32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Homogeneous area
A group of materials with similar composition applied at the same time in the same manner; sampling and assessment are performed by homogeneous area rather than by individual room.
Friability definition
The ability of a material to be crumbled, pulverized, or reduced to powder by hand pressure, indicating a higher potential for airborne fiber release.
Surfacing material
Material sprayed, troweled, or otherwise applied to surfaces such as ceilings and walls for fireproofing or acoustical treatment; often friable and a high priority.
Thermal system insulation
Material applied to pipes, boilers, tanks, ducts, and fittings to prevent heat loss or gain; commonly friable and subject to damage from maintenance activity.
Significantly damaged
A material condition where friable ACM has deteriorated extensively or is likely to become airborne, warranting priority response such as removal or enclosure.
Reinspection interval
Under AHERA, school buildings must be reinspected by an accredited inspector at least once every three years to confirm material condition.
Assessment rating
A recorded judgment of material condition and damage potential, ranging from no damage through significant damage, used to set response priorities.
Fibers per cubic centimeter
The unit used to report airborne asbestos fiber concentration, typically measured by phase contrast microscopy on air samples collected in buildings.
Exposure potential factors
Friability, condition, accessibility, activity level, air movement, and vibration together determine how likely fibers are to be released and inhaled.
High-traffic area risk
Damage to friable ACM in occupied or frequently used spaces increases exposure potential because disturbance and fiber release are more likely.
Water damage effect
Moisture deteriorates asbestos-containing materials and can cause delamination and fiber release, raising the hazard rating of affected material.
Response action types
The five options are operations and maintenance, repair, enclosure, encapsulation, and removal; each has different permanence and cost.
When removal is preferred
Removal is generally chosen for significantly damaged friable material, material facing renovation or demolition, or material that other controls cannot manage.
Enclosure action
An interim control that builds a barrier around the material to prevent disturbance; it requires continued surveillance and does not eliminate the hazard.
Encapsulation action
An interim control that seals the material surface with a coating; unsuitable where water damage or future access is likely, and requires ongoing surveillance.
Repair as response
Limited corrective work such as patching TSI or sealing tears, usually combined with O&M to manage minor damage without full abatement.
Prioritization rule
Significantly damaged friable material in occupied areas is addressed first, followed by lesser damage, then intact material managed under O&M.
Management plan core
An AHERA plan contains inspection and assessment results, selected response actions, a schedule, and the operations and maintenance program.
Plan content requirement
The plan must list homogeneous areas, material locations and quantities, condition assessments, response actions, timetables, and responsible parties.
Periodic surveillance
A visual check of asbestos-containing material condition performed at least every six months, with results recorded and used to update the plan.
Plan preparer
The management plan is developed by an accredited management planner using findings from an accredited inspector's inspection and assessment.
O&M program purpose
An O&M program controls activities that may disturb asbestos during maintenance, repair, cleaning, and minor renovation to prevent fiber release.
Specialized cleaning
Cleaning of asbestos-contaminated surfaces using HEPA vacuuming and wet wiping; dry sweeping and dusting are prohibited because they disperse fibers.
O&M training
Workers whose duties may disturb asbestos receive asbestos awareness training, with more detailed training required for those performing O&M work.
O&M applicability
O&M is appropriate for asbestos material in good condition that is unlikely to be significantly disturbed by normal building activity.
Warning signage
Labels or signs identify asbestos-containing materials and restricted areas so occupants and workers avoid disturbing them.
Accreditation requirement
Inspectors and management planners must complete an EPA-approved course and pass an exam, with annual refresher training for management planners.
Record availability
Inspection records, assessments, and the management plan must be kept on site and made available to regulators and the public.
Annual notification
Written notice to parents, teachers, and employee organizations each year describing the plan's availability and any asbestos response actions.
Plan update trigger
Reinspection findings, completed response actions, or changed material conditions require revision of the management plan and related notifications.
Plain-language communication
Notifications should describe the location and condition of asbestos material and the actions being taken in terms occupants can readily understand.
Notification recordkeeping
Copies of notifications, updates, and surveillance records are retained with the management plan to document compliance.