33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project
A temporary endeavor undertaken to create a unique product, service, or result, with a defined start and end and constrained resources.
Program
A group of related projects and subsidiary work managed in a coordinated way to obtain benefits not available from managing them individually.
Portfolio
A collection of projects, programs, and operations grouped to achieve strategic business objectives; components may not be directly related.
Project Charter
A document issued by the sponsor that formally authorizes the project, names the project manager, and states high-level objectives and constraints.
Phase Gate
A review point at the end of a project phase where continuation, revision, or termination of the project is formally decided.
Value Engineering
A structured, function-based, multidisciplinary study that analyzes functions to identify unnecessary cost and improve value before funds are committed.
Value Formula
Value equals function divided by cost; value rises when function or performance increases, cost decreases, or both occur together.
Function Analysis
Naming each item's purpose with an active verb and measurable noun, then classifying it as basic (essential) or secondary (supporting).
FAST Diagram
A Function Analysis System Technique diagram that maps functions in logical HOW and WHY relationships to reveal dependencies and missing functions.
Job Plan
The VE sequence: information, function analysis, creative, evaluation, development, presentation, and implementation/follow-up phases.
Unnecessary Cost
Cost that contributes no use, esteem, exchange, or aesthetic value; it is the primary target of a value engineering study.
Life-Cycle Cost
Total cost of an asset over its life, including acquisition, operation, maintenance, and disposal; used to compare value alternatives.
Earned Value
The budgeted value of work actually completed, computed as percent complete multiplied by the budget at completion.
Cost Variance
CV = EV minus AC; a negative result indicates the project has spent more than the value of work performed.
Cost Performance Index
CPI = EV divided by AC; a value below 1.0 means the project is getting less work per unit of cost than planned.
Schedule Performance Index
SPI = EV divided by PV; a value below 1.0 indicates less work has been completed than was planned for the period.
Critical Path
The longest-duration sequence of dependent activities through the network; it has zero total float and sets the project duration.
Total Float
The amount an activity can be delayed without delaying the project finish, computed as late start minus early start.
Estimate at Completion
The forecast total cost of the project; commonly BAC divided by CPI when current cost performance is expected to continue.
Expected Monetary Value
EMV equals probability multiplied by impact; used in decision trees to compare alternatives with uncertain outcomes.
Contingency Reserve
Budget or time set aside for identified risks with known probability and impact; it is part of the approved cost baseline.
Management Reserve
Budget held for unidentified risks (unknown unknowns); its use typically requires sponsor approval and it sits outside the cost baseline.
Risk Response Strategies
Threat responses are avoid, transfer, mitigate, accept, and escalate; opportunity responses are exploit, share, enhance, accept, and escalate.
Monte Carlo Simulation
A quantitative technique that runs many randomized iterations of cost or schedule inputs to produce a probability distribution of outcomes.
Risk Appetite
The degree of uncertainty an organization is willing to accept in pursuit of its objectives, expressed as a general willingness to take risk.
Power-Interest Grid
A stakeholder classification mapping authority against concern; high power and high interest stakeholders are managed closely.
Tuckman Stages
The team development sequence of forming, storming, norming, performing, and adjourning, each with distinct leadership needs.
Theory X and Theory Y
McGregor's contrasting assumptions: Theory X sees workers as avoiding work and needing control; Theory Y sees them as self-motivated.
Thomas-Kilmann Modes
Five conflict-handling approaches: competing, collaborating, compromising, avoiding, and accommodating, chosen by importance and relationship.
Servant Leadership
A leadership style that prioritizes serving the team, removing impediments, and enabling self-organization rather than directing through authority.
Conflict Sources
Ranked causes of project conflict: schedules, project priorities, resources, technical opinions, administrative procedures, and personality clashes.
Core Professional Values
The ethical foundation of responsibility, respect, fairness, and honesty that guides conduct in all professional project decisions.
Conflict of Interest
A situation where personal interest could compromise professional judgment; it must be disclosed and managed or the assignment declined.