ACI Special Inspector · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Concrete Construction Inspection

  • Define the special inspector's roles and responsibilities on a concrete project and distinguish them from the contractor's quality-control duties

  • Identify the reference standards and code sections that govern concrete construction inspection

  • List the sequence of inspection hold points from pre-placement through final acceptance

  • Explain how inspection records and daily reports are documented and distributed

Your checkpoint

A one-page inspection responsibility matrix mapping each project party to its concrete inspection duties, with cited code references

Week 2

Concrete Construction Inspection

  • Describe formwork, shoring, and falsework requirements to verify before placement

  • Verify reinforcement size, spacing, cover, laps, and support against the approved drawings

  • Check embedded items, blockouts, and construction joint preparation prior to authorization

  • Explain how to document pre-placement acceptance and issue a placement authorization

Your checkpoint

A completed pre-placement inspection checklist covering forms, reinforcement, and embeddings, with pass/fail criteria for each line item

Week 3

Concrete Construction Inspection

  • Sequence the steps of concrete placement inspection from truck arrival through finishing

  • Evaluate slump, temperature, and air content results against specification limits and decide on acceptance

  • Identify improper placement, consolidation, and curing practices and state the corrective action

  • Describe cold-weather and hot-weather placement precautions an inspector must verify

Your checkpoint

A field decision guide that converts out-of-tolerance slump, temperature, and air results into accept, retest, or reject actions

Week 4

Concrete Construction Inspection & Concrete Field and Laboratory Testing Knowledge

  • Explain curing methods and duration requirements and verify them in the field

  • Describe sampling frequency and location requirements for field test specimens

  • Identify common concrete defects and the inspection evidence needed to characterize them

  • Summarize the concrete testing standards an inspector relies on during placement

Your checkpoint

A mid-plan self-test of at least 40 original practice questions across Domains 1 and 2, scored with a written list of missed topics

Week 5

Concrete Field and Laboratory Testing Knowledge

  • Describe proper sampling procedures for fresh concrete and the effect of sampling errors on results

  • Explain slump, air content, and fresh temperature test procedures step by step

  • Calculate yield, unit weight, and relative yield from field data

  • State the acceptance criteria and tolerances applied to each fresh-concrete test

Your checkpoint

A step-by-step field test procedure card for slump, air content, temperature, and unit weight, each with its acceptance tolerance

Week 6

Concrete Field and Laboratory Testing Knowledge

  • Describe specimen molding, initial curing, and transport requirements for compressive strength cylinders

  • Explain standard versus field curing and how each affects reported strength

  • Compute compressive strength and interpret break results against specified strength

  • Identify testing errors that invalidate strength results and how to document them

Your checkpoint

A worked problem set of at least 10 strength and yield calculations with shown steps and interpreted pass/fail conclusions

Week 7

Concrete Field and Laboratory Testing Knowledge & Concrete Construction Inspection

  • Explain laboratory qualification, calibration, and reporting requirements for concrete testing

  • Interpret a certificate of calibration and a strength test report for completeness and compliance

  • Diagnose nonconformance scenarios and state the required follow-up inspection and testing

  • Reconcile conflicting field and laboratory results using specification acceptance rules

Your checkpoint

A written case analysis of three nonconformance scenarios, each with the governing requirement, required follow-up, and documentation trail

Week 8

Concrete Construction Inspection & Concrete Field and Laboratory Testing Knowledge

  • Recall key code and standard requirements across both domains without references

  • Apply inspection and testing knowledge to timed, scenario-based questions

  • Prioritize remaining weak areas and close them with targeted review

  • Build a personal exam-day checklist of formulas, tolerances, and procedures

Your checkpoint

A full-length timed practice exam of at least 60 original questions, scored, with a written remediation plan for every missed domain

Milestones

Week 2: Can complete a pre-placement checklist from memory and justify each hold point with a code reference

Week 4: Scores at least 70 percent on the 40-question mid-plan self-test and has a written list of weak topics

Week 6: Correctly performs strength and yield calculations on 8 of 10 problems without reference material

Week 8: Scores at least 80 percent on the full-length timed practice exam, with no domain below 70 percent