AACE CFCC Certified Forensic Claims Consultant study materials
AACE CFCC Certified Forensic Claims Consultant study resources

AACE CFCC Certified Forensic Claims Consultant: Claims and Dispute Resolution: Entitlement, Process, and Forum

AACE CFCC Certified Forensic Claims Consultant · Work through your exam, one topic at a time.

All guide sections

Claims and Dispute Resolution: Entitlement, Process, and Forum

The claims lifecycle

A claim moves through notice, presentation, negotiation, and formal dispute resolution. Each stage has contractual and procedural gates that questions frequently test.

Concepts to master

  • Notice and time-bar provisions: strict deadlines for notifying delay or change events. Failure can extinguish entitlement even where the event is proven. Distinguish conditions precedent from mere administrative requirements.
  • Claim presentation: content requirements (basis, causation, quantum, supporting records) and the difference between a claim and an application for payment or variation instruction.
  • Entitlement sources: contract clauses (variations, force majeure, suspension, termination), common law (frustration, misrepresentation), and statutory regimes. Know that entitlement is contract-first.
  • Dispute resolution ladder: engineer's determination or DAB/DB, then amicable settlement period, then arbitration or litigation. Step-skipping is a classic trap.
  • Arbitration vs. litigation: enforceability of awards (New York Convention), confidentiality, party-appointed tribunals, and limited appeal rights versus the broader appeal routes in litigation.
  • Alternative processes: mediation, conciliation, expert determination, adjudication (statutory, interim-binding), and dispute boards. Know which outcomes bind temporarily versus finally.
  • Settlement and without-prejudice privilege: offers, reservations of rights, and the inadmissibility of settlement negotiations.

Traps

Options that treat the engineer's determination as final and binding regardless of contract wording; that assume arbitration is always cheaper or always appealable; or that ignore a lapsed notice period because the underlying facts favor the claimant.

Rule of thumb

Follow the ladder in the contract's own order. Before advising a forum, map every rung: notice → determination → amicable period → arbitration/litigation. A missed rung can make a valid claim unenforceable.

Worked example: A contractor with a strong 60-day delay claim missed a 28-day notice deadline. Entitlement is likely barred despite provable causation - the notice condition precedent governs, not the merits.