ACI Shotcrete Nozzleman Wet-Mix flashcards
ACI Shotcrete Nozzleman Wet-Mix · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Nozzle angle
- The nozzle should be held perpendicular (about 90 degrees, plus or minus 10 degrees) to the receiving surface to maximize compaction and bond while minimizing rebound and shadowing behind reinforcement.
- Nozzle distance
- A typical nozzle-to-surface distance is 0.6 to 1.5 m (about 2 to 5 ft); too close causes gouging and rebound, too far reduces impact velocity and compaction.
- Rebound
- Material that bounces off the surface during shooting; it is highest on overhead work and behind reinforcement and must never be reused or troweled back into the work.
- Lift thickness
- Shotcrete is built up in controlled passes, typically 50 to 100 mm (2 to 4 in) per pass on vertical and overhead work, with thinner first passes overhead.
- Nozzle motion
- A steady circular or elliptical motion with overlapping passes distributes material evenly and avoids sagging, trapped voids, and localized overbuild.
- Shooting sequence
- On vertical walls, start at the bottom and work upward so the lower edge does not collect rebound; encase reinforcement by shooting from behind and around it.
- Water at the nozzle
- In wet-mix shotcrete the nozzleman may adjust water at the discharge point for consistency, but total water-to-cementitious-material ratio must remain within the approved mix design.
- Cementitious content
- Typical wet-mix shotcrete contains roughly 350 to 450 kg/m3 (about 590 to 760 lb/yd3) of cementitious material; higher paste content aids pumpability but increases shrinkage.
- Water-cementitious ratio
- Total water (batch water plus any nozzle water) divided by cementitious material; typical field values are about 0.40 to 0.50 and must not exceed the approved design.
- Maximum aggregate size
- Wet-mix shotcrete aggregate is generally limited to about 10 to 12 mm (3/8 to 1/2 in) to permit pumping and reduce rebound and line blockage.
- Supplementary cementitious materials
- Fly ash, slag, and silica fume improve pumpability, cohesion, and durability; silica fume also reduces rebound and permeability of shotcrete.
- Air entrainment
- Air-entraining admixtures are used for freeze-thaw exposure; entrained air is typically 5 to 8 percent depending on aggregate size and exposure severity.
- Accelerators
- Admixtures added at the nozzle to shorten set time and allow thicker overhead lifts; non-chloride types are used where embedded steel is present, and dosage must be controlled.
- Delivery line size
- Wet-mix shotcrete is commonly pumped through 38 to 50 mm (1.5 to 2 in) lines; line size, pump output, and nozzle air supply must be matched to avoid blockages.
- Nozzle air pressure
- Air pressure at the nozzle is commonly about 0.5 to 0.7 MPa (70 to 100 psi), or as specified by the equipment manufacturer, to propel material onto the surface.
- Pumping continuity
- A steady, continuous pumping rate prevents slug flow and surging, which cause inconsistent nozzle discharge and blockages; lines are pre-dampened before shooting.
- Surface preparation
- Remove loose material, dust, oil, and deteriorated concrete; roughen and clean the substrate so the new shotcrete can develop bond.
- Pre-wetting substrate
- Absorptive substrates are brought to a saturated-surface-dry condition before shooting so the new shotcrete does not lose water to the base; standing water is removed.
- Reinforcement encasement
- Bars must be clean and free of scale, oil, or form release; shotcrete must fully encase reinforcement, so shoot from the correct angle to fill behind bars.
- Scratch coat
- A thin first pass applied on vertical and overhead work to establish bond before building thickness; subsequent lifts follow after initial set as required.
- Finishing timing
- Floating or troweling must be done while the mix is still plastic; working too late tears or delaminates the surface and weakens the skin.
- Trimming to line and grade
- Fresh shotcrete is trimmed and shaped with a rod or cutting tool to line and grade; overworking the surface draws paste and weakens it.
- Construction joints
- Joints are formed by cutting back to sound, square edges; the joint surface is wetted before resuming, and feathered edges are avoided.
- Curing
- After finishing, shotcrete must be kept moist or coated with a curing compound; curing is especially important for thin sections and overhead work.
- Mock-up panel
- A pre-construction test panel, typically at least 500 mm (about 18 in) square, shot in the same orientation as production work to demonstrate nozzleman technique and provide specimens.
- Core testing
- Cores taken from panels or in-place shotcrete are tested for compressive strength and compared with the specified strength to verify acceptance.
- Bond strength testing
- Pull-off or core tests evaluate bond; poor results point to inadequate surface preparation, a dry substrate, or incorrect nozzle angle.
- Thickness verification
- Placed thickness is checked with probes, cores, or depth gauges during and after placement and must meet the specified minimum.
- Nozzleman qualification
- The nozzleman demonstrates competence through the mock-up panel; qualification is tied to the shooting orientation and the approved procedure.
- Silica exposure control
- Respirable crystalline silica controls are required: wet methods, ventilation, and respiratory protection, along with eye, hearing, and hand protection for the crew.
- Emergency shutdown
- The nozzleman must be able to shut off material feed and air quickly; the nozzle is always pointed away from personnel.
- Defect repair
- Voids, delamination, and low-strength areas are removed back to sound material, the surface is prepared, and the area is re-shot or patched with approved repair material.