Quick reference

Shotcrete Materials and Mixtures

  • Shotcrete is mortar or concrete pneumatically projected at high velocity onto a surface; both dry-mix and wet-mix processes use the same basic cementitious constituents.

  • Dry-mix places cement and aggregate dry at the nozzle, adding water there; wet-mix pre-mixes all ingredients including water before pumping.

  • Typical dry-mix water/cement ratio at the nozzle falls near 0.35-0.45; wet-mix is batched at conventional ratios near 0.40-0.50 with water-reducing admixtures.

  • Silica fume at roughly 5-12% of cementitious mass increases cohesion, reduces rebound, and raises compressive strength and impermeability.

  • Aggregate grading for dry-mix shotcrete generally peaks at 10-12 mm (3/8 in); wet-mix may use up to 16 mm (5/8 in) depending on nozzle and hose size.

  • Accelerators shorten set time: alkali-free liquid accelerators are preferred over powdered aluminates because they reduce strength loss and dust.

  • Fiber reinforcement (steel or synthetic) is dosed by volume, commonly 30-60 kg/m3 steel, and is not a substitute for structural reinforcement unless designed as such.

  • Pre-bagged proprietary mixes must be used with the manufacturer's stated water content; field-added water beyond the bag recommendation changes w/c and strength.

Quick reference

Shotcrete Equipment and Application Methods

  • Dry-mix uses a pressure vessel or rotary gun feeding a hose; wet-mix uses a concrete pump (piston or rotor-stator) delivering material to the nozzle.

  • Nozzle distance from the surface is typically 0.9-1.5 m (3-5 ft); greater distance reduces impact velocity and increases rebound.

  • Nozzle should be held perpendicular to the surface; the spray angle should not deviate more than about 15 degrees from normal.

  • Compressed air supply at the nozzle typically requires roughly 7-10 m3/min at 0.5-0.7 MPa for dry-mix; insufficient air causes surging and poor consolidation.

  • Nozzleman technique: steady circular or elliptical motion builds uniform thickness; dwelling in one spot creates lumps and shadowing.

  • Hose size for dry-mix is commonly 32-50 mm; wet-mix lines are typically 50-65 mm with reducers at the nozzle.

  • Rebound is the material that bounces off; it is higher for dry-mix and for overhead work, and rebound must never be reused in the work.

  • Equipment must be cleaned and the line blown clear between mixes; a plugged line is cleared only after depressurizing and with the nozzle pointed away from personnel.

Quick reference

Surface Preparation and Placement

  • Surface must be clean, sound, and free of dust, oil, loose material, and standing water before spraying.

  • Concrete substrates receive a roughened profile (typically CSP 5-7 by acid etching, abrasive blasting, or scarifying) to promote mechanical bond.

  • Substrate should be pre-wetted to saturated-surface-dry (SSD) so it does not draw mixing water from the shotcrete; free water is not permitted.

  • Reinforcement must be clean and free of release agents; minimum cover to reinforcement is typically 15-20 mm for shotcrete in non-corrosive exposure.

  • Spray the first pass into corners and behind reinforcement first, building up in layers rather than one thick pass.

  • Maximum single-pass thickness is roughly 50-75 mm for walls and less (about 25-50 mm) for overhead work; subsequent layers are applied while the previous layer is still workable or after proper preparation.

  • For overhead work, apply material in thin lifts and allow initial set before adding more to prevent sagging and fall-out.

  • Joints and construction interfaces should be square-cut or tapered and cleaned before resuming; cold joints require roughening and wetting.

Quick reference

Inspection, Testing, and Quality Control

  • Compressive strength is evaluated on cores or on test panels sprayed under field conditions; test panels must be cured and cored per project specification.

  • Core diameter is typically 75 mm (3 in) minimum; cores are trimmed, capped, and tested in compression to determine field strength.

  • Acceptance often requires field strength to meet a specified fraction (commonly about 70-85%) of the design or laboratory strength to account for field variability.

  • Thickness is verified by probe, core, or depth gauge; the average of measurements must meet the specified thickness with no single point below a stated minimum.

  • Rebound and overspray are estimated by placing a rebound board or measuring material collected at the base of the work.

  • Bond strength is assessed by pull-off or core inspection; a sound, continuous bond line with no visible delamination is required.

  • Inspection includes verifying nozzleman qualification, mix design approval, water content at the nozzle, and curing method.

  • Curing must begin promptly after final set; wet curing, curing compound, or moist cover is required to prevent plastic and drying shrinkage cracking.

Quick reference

Repair, Safety, and Standards Compliance

  • Defective shotcrete (voids, delamination, honeycomb, low strength) is removed to sound material with square edges before repair.

  • Repair material must be compatible with the parent shotcrete in strength, modulus, and thermal expansion to avoid debonding.

  • Shallow repairs use a bonding agent or roughened, SSD-prepared surface; deep repairs are built up in layers matching the original placement limits.

  • Safety: nozzleman and crew wear eye protection, respiratory protection for dry-mix dust and silica, and hearing protection near compressors.

  • Silica dust controls include wetting, ventilation, and NIOSH-approved respirators; crystalline silica is a known health hazard.

  • Compressed air lines and nozzles are a struck-by hazard; never look into a nozzle or stand in line with the hose during pressurization.

  • Standards and references: ACI 506 (Guide to Shotcrete) and ACI 506.2 (Specification for Shotcrete) govern materials, application, and inspection; ASTM C1140 covers making and testing shotcrete panels.

  • Inspector qualification and nozzleman certification (e.g., ACI or equivalent) are commonly required by specification before production work begins.