ACI Special Inspector study materials
ACI Special Inspector study resources

ACI Special Inspector flashcards

ACI Special Inspector · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Slump test standard
ASTM C143 measures consistency of fresh concrete. Fill cone in three equal layers, rod 25 strokes each, lift mold vertically and measure slump to nearest 1/4 in.
Cylinder compressive strength
ASTM C39 test of hardened concrete. 6x12 in. cylinders loaded at 35 ± 7 psi/s; result is the average of at least two cylinders, reported to nearest 10 psi.
Pressure air meter
ASTM C231 method for air content of normal-weight concrete. Concrete must be free of aggregate over 1.5 in.; daily calibration with known air content is required.
Volumetric air test
ASTM C173 method using isopropyl alcohol to determine air content. Used for lightweight or porous aggregate concrete where pressure method is unreliable.
Sampling fresh concrete
ASTM C172 requires sampling from middle portion of discharge, minimum 1 ft³, composite from several locations, remixed before testing.
Concrete temperature test
ASTM C1064: probe inserted at least 3 in. into concrete mass, reading taken within 5 minutes of sampling, reported to nearest 1 F.
Standard-cured cylinders
Cylinders cured at 60-80 F in moist environment for first 24 hours then lime water or moist room. Represent potential strength of the mix.
Field-cured cylinders
Cylinders cured in the field under the same conditions as the structure. Used to determine when formwork or shoring may be removed.
ACI 318 strength acceptance
Average of any three consecutive strength tests must equal or exceed f'c. No single test may fall below f'c minus 500 psi.
Slump tolerance
Permitted variation from specified slump: ±1 in. when specified is 2 in. or less; ±2 in. for 3-4 in.; ±3 in. for 5 in. or more.
Formwork removal strength
Vertical forms may be removed when concrete reaches 500 psi. Shore removal for structural members requires 70% of design strength unless approved.
Consolidation spacing
Internal vibrator insertion points spaced no more than 1.5 times the radius of action; vibrator inserted vertically and slowly withdrawn.
Construction joint preparation
Joint surface roughened to 1/4 in. amplitude, cleaned of laitance, and pre-wetted before placing new concrete to ensure shear transfer.
Hot weather concrete limit
Concrete temperature as placed must not exceed 90 F (32 C) unless otherwise specified; cooling methods include chilled water and ice.
Cold weather protection
Maintain concrete at 50 F minimum for 7 days, or 40 F for 3 days with insulating protection, to ensure adequate strength development.
Minimum cover requirements
Cast-in-place concrete not exposed to weather: 1.5 in. for slabs and walls, 2 in. for beams and columns, 3 in. for footings.
Post-tensioning elongation check
Measured elongation compared to calculated elongation; agreement within ±7% is typically required before acceptance of the stressing operation.
Concrete placement free fall
Concrete should not free-fall more than 3 to 5 ft; use drop pipes or chutes to prevent segregation during placement.
Curing duration
Concrete surfaces must be cured for at least 7 days when Type I cement is used; 3 days for accelerated or Type III mixes.
Reinforcement cover purpose
Adequate cover protects steel from corrosion, provides fire resistance, and ensures bond between concrete and reinforcement.
Sulfate-resistant cement
Type V cement used where high sulfate exposure exists; Type II provides moderate sulfate resistance. Selection based on soil or water sulfate content.
Water-cement ratio
Ratio of water mass to cementitious material mass. Lower w/c increases strength and durability; typical structural range is 0.40 to 0.50.
Yield per batch
Actual volume produced per batch compared to design volume. Yield deviation beyond 1% signals batching or moisture errors.
Air content tolerance
Total air content must be within ±1.5% of specified value for air-entrained concrete; check with ASTM C231 or C173.
Moisture correction
Aggregate stockpile moisture must be measured and deducted from batch water; free moisture differs from absorption capacity.
Test result averaging
Compressive strength test result is average of two cylinders; if they differ by more than 10%, a third cylinder is tested.
Yield test frequency
Yield, air content, and slump are tested at least once per day of placement and for each 150 yd³ of concrete placed.
Concrete density check
Unit weight of fresh concrete per ASTM C138; used to calculate yield and verify air content when combined with theoretical density.
Accelerated curing
Warm-water or steam curing used to predict 28-day strength; correlation with standard-cured cylinders must be established.
Laitance removal
Weak surface layer of cement and fines must be removed from joints by wire brushing or chipping before new concrete is placed.
Vibration duration
Vibrator should be inserted until concrete surface just becomes glossy; typically 5 to 15 seconds per insertion to avoid segregation.
Concrete sampling frequency
Strength test specimens taken at least once per day, once per 150 yd³, and for each mix design used in a day.