AACE CCP key terms
AACE CCP · Get comfortable with the vocabulary.
- Cost Estimate Classification System
- Related: Basis of Estimate, Contingency
AACE framework that groups estimates into five classes, from Class 5 (little project definition, widest accuracy range) to Class 1 (full definition, narrowest range), linking definition maturity to the estimating method used.
- Basis of Estimate
- Related: Cost Estimate Classification System, Escalation
Written record of how an estimate was developed: scope covered, assumptions, exclusions, pricing sources, method, and expected accuracy range, so reviewers can judge its reliability and later updates can be traced.
- Contingency
- Related: Management Reserve, Basis of Estimate
Money included in the estimate and budget to cover known risks and uncertainties inside the approved scope; it is drawn down as those risks are resolved and is not intended for scope changes.
- Escalation
- Related: Contingency
Provision in an estimate for expected rises in labor, material, and equipment prices between the estimate basis date and the time the cost will actually be incurred.
- Parametric Estimating
- Related: Unit Rate Estimating, Cost Estimate Classification System
Estimating method that derives cost from statistical relationships between historical cost and design parameters such as capacity, weight, or floor area, instead of pricing each work item individually.
- Quantity Takeoff
- Related: Unit Rate Estimating, Work Breakdown Structure
Systematic measurement of the materials and work items shown on drawings and specifications, producing the quantities to which unit costs are later applied.
- Unit Rate Estimating
- Related: Quantity Takeoff, Parametric Estimating
Building an estimate by multiplying measured quantities by unit costs for labor, material, and equipment, then adding indirect costs, markups, and contingency to reach total cost.
- Learning Curve
- Related: Unit Rate Estimating
Model in which labor hours per unit fall by a constant percentage each time cumulative production doubles, used to price repetitive work without overstating the cost of later units.
- Critical Path Method
- Related: Total Float, Forward Pass and Backward Pass
Network scheduling technique that calculates early and late dates for every activity and identifies the longest path through the network, which determines the shortest possible project duration.
- Total Float
- Related: Critical Path Method, Baseline Schedule
Time an activity can slip from its early dates without delaying project completion or violating a constraint; activities whose total float is zero lie on the critical path.
- Forward Pass and Backward Pass
- Related: Critical Path Method, Total Float
Two CPM calculations: the forward pass moves left to right assigning early start and finish dates; the backward pass moves right to left assigning late finish and start dates.
- Precedence Diagram Method
- Related: Critical Path Method, Lag and Lead
Network technique in which activities are drawn as nodes and connected by arrows representing finish-to-start, start-to-start, finish-to-finish, or start-to-finish relationships, sometimes carrying lags.
- Lag and Lead
- Related: Precedence Diagram Method
Lag is a required waiting period inserted between a predecessor and its successor; lead is the opposite, allowing a successor to start before its predecessor finishes.
- Baseline Schedule
- Related: Total Float, Change Control
The approved, time-phased plan against which actual progress and schedule performance are compared; it changes only through formal change control.
- Resource Leveling
- Related: Total Float, Baseline Schedule
Adjusting activity start and finish dates, often lengthening the schedule, so that demand for a limited resource never exceeds the supply available in any period.
- Schedule Risk Analysis
- Related: Critical Path Method, Contingency
Quantitative method, usually Monte Carlo simulation of activity durations and risks, that produces a probability distribution of completion dates instead of one deterministic finish date.
- Earned Value Management
- Related: Planned Value, Earned Value, Cost Performance Index
Method that integrates scope, schedule, and cost by comparing the budgeted value of work performed with the value planned and the money actually spent, all at a status date.
- Planned Value
- Related: Earned Value, Baseline Schedule
The authorized budget assigned to the work scheduled to be completed by the status date; it is the baseline against which earned value is compared.
- Earned Value
- Related: Planned Value, Actual Cost
The budgeted cost of work actually accomplished by the status date, usually calculated as physical percent complete multiplied by the budget for that work.
- Actual Cost
- Related: Earned Value, Cost Performance Index
The total money actually incurred in accomplishing the work performed by the status date, including direct and indirect charges but not commitments for work not yet done.
- Cost Performance Index
- Related: Schedule Performance Index, Estimate at Completion
Earned value divided by actual cost; a result below 1.0 means more has been spent than the work earned, so cost performance is unfavorable.
- Schedule Performance Index
- Related: Cost Performance Index, Planned Value
Earned value divided by planned value; a result below 1.0 means less work has been earned than was scheduled for the status date.
- Estimate at Completion
- Related: To-Complete Performance Index, Actual Cost
Forecast of total project cost, usually actual cost to date plus an estimate to complete; common formulas divide the budget at completion by the cost performance index.
- To-Complete Performance Index
- Related: Estimate at Completion, Cost Performance Index
The cost efficiency, earned value divided by cost, that all remaining work must achieve to finish within a stated budget target such as the original budget or the current forecast.
- Management Reserve
- Related: Contingency, Estimate at Completion
Budget held outside the project cost baseline for unanticipated work within scope but beyond the estimate's contingency; it is released only with management approval.
- Work Breakdown Structure
- Related: Control Account, Quantity Takeoff
Hierarchical breakdown of project scope into deliverables and work packages, providing the framework for estimating, scheduling, assigning responsibility, and measuring performance.
- Control Account
- Related: Work Breakdown Structure, Earned Value Management
A WBS management point where scope, budget, actual cost, and schedule are integrated and performance is measured, normally owned by a single accountable manager.
- Triple Constraint
- Related: Scope Creep, Change Control
The need to balance scope, schedule, cost, quality, and risk; changing any one of them normally requires adjusting at least one of the others.
- Change Control
- Related: Scope Creep, Baseline Schedule
Formal process for documenting, evaluating, approving or rejecting, and communicating changes to baselines so that modifications are authorized rather than absorbed silently.
- Scope Creep
- Related: Change Control, Triple Constraint
Uncontrolled growth of project scope without matching adjustments to time, cost, or resources, typically caused by unmanaged or informal change requests.
- Risk Register
- Related: Contingency, Management Reserve
Log of identified risks recording causes, probability, impact, response plans, owners, and current status, reviewed and updated throughout the life of the project.
- Net Present Value
- Related: Discount Rate, Internal Rate of Return
Sum of a project's future cash flows discounted to present value at a chosen rate, less the initial investment; a positive result means the project adds value at that rate.
- Internal Rate of Return
- Related: Net Present Value, Discount Rate
Discount rate at which a project's net present value equals zero; it is compared with the organization's required rate of return to judge whether the investment is worthwhile.
- Discount Rate
- Related: Net Present Value, Internal Rate of Return
Rate used to convert future cash flows into present value, often set at the minimum acceptable rate of return the organization requires for investments of similar risk.
- Payback Period
- Related: Net Present Value, Life Cycle Cost
Time needed for cumulative cash inflows to equal the initial investment; simple to apply but it ignores the time value of money and everything that happens after payback.
- Life Cycle Cost
- Related: Net Present Value, Payback Period
Total cost of acquiring, operating, maintaining, and disposing of an asset over its whole life, used to compare alternatives instead of looking only at capital cost.
- Sunk Cost
- Related: Life Cycle Cost, Net Present Value
Money already spent that cannot be recovered; it should be excluded from decisions about continuing, because only future costs and benefits are relevant.