AACE CCP flashcards
AACE CCP · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Class 5 estimate
- AACE estimate class with 0% to 2% project definition, prepared for concept screening; expected accuracy is roughly -20% to -50% on the low side and +30% to +100% on the high side.
- PERT expected duration
- The three-point weighted average (O + 4M + P) / 6, where O is optimistic, M is most likely, and P is pessimistic; it approximates the mean of an activity duration distribution.
- Learning curve formula
- Y = aX^b, where Y is unit cost or hours, a is first-unit value, X is cumulative units, and b = log(learning rate)/log 2; an 80% curve gives b approximately -0.322.
- Cost-capacity factor
- C2 = C1 × (Q2/Q1)^n, used to scale plant or facility cost from a known capacity Q1 and cost C1 to a new capacity Q2 using exponent n.
- Contingency versus escalation
- Contingency covers known-unknown scope and estimating uncertainty within project scope; escalation covers anticipated price changes over time; management reserve covers unknown-unknowns outside the approved baseline.
- Bottom-up estimating
- An estimating method that builds total project cost from detailed work-package or activity-level estimates; it is usually more accurate but requires greater definition and effort than parametric or analogy methods.
- Factored estimating
- A capacity or ratio method that derives costs of supporting systems by multiplying the cost of major equipment by published or historical factors; accuracy depends on similarity of the reference project.
- Critical path
- The longest continuous path through a schedule network; it determines the shortest possible project duration, and its activities have zero total float when no constraints alter the calculation.
- Total float
- The amount of time an activity can be delayed without delaying the project finish date; it equals late start minus early start, or late finish minus early finish.
- Free float
- The time an activity can slip without delaying the early start of any successor; it equals the minimum successor early start minus the activity's early finish.
- Resource leveling
- A scheduling technique that adjusts activity start and finish dates, sometimes extending project duration, to resolve resource over-allocation or demand above available limits.
- Cost slope for crashing
- Cost slope = (crash cost - normal cost) / (normal duration - crash duration); it identifies the additional cost per unit of time saved by compressing an activity.
- Finish-to-start relationship
- A precedence relationship in which a successor activity cannot start until its predecessor finishes; it is the most common logical link in CPM schedules and may include a lag.
- Schedule baseline
- The approved version of the project schedule used to compare actual progress and performance; changes to it require formal integrated change control approval.
- Earned value (EV)
- The budgeted cost of work performed, also called BCWP; it quantifies completed work in the project's authorized budget currency and is a core input to cost and schedule performance indices.
- Cost variance (CV)
- CV = EV - AC; a positive value indicates work is under budget, while a negative value indicates work is over budget relative to the budgeted cost of completed work.
- Cost performance index
- CPI = EV / AC; values above 1.0 indicate favorable cost efficiency, values below 1.0 indicate unfavorable cost performance, and the index is used to forecast final cost.
- Schedule performance index
- SPI = EV / PV; values above 1.0 indicate ahead of schedule in earned-value terms, and values below 1.0 indicate behind schedule; it compares earned value with planned value.
- Estimate at completion
- EAC = AC + ETC; a common forecast is EAC = AC + (BAC - EV) / CPI, assuming remaining work continues at the current cost performance index.
- To-complete performance index
- TCPI = (BAC - EV) / (BAC - AC) when targeting the budget, or (EAC - EV) / (EAC - AC) when targeting a revised estimate; values above 1.0 require improved efficiency.
- Earned schedule
- A time-based extension of earned value that converts EV into the date or duration of corresponding planned work; SPI(t) = ES / actual time, and IEAC(t) = planned duration / SPI(t).
- Project triple constraint
- The interdependent objectives of scope, time, and cost, often with quality, that define project performance; changing one generally requires adjustment to at least one other.
- RACI matrix
- A responsibility assignment tool that labels stakeholders as Responsible, Accountable, Consulted, or Informed for tasks; each activity should have one accountable owner.
- Expected monetary value
- EMV = probability × impact for a risk event; it supports quantitative risk analysis by expressing uncertain outcomes in monetary terms and summing across the risk register.
- Communication channels
- The number of communication paths among n stakeholders is n(n - 1) / 2; adding stakeholders increases channel count rapidly and raises project communication complexity.
- Projectized organization
- An organizational structure in which project teams report primarily to project managers, who have high authority over resources and priorities; staff often move between projects after completion.
- Integrated change control
- A process for reviewing, approving, rejecting, and documenting changes to project baselines and deliverables, ensuring impacts on scope, schedule, cost, quality, and risk are assessed.
- Net present value
- NPV = sum of future cash flows discounted at a required rate minus initial investment; a positive NPV indicates the project is expected to add value at that discount rate.
- Internal rate of return
- The discount rate at which a project's NPV equals zero; a project is generally acceptable when its IRR exceeds the organization's required rate of return or hurdle rate.
- Break-even quantity
- Break-even quantity = fixed costs / (unit price - variable cost per unit); it is the sales volume at which total revenue equals total cost and profit is zero.
- Straight-line depreciation
- Annual depreciation = (asset cost - salvage value) / useful life; it allocates an equal depreciation expense to each year of the asset's service life.
- Benefit-cost ratio
- BCR = present value of benefits / present value of costs; a ratio greater than 1.0 indicates that discounted benefits exceed discounted costs for the evaluated alternative.