ACRP-PM · Give each week a clear focus.

8 weeks · About 8 hours per week

Week 1

Project management knowledge applied to clinical research studies & Study planning, scope, and schedule management

  • Map the five ACRP-PM domains to your own study files and label each with its exam weight percentage

  • Define the project life cycle phases (initiation through close-out) and write a one-sentence scope statement for each

  • Build a work breakdown structure for a mock clinical study down to task level

  • Draft a study timeline in a Gantt-style format with dependencies and critical path marked

Your checkpoint

A one-page domain map plus a mock study WBS and Gantt chart with critical path identified

Week 2

Study planning, scope, and schedule management & Project management knowledge applied to clinical research studies

  • Sequence schedule activities and calculate float on at least five tasks

  • Identify schedule compression techniques and describe when each is appropriate

  • Differentiate scope creep from approved change control using three written scenarios

  • Explain how protocol amendments drive scope and schedule replanning

Your checkpoint

A schedule analysis worksheet showing float calculations and three worked scope-change scenarios

Week 3

Budget, resource, and vendor management

  • Build a bottom-up budget for a mock study covering per-patient, site, vendor, and pass-through costs

  • Distinguish fixed, variable, direct, and indirect costs with an example of each

  • Compare three vendor selection approaches and list the contract elements to negotiate

  • Draft a vendor oversight cadence covering metrics, meetings, and escalation triggers

Your checkpoint

A mock study budget with cost categories plus a vendor oversight plan template

Week 4

Risk, quality, and issue management & Budget, resource, and vendor management

  • Construct a risk register with probability, impact, score, owner, and mitigation for ten risks

  • Classify risks by type (operational, regulatory, financial, safety) and rank them

  • Describe quality management tools including QC versus QA and CAPA basics

  • Explain how budget variance analysis triggers corrective action

Your checkpoint

A completed ten-item risk register with scored and ranked risks and mitigation owners

Week 5

Risk, quality, and issue management & Communication, stakeholder, and team leadership

  • Write an issue escalation path with defined thresholds and timeframes

  • Apply root-cause analysis to two mock study deviations

  • Identify stakeholder categories and map influence versus interest

  • Draft a communication plan covering audience, channel, frequency, and content

Your checkpoint

An issue escalation flowchart plus a stakeholder map and communication plan

Week 6

Communication, stakeholder, and team leadership

  • Describe team development stages and match leadership actions to each stage

  • Outline conflict resolution approaches and select one for a written scenario

  • Explain motivation and delegation techniques for cross-functional study teams

  • Draft a meeting agenda and decision log for a study team meeting

Your checkpoint

A team leadership playbook covering stages, conflict, and delegation with a sample agenda and decision log

Week 7

Project management knowledge applied to clinical research studies & Study planning, scope, and schedule management & Budget, resource, and vendor management & Risk, quality, and issue management & Communication, stakeholder, and team leadership

  • Integrate concepts across all domains into a single end-to-end mock study narrative

  • Answer timed practice sets weighted by domain percentage

  • Log every missed item by domain and error type (knowledge gap versus misread)

  • Re-teach your three weakest concepts in writing without notes

Your checkpoint

A timed practice score report with a categorized error log and three written concept summaries

Week 8

Project management knowledge applied to clinical research studies & Study planning, scope, and schedule management & Budget, resource, and vendor management & Risk, quality, and issue management & Communication, stakeholder, and team leadership

  • Re-drill all logged weak areas until each is answered correctly twice consecutively

  • Complete two full-length timed simulations under exam conditions

  • Review formula and terminology sheets for budget, schedule, and risk

  • Finalize a test-day strategy covering pacing and question triage

Your checkpoint

Two completed simulation score reports with a final weak-area remediation checklist and test-day plan

Milestones

Week 2: Can build a WBS, sequence a schedule, and calculate float without notes

Week 4: Score at least 70% on a self-made budget and risk quiz

Week 6: Can explain risk, quality, and stakeholder concepts to another person unaided

Week 7: Timed practice score at or above target passing threshold with error log complete

Week 8: Both full-length simulations passed at or above target score with all weak areas closed