ACRP-PM · Build recall with a focused review session.

33 cards. Read the term and the definition here. The deck at the top of this page is optional.

Triple constraint
The interdependent relationship among scope, time, and cost. Changing one requires adjusting at least one other, and quality is affected by how the trade-off is managed.
Progressive elaboration
Iteratively refining project plans as more detail and information become available. Early estimates therefore carry wider ranges than later ones.
Project versus operations
A project is temporary and produces a unique deliverable; operations are ongoing and repetitive. A clinical study is a project with a defined end.
Deliverable
Any measurable, verifiable outcome or output that must be produced to complete the project, such as a protocol, monitoring report, or clinical study report.
Milestone
A significant point or event in the project with zero duration. It marks completion of a key deliverable, such as first patient in or database lock.
Process groups
Initiating, Planning, Executing, Monitoring and Controlling, and Closing. These groups recur across project phases rather than occurring only once.
Scope baseline
The approved scope statement plus the work breakdown structure and its dictionary. It is the reference against which scope changes are evaluated.
Work breakdown structure
A hierarchical decomposition of total project scope into deliverables and work packages. The lowest level should be estimable and assignable to one owner.
Critical path
The longest-duration path through the project network. It determines the minimum project duration and its activities have zero total float.
Total float
The amount of time an activity can be delayed without delaying the project finish date. It equals late start minus early start.
Crashing versus fast-tracking
Crashing adds resources or cost to shorten duration; fast-tracking overlaps activities that were sequential and increases risk.
Scope creep
Uncontrolled expansion of project scope without approved change control, often adding work without corresponding time, cost, or resource adjustments.
Rolling wave planning
Detailing near-term work in full while leaving later work at a higher level until more information becomes available.
Per-patient cost
Total study cost minus fixed costs, divided by planned enrollment. Used to price per-patient fees and evaluate change orders.
Cost variance
CV = EV − AC. A positive value means the project is under budget; a negative value means it is over budget.
Cost performance index
CPI = EV ÷ AC. A value below 1.0 indicates the project is spending more than planned for the work earned.
Schedule performance index
SPI = EV ÷ PV. A value below 1.0 indicates the project is behind schedule relative to the planned value of work.
Estimate at completion
EAC = BAC ÷ CPI when current cost performance is expected to continue. It forecasts total cost at project completion.
Resource leveling
Adjusting start and finish dates to resolve resource over-allocation. It may extend the schedule and change the critical path.
Fixed-price contract
A contract where the vendor agrees to a set price for defined deliverables, shifting cost risk to the vendor if costs increase.
Risk versus issue
A risk is an uncertain future event that may affect objectives; an issue is a risk that has already occurred and needs action.
Risk score
Probability multiplied by impact. Scores above a defined threshold typically require a formal response plan and escalation.
Risk responses
For threats: avoid, transfer, mitigate, accept. For opportunities: exploit, share, enhance, accept. Each response needs an assigned owner.
Residual versus secondary risk
Residual risk remains after a response is applied; secondary risk is a new risk created by implementing the response itself.
Quality assurance versus control
Quality assurance is process-focused and preventive; quality control is product-focused and detects defects through inspection and testing.
Root cause analysis
Techniques such as the 5 Whys and fishbone diagram that separate the underlying cause of a problem from its visible symptoms.
Stakeholder power/interest grid
A classification tool. High power and high interest stakeholders are managed closely; low power and low interest are simply monitored.
Communication channels
The number of communication paths equals n(n − 1) ÷ 2, where n is the number of stakeholders. Complexity grows rapidly with team size.
Tuckman stages
Forming, storming, norming, performing, and adjourning. Teams typically pass through these stages in sequence before reaching productivity.
RACI matrix
Responsible does the work, Accountable approves and is single per task, Consulted provides two-way input, Informed receives one-way updates.
Conflict resolution modes
Collaborating (win-win), compromising, accommodating, competing, and avoiding. Collaborating is preferred for important issues with time available.
Push versus pull communication
Push sends information to recipients (reports, emails); pull makes information available on demand (shared repositories). Routine status uses push.
Lessons learned
Documented knowledge about what worked and what did not, captured throughout the project and finalized during closing for reuse.