AACE CCP study materials
AACE CCP study resources

AACE CCP key terms

AACE CCP · Get comfortable with the vocabulary.

Cost Estimate Classification System

AACE framework that groups estimates into five classes, from Class 5 (little project definition, widest accuracy range) to Class 1 (full definition, narrowest range), linking definition maturity to the estimating method used.

Related: Basis of Estimate, Contingency
Basis of Estimate

Written record of how an estimate was developed: scope covered, assumptions, exclusions, pricing sources, method, and expected accuracy range, so reviewers can judge its reliability and later updates can be traced.

Related: Cost Estimate Classification System, Escalation
Contingency

Money included in the estimate and budget to cover known risks and uncertainties inside the approved scope; it is drawn down as those risks are resolved and is not intended for scope changes.

Related: Management Reserve, Basis of Estimate
Escalation

Provision in an estimate for expected rises in labor, material, and equipment prices between the estimate basis date and the time the cost will actually be incurred.

Related: Contingency
Parametric Estimating

Estimating method that derives cost from statistical relationships between historical cost and design parameters such as capacity, weight, or floor area, instead of pricing each work item individually.

Related: Unit Rate Estimating, Cost Estimate Classification System
Quantity Takeoff

Systematic measurement of the materials and work items shown on drawings and specifications, producing the quantities to which unit costs are later applied.

Related: Unit Rate Estimating, Work Breakdown Structure
Unit Rate Estimating

Building an estimate by multiplying measured quantities by unit costs for labor, material, and equipment, then adding indirect costs, markups, and contingency to reach total cost.

Related: Quantity Takeoff, Parametric Estimating
Learning Curve

Model in which labor hours per unit fall by a constant percentage each time cumulative production doubles, used to price repetitive work without overstating the cost of later units.

Related: Unit Rate Estimating
Critical Path Method

Network scheduling technique that calculates early and late dates for every activity and identifies the longest path through the network, which determines the shortest possible project duration.

Related: Total Float, Forward Pass and Backward Pass
Total Float

Time an activity can slip from its early dates without delaying project completion or violating a constraint; activities whose total float is zero lie on the critical path.

Related: Critical Path Method, Baseline Schedule
Forward Pass and Backward Pass

Two CPM calculations: the forward pass moves left to right assigning early start and finish dates; the backward pass moves right to left assigning late finish and start dates.

Related: Critical Path Method, Total Float
Precedence Diagram Method

Network technique in which activities are drawn as nodes and connected by arrows representing finish-to-start, start-to-start, finish-to-finish, or start-to-finish relationships, sometimes carrying lags.

Related: Critical Path Method, Lag and Lead
Lag and Lead

Lag is a required waiting period inserted between a predecessor and its successor; lead is the opposite, allowing a successor to start before its predecessor finishes.

Related: Precedence Diagram Method
Baseline Schedule

The approved, time-phased plan against which actual progress and schedule performance are compared; it changes only through formal change control.

Related: Total Float, Change Control
Resource Leveling

Adjusting activity start and finish dates, often lengthening the schedule, so that demand for a limited resource never exceeds the supply available in any period.

Related: Total Float, Baseline Schedule
Schedule Risk Analysis

Quantitative method, usually Monte Carlo simulation of activity durations and risks, that produces a probability distribution of completion dates instead of one deterministic finish date.

Related: Critical Path Method, Contingency
Earned Value Management

Method that integrates scope, schedule, and cost by comparing the budgeted value of work performed with the value planned and the money actually spent, all at a status date.

Related: Planned Value, Earned Value, Cost Performance Index
Planned Value

The authorized budget assigned to the work scheduled to be completed by the status date; it is the baseline against which earned value is compared.

Related: Earned Value, Baseline Schedule
Earned Value

The budgeted cost of work actually accomplished by the status date, usually calculated as physical percent complete multiplied by the budget for that work.

Related: Planned Value, Actual Cost
Actual Cost

The total money actually incurred in accomplishing the work performed by the status date, including direct and indirect charges but not commitments for work not yet done.

Related: Earned Value, Cost Performance Index
Cost Performance Index

Earned value divided by actual cost; a result below 1.0 means more has been spent than the work earned, so cost performance is unfavorable.

Related: Schedule Performance Index, Estimate at Completion
Schedule Performance Index

Earned value divided by planned value; a result below 1.0 means less work has been earned than was scheduled for the status date.

Related: Cost Performance Index, Planned Value
Estimate at Completion

Forecast of total project cost, usually actual cost to date plus an estimate to complete; common formulas divide the budget at completion by the cost performance index.

Related: To-Complete Performance Index, Actual Cost
To-Complete Performance Index

The cost efficiency, earned value divided by cost, that all remaining work must achieve to finish within a stated budget target such as the original budget or the current forecast.

Related: Estimate at Completion, Cost Performance Index
Management Reserve

Budget held outside the project cost baseline for unanticipated work within scope but beyond the estimate's contingency; it is released only with management approval.

Related: Contingency, Estimate at Completion
Work Breakdown Structure

Hierarchical breakdown of project scope into deliverables and work packages, providing the framework for estimating, scheduling, assigning responsibility, and measuring performance.

Related: Control Account, Quantity Takeoff
Control Account

A WBS management point where scope, budget, actual cost, and schedule are integrated and performance is measured, normally owned by a single accountable manager.

Related: Work Breakdown Structure, Earned Value Management
Triple Constraint

The need to balance scope, schedule, cost, quality, and risk; changing any one of them normally requires adjusting at least one of the others.

Related: Scope Creep, Change Control
Change Control

Formal process for documenting, evaluating, approving or rejecting, and communicating changes to baselines so that modifications are authorized rather than absorbed silently.

Related: Scope Creep, Baseline Schedule
Scope Creep

Uncontrolled growth of project scope without matching adjustments to time, cost, or resources, typically caused by unmanaged or informal change requests.

Related: Change Control, Triple Constraint
Risk Register

Log of identified risks recording causes, probability, impact, response plans, owners, and current status, reviewed and updated throughout the life of the project.

Related: Contingency, Management Reserve
Net Present Value

Sum of a project's future cash flows discounted to present value at a chosen rate, less the initial investment; a positive result means the project adds value at that rate.

Related: Discount Rate, Internal Rate of Return
Internal Rate of Return

Discount rate at which a project's net present value equals zero; it is compared with the organization's required rate of return to judge whether the investment is worthwhile.

Related: Net Present Value, Discount Rate
Discount Rate

Rate used to convert future cash flows into present value, often set at the minimum acceptable rate of return the organization requires for investments of similar risk.

Related: Net Present Value, Internal Rate of Return
Payback Period

Time needed for cumulative cash inflows to equal the initial investment; simple to apply but it ignores the time value of money and everything that happens after payback.

Related: Net Present Value, Life Cycle Cost
Life Cycle Cost

Total cost of acquiring, operating, maintaining, and disposing of an asset over its whole life, used to compare alternatives instead of looking only at capital cost.

Related: Net Present Value, Payback Period
Sunk Cost

Money already spent that cannot be recovered; it should be excluded from decisions about continuing, because only future costs and benefits are relevant.

Related: Life Cycle Cost, Net Present Value