AACE CFCC Certified Forensic Claims Consultant flashcards
AACE CFCC Certified Forensic Claims Consultant · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Forensic schedule analysis
- A systematic comparison of planned versus actual performance using CPM logic to identify, measure, and apportion delay events and their effect on project completion.
- As-planned versus as-built
- A delay analysis method comparing the baseline schedule to the actual schedule to determine net delay, though it does not isolate individual event causation without further steps.
- Time impact analysis
- A prospective method inserting a delay event into the contemporaneous schedule at the point of occurrence and measuring the resulting change to completion.
- Window analysis
- A contemporaneous, period-by-period delay method that updates the schedule in windows and attributes delay within each window to specific events.
- Critical path
- The longest continuous chain of dependent activities through a network; any delay on this path extends project completion unless float is available.
- Total float
- The amount of time an activity can be delayed without delaying project completion; consumption of float affects entitlement to time extensions.
- Concurrent delay
- Two or more independent delay events occurring in the same period, each affecting the critical path, generally barring time-related cost recovery for that period.
- Pacing delay
- A deliberate slowdown by one party to match an existing delay caused by another, often raised as a defense against a delay claim.
- Total cost method
- A quantum method computing the difference between actual and bid cost; disfavored and admissible only when four strict conditions of impracticability and reasonableness are met.
- Modified total cost method
- An adjustment to the total cost method that deducts contractor-caused cost overruns and other non-compensable amounts before computing the claim.
- Measured-mile method
- A productivity analysis comparing bid or baseline production rates to actual rates over comparable work units to isolate owner-caused inefficiency.
- Disruption versus delay
- Disruption is lost productivity that raises unit costs without necessarily extending completion; delay is time impact on the critical path extending completion.
- Lost productivity claim
- A claim for increased labor or equipment cost per unit of work caused by interference, stacking of trades, or out-of-sequence work.
- Contemporaneous records
- Daily reports, cost ledgers, and correspondence created at the time of the event; the most reliable and persuasive evidence in forensic analysis.
- Cause and effect analysis
- The forensic process linking a specific event to a specific schedule or cost impact through documented logic, not mere correlation.
- Quantum
- The monetary or time value of a proven claim, established with reasonable certainty through records and accepted cost methods.
- Claim entitlement
- The contractual or legal basis giving the claimant the right to relief, independent of the amount of damages or delay suffered.
- Notice provision
- A contract clause requiring written notice of a claim within a stated period; often a condition precedent whose breach can bar the claim.
- Condition precedent
- A contractual requirement that must be satisfied before a right arises, such as timely notice before a claim becomes enforceable.
- Constructive change
- Work ordered or compelled by owner conduct without a formal change order, giving the contractor a right to equitable adjustment.
- Differing site conditions
- Physical conditions materially differing from contract documents (Type I) or from what reasonable investigation would reveal (Type II), entitling adjustment with notice.
- Suspension of work
- A temporary stoppage ordered by the owner; the contractor may recover time and costs but generally not profit on the suspended work.
- Termination for convenience
- Owner termination without contractor fault; the contractor recovers costs incurred plus reasonable profit on performed work, not anticipatory profit.
- Termination for default
- Termination due to contractor failure; the owner may recover excess reprocurement costs, and the contractor bears the burden of proving the default was excused.
- Acceleration
- Compressing performance to finish earlier than the adjusted schedule; may be actual (directed) or constructive (caused by owner-caused delay).
- Constructive acceleration
- When the owner refuses a justified time extension but requires completion on the original date, entitling the contractor to acceleration costs.
- Mediation
- A non-binding facilitated negotiation in which a neutral helps parties reach settlement; the mediator does not impose a decision.
- Arbitration
- A binding private adjudication by a neutral panel; awards are final with very limited judicial review on grounds like fraud or exceeding authority.
- Burden of proof
- The obligation of the claimant to establish entitlement, causation, and quantum by a preponderance of the evidence; unproven amounts are disallowed.
- Limitations period
- The contractual or statutory deadline for filing a claim, typically running from when the claimant knew or should have known of the event.
- Equitable adjustment
- A contract price or time adjustment restoring the contractor to the position it would have occupied absent the changed condition, without windfall.
- Dispute resolution ladder
- A contractual escalation sequence such as negotiation, mediation, adjudication, then arbitration or litigation, each with defined timing and cost.