valve or orifice using its Cv or manufacturer curve
Describe the proportional hydronic balancing procedure for a multi-zone loop and the role of a differential-pressure bypass
Convert between gpm, head, and brake horsepower and check a pump reading against its curve
Your checkpoint
A hydronic balancing narrative for a three-zone loop with predicted valve settings, computed flows, and a pump operating-point comparison
Building Pressurization, Exhaust, and Ventilation Verification
Calculate building pressure differential from measured outside, return, and exhaust airflows and state whether the design intent is met
Explain the role of stairwell, elevator, and smoke-control pressurization and the verification tests used for each
Verify outside-air ventilation rates against design and describe how to confirm economizer and minimum-position damper operation
Identify exhaust-system verification steps including hood face velocity, capture velocity, and makeup air interaction
List the field measurements needed to document a building pressurization report
Your checkpoint
A mock pressurization and ventilation verification report for one floor showing measured flows, computed differential, and a compliance statement
Controls, DDC Interfaces, and System Verification
Trace a DDC control sequence for an air handler and identify the points a balancer must verify at each mode
Explain sensor types and calibration checks for temperature, pressure, and airflow transmitters used in control loops
Describe how to interface with a building automation system to trend points and confirm damper and valve positions
Diagnose control-related balancing failures such as hunting, minimum-position drift, and sensor offset, and state the corrective test
Your checkpoint
A trend-log analysis of a simulated AHU showing mode transitions, verified setpoints, and two documented control discrepancies with corrective actions
Reporting, Documentation, and Standards Compliance & Project Management, Safety, and Professional Ethics
Assemble a complete TAB report outline covering instrument list, calibration records, design versus measured values, and deficiency log
Apply the reporting and procedural requirements of the relevant industry standards to a sample project and note gaps
Draft a deficiency and punch-list entry that states the observed condition, the standard reference, and the required corrective action
Outline a site safety plan covering electrical, fall, confined-space, and rotating-equipment hazards for a TAB visit
Your checkpoint
A full mock TAB report with cover, instrument and calibration appendix, measured-versus-design tables, and a deficiency log
Project Management, Safety, and Professional Ethics & HVAC System Fundamentals and Psychrometrics & Test Instruments, Calibration, and Measurement Uncertainty & Air Flow Measurement and Balancing Procedures & Hydronic System Balancing and Pump/Fluid Measurement & Building Pressurization, Exhaust, and Ventilation Verification & Controls, DDC Interfaces, and System Verification & Reporting, Documentation, and Standards Compliance
Complete a timed 60-question mixed-domain practice set and score each domain separately
Review every missed item and write the underlying principle plus the correct method for each
Re-derive the psychrometric and uncertainty formulas from memory without notes
State the ethical obligations around reporting accuracy, conflict of interest, and data integrity in a TAB engagement
Your checkpoint
A scored practice exam with a domain-by-domain error log and a written remediation list for any domain below 70 percent
Milestones
Week 2: Score at least 80 percent on a 15-question psychrometrics and uncertainty self-quiz and produce a complete uncertainty budget
Week 4: Complete both the duct traverse worksheet and the hydronic balancing narrative with all computed values within stated tolerances
Week 6: Demonstrate correct DDC sequence tracing on two air handlers and document at least two control discrepancies with corrective tests
Week 8: Score at least 75 percent overall on the timed mixed-domain practice exam with no single domain below 70 percent