AEE CMVP flashcards
AEE CMVP · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Routine adjustment
- An adjustment to baseline energy use that accounts for expected, predictable changes in operating conditions such as weather, occupancy, or production volume, typically applied using a model.
- Non-routine adjustment
- An adjustment to baseline energy use for unexpected or one-time changes such as building additions, equipment replacement, or changes in facility use, handled ad hoc.
- Adjusted baseline
- The baseline energy use modified by both routine and non-routine adjustments to reflect current conditions, used to calculate savings.
- Savings formula
- Savings = (Baseline Energy − Reporting-Period Energy) ± Adjustments. This is the fundamental equation for determining energy savings.
- Option A
- Retrofit Isolation: Key Parameter Measurement. Some parameters are measured, others are estimated with justification. Used when some parameters are known to be stable or insignificant.
- Option B
- Retrofit Isolation: All Parameter Measurement. All parameters affecting energy use are measured, often with dedicated meters. More accurate but costlier than Option A.
- Option C
- Whole Facility. Uses whole-building utility meter data to measure total facility energy use. Best for multi-ECM projects with savings >10% of baseline.
- Option D
- Calibrated Simulation. Uses a calibrated energy simulation model to estimate savings when baseline data are unavailable or for new construction.
- M&V cost guideline
- M&V costs typically range from 1% to 10% of project cost, depending on the M&V option and project complexity, and should be proportional to savings uncertainty.
- Retrofit isolation
- An M&V approach that focuses on individual ECMs, isolating their energy use from the rest of the facility using dedicated meters or measurements.
- Option A estimates
- In Option A, parameters not measured must be estimated based on evidence such as manufacturer data, spot measurements, or engineering calculations, and documented.
- Option B metering
- Option B requires continuous or periodic measurement of all parameters affecting the ECM's energy use, often using dedicated meters for the ECM.
- Measurement boundary
- The physical or virtual boundary that defines what energy flows are included in the M&V analysis; must be consistent between baseline and reporting periods.
- Whole facility approach
- An M&V approach that uses whole-building utility meters to measure total facility energy use, suitable for projects with multiple ECMs and savings >10% of baseline.
- Whole-building regression
- A statistical model relating whole-building energy use to independent variables like weather or occupancy, used in Option C to adjust baseline and determine savings.
- Option C applicability
- Option C is applicable when savings are greater than about 10% of baseline whole-facility energy use and when multiple ECMs are implemented.
- M&V Plan
- A document that outlines the M&V approach, responsibilities, data collection, adjustments, reporting, and budget for a project, agreed upon by stakeholders.
- M&V Plan elements
- Key elements include project description, ECM list, M&V option selection, baseline definition, measurement boundaries, adjustment method, data management, reporting schedule, and budget.
- M&V Plan timing
- The M&V Plan should be developed early, ideally during project design, to ensure data collection and metering requirements are included in the project scope.
- Stakeholder agreement
- The M&V Plan should be agreed upon by all stakeholders (owner, ESCO, verifier) before implementation to avoid disputes over savings verification.
- Savings report contents
- A savings report must include baseline energy, reporting-period energy, adjustments, savings, uncertainty, and the M&V option used, with clear units and explanations.
- Uncertainty reporting
- Savings reports should state uncertainty at a confidence level (e.g., 90%) and explain how it was determined, including model and meter uncertainty.
- Non-routine adjustment reporting
- Savings reports must document any non-routine adjustments, their rationale, and their impact on reported savings.
- Transparency in reporting
- Savings reports should be transparent, reproducible, and include raw data or references, allowing third-party verification.
- Meter accuracy class
- Meters are classified by accuracy (e.g., Class 1 high accuracy, Class 2 lower); selection depends on the required precision of the M&V analysis.
- Metering interval
- The frequency of meter readings (e.g., 15-minute, hourly, monthly); chosen based on ECM variability and the M&V option.
- Meter calibration
- Regular calibration of meters ensures accuracy; calibration dates and results should be documented and included in the M&V Plan.
- Temporary vs permanent metering
- Temporary metering is used for short-term measurements (e.g., Option A), while permanent metering supports continuous verification (e.g., Option B or C).
- Data validation
- Procedures to check for gaps, outliers, and meter drift in metered data, ensuring data quality for savings calculations.
- Change-point regression
- A regression model that uses change-points (e.g., balance points) to represent heating and cooling energy use as a function of outdoor temperature.
- CV(RMSE)
- Coefficient of Variation of the Root Mean Squared Error; a goodness-of-fit metric. Values below 15% (or 10% for Option C) are often used as calibration criteria.
- Model extrapolation
- Using a regression model outside the range of baseline data; should be avoided, and non-routine adjustments used instead if conditions exceed baseline range.