AACE CCT study materials
AACE CCT study resources

AACE CCT flashcards

AACE CCT · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Contingency
Reserve within the project estimate base that covers known risks and uncertainties inside approved scope; it is drawn down as risks retire and excludes escalation and management reserve.
Management reserve
Funds held outside the project cost baseline for unknown-unknowns and unapproved scope changes; spending requires management authorization and it is not part of the estimate for planned work.
Six-tenths rule
Capacity scaling formula C2 = C1 × (Q2/Q1)^0.6 used for order-of-magnitude equipment or plant estimates; valid only over moderate capacity ranges and when the exponent is validated from actual data.
Learning curve formula
Unit cost model Tn = T1 × n^b where b = log(learning rate)/log 2; an 80% curve gives b ≈ −0.322 and represents improving repetitive labor productivity.
Bottom-up estimating
Method that builds total cost by aggregating detailed work-package estimates of quantities, hours and rates; the most accurate and most labor-intensive technique, typical of definitive estimates.
AACE estimate class
Rating from Class 5 (order of magnitude, 0–2% definition) to Class 1 (definitive, 65–100% definition) assigned by end usage and definition maturity, not by estimating methodology.
Escalation
Projected increase in price levels applied to base-date costs using cost indices; it addresses inflation, not scope uncertainty, and is kept separate from contingency.
Parametric estimating
Model that estimates cost from statistical relationships between historical costs and drivers such as capacity, weight or throughput; suited to early phases with limited design detail.
Total float
Time an activity can slip without delaying the project finish; equals LS − ES or LF − EF, and the critical path carries the least total float, normally zero.
Free float
Time an activity can slip without delaying any successor's early start; equals the earliest successor ES minus the activity's early finish.
Forward pass
CPM calculation establishing each activity's earliest start and finish, moving from project start to finish and taking the maximum predecessor early finish.
PERT expected duration
Three-point weighted average (O + 4M + P)/6 giving expected activity duration; the standard deviation is (P − O)/6, used for probabilistic schedule risk.
Critical path
Longest dependent chain through the network; it defines the shortest possible project duration and has zero, or the least, total float.
Resource leveling
Rescheduling within float to flatten resource demand; where float is insufficient it extends project duration and can move the critical path.
Duration formula
Activity duration = quantity of work ÷ (productivity per resource × number of resources); changing crew size changes the duration in this relationship.
Schedule baseline
Approved time-phased schedule against which progress and float consumption are measured; only formally approved changes may modify it.
Cost Performance Index
CPI = EV ÷ AC. Values below 1.0 mean cost overrun relative to work earned; above 1.0 means work earned cost less than budgeted.
Schedule Performance Index
SPI = EV ÷ PV. Values below 1.0 indicate work is behind plan; cost-based SPI converges to 1.0 at completion, so it is unreliable for forecasting.
Estimate at completion
Forecast of total project cost; the common formula BAC ÷ CPI assumes current cost efficiency continues, while AC plus a bottom-up ETC is used when variances are atypical.
To-complete performance index
TCPI = (BAC − EV) ÷ (BAC − AC); above 1.0 means the remaining work must be performed more efficiently than has been achieved to date.
Earned value
Budgeted cost of work performed, EV = budgeted cost × physical percent complete; combined with PV and AC it produces variances and performance indices.
Cost variance
CV = EV − AC. A negative result is a cost overrun; variance is stated in currency units, while CPI expresses the same relationship as a ratio.
50/50 earning rule
Fixed-formula progress rule crediting 50% of an activity's budget at start and the remainder at finish; suited to short-duration tasks.
Variance threshold
Predefined limit that triggers investigation or a corrective action plan when cost or schedule variance exceeds it, supporting management by exception.
Net present value
Sum of future cash flows discounted at the required rate minus the initial investment; a positive NPV means the project adds value at that discount rate.
Internal rate of return
Discount rate that makes a project's NPV equal to zero; compared against the hurdle rate or cost of capital, a higher IRR is preferred.
Payback period
Time for cumulative cash inflows to recover the initial investment; it ignores cash flows after payback and, unless discounted, the time value of money.
Break-even quantity
Units needed for revenue to equal total cost: fixed costs divided by unit contribution margin, where margin is unit price minus unit variable cost.
Markup versus margin
Markup is a percentage of cost added to set price, while margin is a percentage of price; margin = markup ÷ (1 + markup).
Sunk cost
Money already spent and unrecoverable by any future action; it must be excluded when evaluating incremental cash flows between alternatives.
Direct versus indirect cost
Direct costs are traceable to a specific deliverable; indirect costs such as overhead and supervision are allocated across work using a defined basis.
Benefit-cost ratio
Present value of benefits divided by present value of costs; a ratio greater than 1.0 indicates benefits exceed costs at the chosen discount rate.