AACE DRMP flashcards
AACE DRMP · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Expected Monetary Value
- EMV is the probability-weighted sum of all possible outcomes of an uncertain event. Compare alternatives by choosing the highest EMV when the decision-maker is risk-neutral.
- Decision tree node shapes
- In a decision tree, squares mark decision nodes where the team chooses among alternatives; circles mark chance nodes where probabilities apply; terminal branches carry payoff values.
- Expected Value of Perfect Information
- EVPI equals the expected value with perfect information minus the expected value of the best alternative without it. It is the maximum amount worth paying to remove uncertainty.
- Expected Value of Sample Information
- EVSI equals the expected value with imperfect test or survey information minus the expected value without it. Information should be gathered only when its cost is below EVSI.
- Risk-averse utility curve
- A concave utility function in which each additional unit of money adds less utility. The decision-maker prefers a certain sum to a gamble of equal expected value.
- Certainty equivalent
- The guaranteed amount that a decision-maker values equally to a risky gamble. The risk premium equals the gamble's EMV minus this certainty equivalent.
- Sunk cost rule
- Money already spent cannot be recovered and must be excluded from a decision. Only incremental future costs and benefits of each alternative belong in the comparison.
- Framing bias
- Choices shift depending on whether outcomes are described as gains or as losses. Losses usually loom larger, so the same alternative can look attractive or unattractive purely from presentation.
- Anchoring bias
- Over-reliance on an initial number, such as a first estimate or a prior bid, when making later judgments. Subsequent estimates stay too close to the anchor even when it is arbitrary.
- Analytic Hierarchy Process
- A multi-criteria method that compares criteria and alternatives in pairs on a 1-to-9 ratio scale, derives weights from the comparison matrix, and ranks alternatives by weighted score.
- Consistency ratio threshold
- The consistency ratio measures how far a pairwise comparison matrix departs from perfect consistency. A value of 0.10 or less is generally accepted; higher values require revised judgments.
- One-at-a-time sensitivity analysis
- Vary one input while holding the others at base case to see whether the preferred alternative changes. The break-even value marks the point where the decision reverses.
- Tornado diagram
- A horizontal bar chart ranking uncertain variables by how much the outcome swings between their low and high values. The widest bar identifies the most influential driver.
- Decision tree rollback
- The fold-back procedure solves a tree from right to left: each chance node is replaced by its EMV and each decision node by its best branch, until the root value is obtained.
- Dominated alternative
- An option that performs no better than another on every criterion and is worse on at least one. It can be eliminated before scoring, saving effort and simplifying the choice.
- Weighted scoring model
- Normalize each alternative's score to a common scale, multiply by criterion weights that sum to 1.0, and add. The highest total identifies the preferred alternative in multi-criteria decisions.
- Risk register
- A living log of identified risks recording ID, cause, event, potential effect, probability, impact, score, owner, planned response, and residual rating. It is reviewed and updated throughout the project.
- Risk breakdown structure
- A hierarchical grouping of risk sources such as technical, external, organizational, and project management categories. It supports systematic identification and shows where exposure concentrates.
- Probability-impact matrix
- A grid plotting likelihood against impact using defined scales, usually five by five. Each cell yields a risk score that ranks threats for response priority.
- Risk appetite
- The amount of risk an organization is willing to accept in pursuit of its objectives, stated as a broad directional preference rather than a precise numeric limit.
- Risk tolerance
- The practical range of deviation from objectives that an organization can absorb within a given risk category. It translates broad appetite into measurable limits for specific project areas.
- Risk threshold
- A specific quantitative limit at which a risk becomes unacceptable and a response must be triggered. Thresholds sit inside tolerance bands and are written into project plans.
- Threat response: avoid
- Change the plan to eliminate the threat entirely, for example by dropping a scope element, using proven technology, or relocating a facility. Avoidance removes both the risk and its potential gain.
- Threat response: transfer
- Shift the financial consequence of a threat to a third party through insurance, bonds, warranties, or fixed-price contracts. The risk event can still occur; ownership of the impact moves.
- Threat response: mitigate
- Reduce the probability or impact of a threat to an acceptable level, for instance through prototyping, added inspections, or extra stock. Residual risk remains and must be tracked.
- Threat response: accept
- Acknowledge the risk and take no action beyond monitoring, appropriate when exposure is below tolerance or response cost exceeds benefit. Active acceptance sets aside a contingency reserve.
- Contingency reserve
- Budget or time set aside for identified risks that have been accepted or mitigated. It sits inside the cost or schedule baseline and is managed by the project manager.
- Management reserve
- Funds held outside the baseline for unidentified risks and unforeseen scope changes. Release usually requires sponsor or management approval because it changes the authorized baseline.
- Residual risk
- The exposure that remains after a response has been implemented. It must be assessed and recorded, because some risk usually persists even after strong mitigation.
- Secondary risk
- A new risk created by the response itself, such as a fixed-price contract that pushes a supplier toward quality shortcuts. Secondary risks are analyzed like any other risk.
- PERT three-point estimate
- Expected value equals optimistic plus four times most likely plus pessimistic, all divided by six. Standard deviation equals pessimistic minus optimistic, divided by six.
- Monte Carlo simulation
- Iteratively samples probability distributions for cost or schedule elements to produce a distribution of total outcomes. Outputs include confidence levels, contingency for a target probability, and sensitivity rankings.