- Shotcrete definition
- Mortar or concrete pneumatically projected at high velocity onto a surface, consolidating on impact; placed by dry-mix or wet-mix process.
- Dry-mix process
- Cement and aggregate are mixed dry and conveyed pneumatically to the nozzle, where water is added immediately before projection onto the surface.
- Wet-mix process
- All ingredients, including water, are pre-mixed before pumping to the nozzle; water content is controlled at the batch plant rather than at the nozzle.
- Silica fume role
- A very fine pozzolan added at roughly 5-12% of cementitious mass; it increases cohesion, reduces rebound, and improves strength and impermeability.
- Accelerator function
- An admixture that shortens set time so shotcrete gains early strength and adheres, especially on overhead and vertical surfaces; alkali-free types are preferred.
- Fiber reinforcement dose
- Steel or synthetic fibers added by volume, commonly around 30-60 kg/m3 for steel, to improve toughness and crack resistance; not a substitute for structural steel.
- Nozzle distance rule
- The nozzle is held roughly 0.9-1.5 m (3-5 ft) from the surface; too far reduces impact velocity and increases rebound and overspray.
- Nozzle angle rule
- The nozzle is held perpendicular to the surface, deviating no more than about 15 degrees from normal, to maximize compaction and minimize rebound.
- Wet-mix pumping equipment
- A piston or rotor-stator concrete pump delivers pre-mixed shotcrete through a hose to the nozzle, where compressed air accelerates the stream.
- Dry-mix feeding equipment
- A pressure vessel or rotary gun meters dry material into a compressed-air stream that carries it through the hose to the water ring at the nozzle.
- Nozzleman motion
- A steady circular or elliptical sweeping motion builds uniform thickness; dwelling in one location creates lumps and shadowed, under-filled areas.
- Rebound definition
- Material that bounces off the surface during spraying; it is higher for dry-mix and overhead work and must never be reused in the work.
- Compressed air requirement
- Dry-mix typically needs about 7-10 m3/min at 0.5-0.7 MPa at the nozzle; insufficient air causes surging and poor consolidation.
- Surface preparation
- Substrate must be clean, sound, and free of dust, oil, and loose material; concrete is roughened to provide mechanical bond before spraying.
- SSD substrate condition
- Saturated-surface-dry means the substrate is moist but has no free water, so it neither draws mixing water from nor adds water to the shotcrete.
- Surface profile CSP
- Concrete surface roughness classified by Concrete Surface Profile (CSP) numbers; shotcrete typically requires a CSP 5-7 profile for adequate bond.
- Single-pass thickness
- Maximum thickness applied in one pass, roughly 50-75 mm on walls and about 25-50 mm overhead; thicker buildup uses multiple lifts.
- Overhead placement
- Apply in thin lifts and allow initial set between lifts to prevent sagging and fall-out; the first material goes into corners and behind reinforcement.
- Cold joint treatment
- Construction interfaces are square-cut or tapered, cleaned, roughened, and wetted before resuming placement to restore continuity and bond.
- Test panel purpose
- Field-sprayed panels replicate job conditions; cores cut from them are tested for compressive strength and inspected for thickness and bond.
- Core diameter minimum
- Compressive strength cores are typically at least 75 mm (3 in) in diameter, trimmed, capped, and tested in compression per project specification.
- Field strength acceptance
- Field-cured strength commonly must reach about 70-85% of design or laboratory strength to account for field variability and rebound effects.
- Thickness verification
- Thickness is checked by probe, core, or depth gauge; the average must meet the specified thickness and no single point may fall below the stated minimum.
- Bond strength check
- Assessed by pull-off test or core inspection; a continuous bond line with no visible delamination or hollow sound is required.
- Curing requirement
- Curing begins promptly after final set using wet curing, moist cover, or curing compound to prevent plastic and drying shrinkage cracking.
- Defect removal
- Voids, delamination, honeycomb, and low-strength shotcrete are removed back to sound material with square edges before any repair material is placed.
- Repair material compatibility
- Repair material must match the parent shotcrete in strength, modulus, and thermal expansion to prevent debonding and cracking at the interface.
- Silica dust protection
- Crystalline silica is a health hazard; controls include wetting, ventilation, and NIOSH-approved respirators for dry-mix dust exposure.
- Compressed air hazard
- Never look into a nozzle or stand in line with a pressurized hose; lines are depressurized before clearing plugs to avoid struck-by injury.
- ACI 506 reference
- ACI 506 is the Guide to Shotcrete and ACI 506.2 the Specification for Shotcrete; they govern materials, application, and inspection practice.
- ASTM C1140 scope
- Covers making and testing shotcrete test panels in the field, including spraying, curing, and core extraction for strength evaluation.
- Nozzleman qualification
- Nozzlemen are typically certified through an approved program before production work; the inspector verifies current qualification and technique.