- Air Barrier System
- Related: Air Leakage, Continuity, Pressure Boundary
The continuous combination of materials, components, and seals that together resist air leakage through the building enclosure, including joints and transitions between different materials.
- Air Leakage
- Related: Air Barrier System, Stack Effect
Unintended movement of air through gaps, cracks, and porous paths in the building enclosure, driven by pressure differences and carrying heat and moisture with it.
- Stack Effect
- Related: Infiltration, Pressure Boundary
Upward air movement caused by indoor air being warmer and lighter than outdoor air, producing positive pressure high in the building and negative pressure near the bottom.
- Infiltration
- Related: Exfiltration, Stack Effect
Outdoor air entering a building through unintentional openings, typically driven by wind, stack effect, or mechanical imbalance, and often carrying moisture and pollutants indoors.
- Exfiltration
- Related: Infiltration, Air Leakage
Indoor air escaping outward through unintentional openings in the enclosure, which can push warm moist air into wall cavities where it may condense.
- Pressure Boundary
- Related: Air Barrier System, Continuity
The defined plane or surface separating conditioned from unconditioned space that the air barrier system is meant to establish and maintain around the enclosure.
- Continuity
- Related: Transition Membrane, Penetration Seal
The requirement that air barrier materials connect without gaps across walls, roofs, floors, penetrations, and joints so the assembly performs as one sealed envelope.
- Air Permeance
- Related: ASTM E2178
A measure of how much air passes through a unit area of a material at a stated pressure difference, usually reported in liters per second per square meter.
- Vapor Retarder
- Related: Air Barrier System
A material that limits how much water vapor diffuses through an assembly, helping keep moisture from condensing inside walls, roofs, and floors.
- Self-Adhered Membrane
- Related: Transition Membrane, Substrate Preparation
A factory-made sheet with pressure-sensitive adhesive backing that bonds to a substrate when pressed in place, commonly used for wall and transition air barrier work.
- Fluid-Applied Membrane
- Related: Self-Adhered Membrane, Substrate Preparation
A liquid coating sprayed, rolled, or brushed onto a substrate that cures into a seamless air barrier film and readily covers irregular shapes and details.
- Transition Membrane
- Related: Continuity, Lap Width
A flexible strip or coating used to bridge the joint where two different air barrier materials or substrates meet, keeping the seal continuous across the change.
- Joint Sealant
- Related: Penetration Seal, Termination
A mastic or elastomeric material placed in gaps between components to block air and water movement while allowing the joint to move without tearing.
- Penetration Seal
- Related: Continuity, Joint Sealant
A detail that closes the gap around pipes, conduits, ducts, or fasteners passing through the air barrier, restoring the assembly's resistance to air flow.
- Spray Polyurethane Foam
- Related: Penetration Seal, Fluid-Applied Membrane
A two-component material sprayed in place that expands and cures into a rigid cellular layer, providing insulation and, in some formulations, air sealing.
- ASTM E2178
- Related: Air Permeance, ASTM E2357
A standard laboratory test method that measures air permeance of air barrier materials, producing the material-level leakage data used to qualify products for use.
- ASTM E2357
- Related: ASTM E2178, Acceptance Criteria
A standard test method for measuring air leakage of air barrier assemblies built on a test frame, so joints, laps, and details are included rather than the material alone.
- Acceptance Criteria
- Related: ASTM E2357, Nonconformance
The pass or fail thresholds stated in a specification or program, such as a maximum leakage rate, against which field observations and test results are judged.
- Specification Section 07 27 00
- Related: Acceptance Criteria, Workmanship Verification
The project specification section that states requirements for air barrier materials, installation, and quality control, and serves as the auditor's primary reference when judging compliance.
- Substrate Preparation
- Related: Self-Adhered Membrane, Workmanship Verification
Cleaning and repairing the surface before membrane or coating installation, removing dust, frost, and protrusions so adhesives and sealants bond reliably.
- Lap Width
- Related: Transition Membrane, Workmanship Verification
The distance one sheet or membrane overlaps another, which must meet the manufacturer's minimum so the joint stays sealed against air and water.
- Termination
- Related: Joint Sealant, Continuity
The point where an air barrier material ends and is sealed off, such as at a roof edge, foundation, or opening, requiring a deliberate sealed detail.
- Workmanship Verification
- Related: Substrate Preparation, Lap Width
Systematic field checking that installation matches the manufacturer's written instructions and project specification, covering laps, sealing, surface preparation, and protection of finished work.
- Mock-Up
- Related: Workmanship Verification, Audit Plan
A full-scale sample installation of an assembly completed before production work, used to confirm that details, workmanship, and test results meet the specification.
- Audit Plan
- Related: Sampling, Field Audit Report
A written document setting out the scope, locations, sampling approach, personnel, schedule, and reporting requirements for a field audit before work begins.
- Sampling
- Related: Representative Sample, Audit Plan
Selecting a portion of the installed work to inspect or test, chosen so the results reasonably represent the whole installation within the stated confidence.
- Representative Sample
- Related: Sampling, Audit Plan
A subset of work chosen to reflect the range of conditions, installers, and details present, rather than only the easiest or most visible areas.
- Chain of Custody
- Related: Sampling, Field Audit Report
A documented record of who collected, handled, and transported a sample or record, showing it was not altered before examination or testing.
- Blower Door Test
- Related: Pressure Differential, Air Leakage
A diagnostic procedure using a calibrated fan and pressure gauge to pressurize or depressurize a building and measure air leakage across the whole enclosure.
- Chamber Test
- Related: Pressure Differential, ASTM E2357
A field or laboratory procedure that encloses a section of assembly, applies a known pressure difference, and measures airflow to quantify local leakage.
- Smoke Pencil
- Related: Blower Door Test, Pressure Differential
A small device that releases a visible smoke trail, which bends toward openings where air is leaking, making leak locations easy to see.
- Infrared Thermography
- Related: Blower Door Test, Air Leakage
Thermal imaging that shows surface temperature differences, helping reveal missing insulation, air leakage paths, and moisture when weather conditions favor detection.
- Pressure Differential
- Related: Blower Door Test, Chamber Test
The difference in air pressure between two spaces, measured with a manometer or gauge, which drives air movement and sets the conditions for testing.
- Nonconformance
- Related: Corrective Action, Acceptance Criteria
A documented instance where installed work or a process fails to meet a specified requirement, which must be tracked and resolved before the work is accepted.
- Corrective Action
- Related: Nonconformance, Field Audit Report
The specific repair or process change made to eliminate a detected nonconformance and reduce the chance it happens again on the project.
- Field Audit Report
- Related: Nonconformance, Chain of Custody
A written record of an audit's scope, observations, evidence, nonconformances, and conclusions, prepared so a reader can follow what was checked and found.
- Conflict of Interest
- Related: Impartiality
A situation where an auditor's financial, personal, or business ties could bias findings, which must be disclosed and avoided to keep the audit credible.
- Impartiality
- Related: Conflict of Interest
The auditor's freedom from favoritism or pressure, so judgments rest only on evidence and stated requirements rather than on who performed the work.
- Fall Protection
- Related: Personal Protective Equipment
Systems such as harnesses, guardrails, and anchor points that prevent or arrest a fall when an auditor works at height on site.
- Personal Protective Equipment
- Related: Fall Protection
Wearable gear such as hard hats, eye protection, gloves, and respirators that reduce injury and exposure risks while inspecting active construction sites.