You are the general manager of a 220-room full-service hotel in a competitive downtown market. The hotel is 18 years old and has not undergone a major renovation in 12 years. Guest satisfaction scores (GSS) have declined from 82 to 74 over the past two years, primarily due to comments about dated bathrooms, worn furniture, and slow Wi-Fi. The hotel's RevPAR index has fallen from 105 to 98. The owner has approved a $6 million renovation budget but wants it completed in two phases over two years to minimize disruption. Phase 1 would cover guest rooms (bathrooms, furniture, carpet, Wi-Fi) at $4 million; Phase 2 would cover public areas and meeting space at $2 million. The hotel's current occupancy is 72% with an ADR of $180. The competitive set's average occupancy is 75% with an ADR of $175. The hotel has a strong group base (40% of room nights) but is losing corporate transient business. The owner is concerned about ROI and wants a recommendation on sequencing and scope.

1. Evaluate the proposed two-phase renovation plan. What are the risks and benefits of this sequencing? Should you recommend a different approach?

Read the worked answer

The two-phase plan has merits but also risks. Benefits: Phasing minimizes revenue disruption and spreads capital outlay. Focusing on guest rooms first directly addresses the biggest driver of GSS decline (bathrooms, furniture, Wi-Fi) and should improve the guest experience quickly. Risks: Public areas will remain dated for another year, which may continue to hurt the hotel's image, especially for group business that uses meeting space. The hotel might lose group bookings if meeting space is not updated. Also, construction in phases can create a 'construction zone' perception for an extended period.

Recommendation: Keep the two-phase approach but consider accelerating Phase 1 to six months and starting Phase 2 immediately after, with a compressed timeline. Alternatively, if the hotel can manage disruption, a single-phase renovation over 12 months might be better for market perception. However, given the group base, phasing may be necessary to avoid displacing group business. I would recommend: Phase 1 (guest rooms) start immediately and complete within 8 months, with work done floor by floor to minimize displacement. Phase 2 (public areas) start right after Phase 1, but schedule the meeting space renovation during low-demand periods (e.g., holidays). Also, invest in a temporary Wi-Fi upgrade immediately to address the most vocal complaint. The key is to communicate the renovation to guests and group clients, and to ensure that the renovated product is reflected in pricing and sales efforts.

2. Calculate the potential ROI of the renovation. What metrics would you use to justify the investment to the owner?

Read the worked answer

ROI calculation should consider incremental revenue and cost savings. Current RevPAR = 72% * $180 = $129.60. Competitive set RevPAR = 75% * $175 = $131.25. The hotel's RevPAR index is 98, meaning it underperforms the comp set. After renovation, aim to increase RevPAR index to 105 (historical level). Target RevPAR = 105% * $131.25 = $137.81. Incremental RevPAR = $137.81 - $129.60 = $8.21. Annual incremental room revenue = $8.21 * 220 rooms * 365 days = $659,000. Assuming 70% flow-through to GOP, incremental GOP = $461,000. Additionally, consider increased group rates and ancillary spending. The $6 million investment yields a 7.7% return on incremental GOP alone, but also consider the impact on asset value. Using a 10x EBITDA multiple, the incremental value could be $4.6 million, plus the renovation extends the hotel's life. Other metrics: payback period (approx. 13 years on GOP alone, but shorter if considering value), IRR, and NPV. Also, consider the cost of not renovating: continued decline in GSS and RevPAR. Justify with market data: competitors have renovated, and guest expectations have risen. The owner should see this as necessary to maintain market share.