AHERA Project Designer study materials
AHERA Project Designer study resources

AHERA Project Designer key terms

AHERA Project Designer · Get comfortable with the vocabulary.

Asbestos-Containing Material (ACM)

Any material or product that contains more than one percent asbestos by weight, as determined using polarized light microscopy or an equivalent method accepted under the applicable regulation.

Related: Presumed ACM, Bulk Sample
Category I Nonfriable ACM

Nonfriable asbestos-containing material that is unlikely to become friable when disturbed, such as packings, gaskets, resilient floor coverings, and asphalt roofing products that are not friable.

Related: Category II Nonfriable ACM, Friable
Category II Nonfriable ACM

Any nonfriable asbestos-containing material that is not Category I, such as cementitious siding, transite pipe, and asphalt roofing that may become friable under demolition or severe handling.

Related: Category I Nonfriable ACM, Regulated Asbestos-Containing Material
Friable

Describes material that can be crumbled, pulverized, or reduced to powder by hand pressure when dry, and therefore readily releases airborne fibers during disturbance.

Related: Nonfriable, Fiber Release
Presumed ACM

Material assumed to contain asbestos because it has not been sampled or because sampling results are unavailable, and which must be treated as asbestos-containing until proven otherwise.

Related: Asbestos-Containing Material (ACM), Bulk Sample
Bulk Sample

A physical portion of a suspect material collected and analyzed in a laboratory to determine asbestos content, typically by polarized light microscopy with gravimetric or point-counting methods.

Related: Polarized Light Microscopy (PLM), Presumed ACM
Polarized Light Microscopy (PLM)

A laboratory technique that identifies asbestos minerals in bulk samples by their optical properties, including refractive index, birefringence, and extinction behavior under polarized light.

Related: Bulk Sample, Point Counting
Point Counting

A quantitative microscopic method in which a trained analyst counts asbestos and non-asbestos particles on a prepared slide to estimate the percentage of asbestos in a bulk sample.

Related: Polarized Light Microscopy (PLM), Bulk Sample
Homogeneous Area

A surface area of material that is uniform in color and texture, so that a single set of representative samples can characterize the asbestos content of the entire area.

Related: Bulk Sample, Presumed ACM
Regulated Asbestos-Containing Material (RACM)

A regulatory classification covering friable asbestos material, Category I and II nonfriable material that has become friable, and nonfriable material that will be disturbed in a way that crushes or pulverizes it.

Related: Category I Nonfriable ACM, Category II Nonfriable ACM
National Emission Standards for Hazardous Air Pollutants (NESHAP)

Federal Clean Air Act regulations that set work practice and emission control requirements for asbestos handling, including notification, wetting, packaging, and disposal obligations.

Related: Regulated Asbestos-Containing Material (RACM), Waste Shipment Record
AHERA

The Asbestos Hazard Emergency Response Act, a federal law requiring inspection, management planning, and response actions for asbestos in schools, and establishing accreditation for asbestos professionals.

Related: Accredited Project Designer, Management Plan
Accredited Project Designer

A person who has completed required training and passed an examination, and who is responsible for designing asbestos response actions and preparing the specifications and drawings for a project.

Related: AHERA, Abatement Specification
Management Plan

A written document prepared for a school or facility that describes the location and condition of asbestos-containing material and the response actions planned to manage it over time.

Related: AHERA, Operations and Maintenance Program
Operations and Maintenance (O&M) Program

An ongoing program of work practices, training, and cleaning designed to prevent disturbance of asbestos-containing material that remains in place and to minimize fiber release during routine activities.

Related: Management Plan, Encapsulation
Abatement

A response action that removes, encapsulates, or encloses asbestos-containing material, or that prepares damaged material for disposal, in order to prevent fiber release.

Related: Removal, Encapsulation, Enclosure
Removal

An abatement method in which asbestos-containing material is physically taken out of a building or structure and disposed of as regulated waste.

Related: Abatement, Waste Shipment Record
Encapsulation

An abatement method in which a sealant is applied to the surface of asbestos-containing material to bind the fibers and prevent their release, without removing the material.

Related: Enclosure, Abatement
Enclosure

An abatement method in which a permanent airtight barrier is built around asbestos-containing material to isolate it from occupied space, leaving the material in place.

Related: Encapsulation, Abatement
Glovebag

A sealed plastic bag with built-in gloves and access ports that lets a worker remove small amounts of asbestos-containing material while keeping hands isolated from the work area.

Related: Negative Pressure Enclosure, Wetting
Negative Pressure Enclosure

A containment built around a work area and kept under lower air pressure than surrounding spaces, so that air flows inward and any released fibers are captured by filtration.

Related: HEPA Filter, Glovebag
HEPA Filter

A high-efficiency particulate air filter rated to remove at least 99.97 percent of airborne particles of 0.3 micrometers in diameter, used on vacuums and ventilation units in abatement work.

Related: Negative Pressure Enclosure, Air Monitoring
Wetting

The practice of soaking asbestos-containing material with water or a wetting agent before and during disturbance to suppress dust and reduce airborne fiber release.

Related: Friable, Fiber Release
Fiber Release

The emission of asbestos fibers into the air when material is disturbed, damaged, cut, sanded, or otherwise physically broken apart.

Related: Friable, Wetting
Abatement Specification

A written document that defines the scope, methods, materials, sequence, and quality requirements of an asbestos abatement project, and forms part of the contract documents.

Related: Accredited Project Designer, Scope of Work
Scope of Work

The portion of project documents that describes exactly what work is to be performed, including quantities, locations, and boundaries of the abatement area.

Related: Abatement Specification, Pre-Bid Conference
Pre-Bid Conference

A meeting held before bids are submitted at which the project designer explains the scope and specifications and answers contractor questions so that bids are based on a common understanding.

Related: Scope of Work, Abatement Specification
Respiratory Protection Program

A written employer program covering respirator selection, fit testing, medical evaluation, training, and maintenance requirements for workers who may be exposed to airborne asbestos.

Related: Fit Test, Permissible Exposure Limit
Fit Test

A qualitative or quantitative test that checks whether a tight-fitting respirator seals properly against a worker's face before the respirator is used.

Related: Respiratory Protection Program, Permissible Exposure Limit
Permissible Exposure Limit (PEL)

The legally enforceable maximum airborne concentration of asbestos to which a worker may be exposed, averaged over a specified time period.

Related: Excursion Limit, Respiratory Protection Program
Excursion Limit

A short-term ceiling on airborne asbestos concentration that must not be exceeded over a brief sampling period, regardless of the longer-term average exposure.

Related: Permissible Exposure Limit (PEL), Air Monitoring
Air Monitoring

The collection and laboratory analysis of air samples to measure airborne asbestos fiber concentrations during abatement, after completion, or in occupied areas.

Related: Phase Contrast Microscopy (PCM), Clearance
Phase Contrast Microscopy (PCM)

A rapid, low-cost laboratory method that counts all fibers in an air sample regardless of mineral type, and is the standard method for most abatement air monitoring.

Related: Air Monitoring, Transmission Electron Microscopy (TEM)
Transmission Electron Microscopy (TEM)

A high-resolution laboratory method that identifies and counts asbestos fibers specifically by their structure and elemental composition, used for definitive clearance and verification sampling.

Related: Phase Contrast Microscopy (PCM), Clearance
Clearance

The formal determination, based on visual inspection and satisfactory air sampling results, that a containment area is clean enough to be released for reoccupancy or further work.

Related: Air Monitoring, Transmission Electron Microscopy (TEM)
Waste Shipment Record

A document that tracks regulated asbestos waste from the generation site to the disposal facility, confirming proper transport and disposal and retained as a project record.

Related: Regulated Asbestos-Containing Material (RACM), Removal
Chain of Custody

A documented record of who collected, handled, and transported a sample at each step, used to show that samples and results are reliable and unaltered.

Related: Bulk Sample, Air Monitoring
Project Recordkeeping

The organized retention of documents such as inspection reports, specifications, air monitoring data, waste records, and clearance results to demonstrate compliance after a project ends.

Related: Waste Shipment Record, Chain of Custody