Earned Value With a One-Time Insurance Claim

AACE CCT · Put your knowledge to work in context.

All case studies

Earned Value With a One-Time Insurance Claim

At the end of month 6 of a 12-month, $12.0M fixed-price automation project: PV = $6.00M, EV = $5.10M, AC = $5.70M. The cost ledger shows $0.40M of AC attributable to rework of a control panel damaged in transit; the panel has been rebuilt, the rework is not in the baseline, and the insurer has accepted the claim in principle but has not yet paid. The project manager reports CPI 0.89 and states the project will finish at $13.4M. Client milestone dates are contractually fixed. The schedule still shows 12 months overall, with 8 months of work remaining on the critical path.

1. Compute CPI, SPI, CV and SV, and evaluate the PM's EAC. Should the rework cost be in the forecast?

Read the worked answer

Basic indices

  • CPI = EV/AC = 5.10/5.70 = 0.895
  • SPI = EV/PV = 5.10/6.00 = 0.850
  • CV = EV − AC = −$0.60M
  • SV = EV − PV = −$0.90M

The PM's EAC. BAC/CPI = 12.0/0.895 = $13.41M. The arithmetic is right; the input is contaminated.

The $0.40M of rework. It is in AC but not in the baseline and not the contractor's fault. Leaving it in CPI computes a performance index that includes a one-time event as if it were a recurring productivity trend. Strip it: adjusted AC = $5.30M, adjusted CPI = 5.10/5.30 = 0.962.

Then decide what happens to the $0.40M.

  • If the insurer pays in full, it is a receivable, not a cost overrun: exclude from the forecast entirely and carry it on the balance sheet.
  • If recovery is partial or uncertain, carry the unrecovered portion as a discrete forecast item on top of the performance-based estimate - do not let it distort CPI.

Forecast with the adjusted index: EAC = 5.70 + (12.00 − 5.10)/0.962 = $12.87M including the rework already spent, or about $12.47M excluding it, less any insurance recovery.

2. The PM's EAC is one of several defensible ones. Which would you choose and why? Also forecast the completion date using earned schedule, stating your assumptions.

Read the worked answer

Choosing an EAC. The candidates:

  • BAC/CPI = $13.41M - assumes the cost variance is permanent and repeats. Reasonable default, but it ignores the schedule variance and treats a one-off as recurring.
  • Composite: AC + (BAC − EV)/(CPI × SPI) = 5.70 + 6.90/0.760 = $14.77M - assumes cost and schedule variance are both permanent. Appropriate when the schedule slip is driving the cost growth (rework, overtime, extended supervision).
  • Adjusted-CPI EAC ≈ $12.5–12.9M - removes the one-time event.

Selection logic, not formula recall. Look at why the schedule and cost variance exist. Here the SPI of 0.85 is partly procurement front-loading and partly the panel event. If the delay is genuinely driving indirect cost growth, the composite EAC is right despite looking punitive. If the schedule variance is a measurement artifact, use the adjusted CPI. Justify it with evidence - the cost ledger by account, not the summary index.

Earned schedule (linear approximation). ES = 6 × (5.10/6.00) = 5.1 months; AT = 6; SPI(t) = 5.1/6 = 0.85; independent EAC(t) = PD/SPI(t) = 12.0/0.85 = 14.1 months, i.e. roughly 2 months late.

Assumption to state: linear PV, which is often wrong on a project with front-loaded procurement - the true ES is found by interpolating the PV curve. Report the interval as well as the point.

3. What leading indicators would you put in front of the client for the next three months, and what corrective action follows?

Read the worked answer

Leading indicators

  • Budgeted cost of work remaining (BCWR) and its burn rate against the remaining plan, by discipline.
  • Float consumption on the critical and near-critical paths - this is the earliest schedule warning.
  • Open RFIs, change orders and submittals ageing, plus their committed schedule impact.
  • Rework hours as a percentage of total hours - directly relevant here.
  • Procurement: vendor schedule performance on the automation hardware, where EVM lags reality by weeks.
  • Staffing versus plan, and overtime percentage as an early cost-growth signal.

Corrective actions

  1. Resolve the insurance claim on a date certain; carry it as a receivable with a defined owner inside the team.
  2. Recover the critical path by re-sequencing commissioning and testing and by adding a second shift at the panel integration stage.
  3. Separate owner-caused delay from contractor-caused delay and start the notice trail now, before the milestone dates are missed.
  4. Reset the EAC once, with a documented basis, and stop re-forecasting monthly - repeated small revisions destroy the forecast's credibility.
  5. Re-baseline only if the client approves a scope or date change; otherwise keep measuring against the contract baseline.