A $8.5M Fixed-Price Bid With Retention, LDs and a Competing Job

AACE CCT · Put your knowledge to work in context.

All case studies

A $8.5M Fixed-Price Bid With Retention, LDs and a Competing Job

A contractor is invited to bid an $8.5M, 14-month fixed-price contract. Estimated direct and indirect cost is $7.60M. Terms: 5% retention released 12 months after acceptance; monthly progress payments 45 days after invoice; 10% performance bond priced at 1.2% of contract value per year; liquidated damages of 0.5% of contract value per week, capped at 10%. Mobilization in month 1 consumes $1.2M of cost against $0.5M of billing. The contractor's weighted average cost of capital is 9%. A second opportunity - a $3.0M cost-plus job with a 9% fee - would occupy the same site crew in months 1 through 6.

1. Compute the expected gross margin and the peak cash requirement. Estimate the financing cost of the payment terms.

Read the worked answer

Margin

  • Price $8.50M − cost $7.60M = $0.90M
  • On price: 10.6%; on cost: 11.8%

Cash timing

  • Month 1: $1.20M cost against $0.50M billing → $0.70M out of pocket before the first invoice is even issued.
  • 45-day terms mean month 1 billing lands in month 3. With a 45-day lag on roughly $0.55M/month of revenue, receivables hover near $0.85M.
  • Retention accrues at 5% of billings, peaking near $0.43M, held until 12 months after acceptance.
  • Peak working capital: roughly $1.3M–$1.5M.

Financing cost at 9%

  • Mobilization/receivables gap: ~$1.1M average × 9% × 4/12 ≈ $33k
  • Retention: $430k × 9% × ~1.2 years ≈ $46k
  • Performance bond: $850k bonded × 1.2%/yr × 14/12 ≈ $12k
  • Total carry ≈ $90k, about 10% of the gross margin.

Read it honestly. A 10.6% gross margin that loses a tenth of itself to carry is a ~9.5% job before any risk reserve - and none of that reserve exists yet.

2. How should the LD cap and the retention be reflected in the bid? Quantify the exposure.

Read the worked answer

LD exposure. 0.5% of $8.5M per week = $42,500/week; the 10% cap is reached at 20 weeks and equals $850,000. That is 94% of the entire gross margin. In plain terms: the job is one roughly 20-week delay from a break-even outcome, and the risk is concentrated in whatever drives the critical path - design approvals, long-lead automation equipment, site access.

Retention exposure. Up to $425,000 locked up for a year past acceptance, with counterparty risk on the client for that period. It is not a cost so much as capital and credit risk.

How to reflect it in the bid

  1. Price a risk reserve, sized from a schedule risk analysis of the LD drivers, not from a gut percentage. If a P80 schedule puts completion 6 weeks out, the expected LD is ~$255k and it must appear in the price or in a contingency the company holds.
  2. Qualify the bid. Bid the LD regime you can accept - a lower weekly rate, a later cap trigger, or carve-outs for client-caused delay, force majeure and owner-furnished equipment.
  3. Negotiate the retention, not the price: reduction to 2.5% at 50% completion and release at acceptance instead of 12 months later is often easier to win than a higher price, and it is worth ~$25k in carry.

3. Bid, no-bid, or bid with conditions? Bring the cost-plus opportunity and cash flow into the recommendation.

Read the worked answer

Compare the two jobs on risk-adjusted contribution, not headline margin

  • Fixed price: $0.90M gross, less ~$90k carry, less a risk reserve that could approach the full margin if the 20-week LD cap is breached.
  • Cost-plus: $3.0M × 9% = $270k fee, no LD, no retention, monthly cost recovery - low risk, low carry, and it keeps the crew utilised in months 1–6.

The two are not mutually exclusive, and that is the point. The cost-plus job uses the crew for six months; the fixed-price job's critical work starts with mobilization. If the schedule can be sequenced so the cost-plus work runs in the first six months and the fixed-price scope front-loads engineering and procurement rather than field labour, both can be taken. If it truly is either/or, the $270k fee plus zero LD risk may beat a $900k margin carrying $850k of LD exposure.

If you bid the fixed-price job, do it with conditions:

  1. Notice provisions and time-extension entitlement drafted tightly - a time bar you cannot meet is worse than no clause.
  2. Front-load the schedule of values within contract limits so mobilization is recovered in month 1 rather than month 3. Legitimate, but it must be transparent and approved, not hidden.
  3. Secure payment security - parent guarantee, letter of credit or prompt-payment legislation - given the retention period.

Recommendation: bid with qualifications and a priced risk reserve, take the cost-plus job for the crew, and walk away only if the client refuses to move on either the LD cap or the retention release.