ACRP-PM: Communication, Stakeholder, and Team Leadership

ACRP-PM · Work through your exam, one topic at a time.

All guide sections

Communication, Stakeholder, and Team Leadership

The core idea

Trials succeed through coordinated people. Know the communication management plan: who needs what information, in what format, frequency, and channel, and who owns each message. Understand stakeholder analysis-identifying stakeholders, assessing interest and influence, and planning engagement-and the power/interest grid. Recognize that the sponsor, investigators, site staff, IRB/IEC, regulators, participants, and vendors have different needs and authority levels.

Concepts to master

Distinguish formal vs. informal and written vs. verbal communication, and know when documentation is required (e.g., decisions, deviations, changes). Understand team development stages (forming, storming, norming, performing, adjourning) and conflict management modes: collaborating (win-win, usually preferred for important issues), compromising, accommodating, avoiding, and forcing. Know motivation and delegation principles and the PM's role as facilitator rather than clinical decision-maker. Recognize escalation paths and the value of a communication matrix and RACI for clarifying roles.

Traps

Distractors include choosing "avoiding" conflict when collaboration is appropriate, communicating only verbally on decisions that require documentation, and bypassing the chain of command by escalating to a regulator or sponsor prematurely. Another trap: assuming the PM should make clinical judgments-clinical decisions belong to qualified investigators and medical monitors. Also watch for confusing authority with influence; a high-interest, low-influence stakeholder still needs engagement.

Rule of thumb

Match the channel to the stakes: high-stakes, irreversible, or regulated decisions belong in writing with the right approvers; routine updates can be informal.

Worked example

Two coordinators disagree on visit scheduling. The PM facilitates a collaborative discussion, documents the agreed process, and updates the communication plan-rather than issuing a directive (forcing) or ignoring it (avoiding).