AISC CSE · Give each week a clear focus.
8 weeks · About 7 hours per week
Personnel and organization
Map reporting lines, role boundaries, and accountability interfaces for a structural engineering team on a one-page chart.
Distinguish the responsibilities of the engineer of record, delegated designer, checker, and quality reviewer across three written scenarios.
Draft an escalation path for technical disagreements and nonconformance reporting.
Self-test 20 items on personnel roles and accountability, score at least 80%, and log every missed item with a correction note.
Your checkpoint
One-page organization and accountability map plus a scored 20-item self-test at 80% or higher with a correction log.
Personnel and organization & Experience and documented procedures
Convert the accountability map into a documented procedure checklist for project initiation, checking, and approval.
Write five document-control rules covering revisions, approvals, transmittals, retention, and superseded copies.
Trace two self-created project record sets through the checklist and identify gaps.
Build a 12-item audit checklist that links personnel roles to documented procedure steps.
Your checkpoint
Documented procedure checklist and 12-item audit checklist validated by a gap review of two self-created project record sets.
Experience and documented procedures
Draft a project quality plan outline with document hierarchy, review stages, and record retention.
Define acceptance criteria for calculations, drawings, and specifications in a one-page matrix.
Create a revision-control log template and simulate three revision cycles.
Explain in a 150-word written summary how documented procedures support traceability.
Your checkpoint
Project quality plan outline plus a revision-control log showing three simulated revision cycles with all approval fields completed.
Experience and documented procedures & Knowledge and competence
Build a competence matrix that maps tasks to required knowledge, experience, and verification methods.
Write three competency-based interview questions with scoring anchors for structural review roles.
Design a training record template that links task authorization to evidence.
Self-assess against the matrix and create a gap-closing plan with target dates.
Your checkpoint
Competence matrix and gap-closing plan covering at least 10 tasks, plus three scored interview question sets.
Knowledge and competence
Differentiate knowledge, skill, and experience requirements for three role levels.
Draft a supervised-work progression from trainee to independent reviewer with sign-off gates.
Create a 10-item scenario quiz on competence decisions and score at least 80%.
Audit sample training records for completeness and identify three improvement actions.
Your checkpoint
Role progression framework with sign-off gates and a scored 10-item competence quiz at 80% or higher.
Equipment and facilities
Inventory equipment and facilities needed for analysis, drafting, testing, and document storage.
Write calibration, maintenance, and verification schedules for three critical tools or systems.
Define environmental and access controls for records and computing resources.
Perform a mock facility and equipment readiness review and log findings.
Your checkpoint
Equipment and facility register with maintenance and calibration schedule plus mock readiness review findings log.
Commitment to quality and error prevention & Experience and documented procedures
Map error sources across intake, analysis, checking, approval, and issuance.
Write a nonconformance and corrective-action procedure with root-cause prompts.
Design three leading quality indicators and a monthly review cadence.
Conduct a mock root-cause analysis on one self-created error case.
Your checkpoint
Error-prevention map, corrective-action procedure, and one completed mock root-cause analysis with three indicators.
Commitment to quality and error prevention & Personnel and organization
Integrate all five domains into a one-page quality system crosswalk.
Complete a timed 80-item cumulative self-test and score at least 85%.
Revise weak areas using the correction log and produce a final 20-rule personal checklist.
Present a 10-minute mock audit walkthrough linking personnel, procedures, competence, equipment, and error prevention.
Your checkpoint
Integrated quality system crosswalk, timed 80-item self-test score at 85% or higher, and final 20-rule checklist.
Milestones
Week 4: Domain 1 and domain 2 foundation artifacts are complete; a cumulative 40-item self-test covering domains 1 and 2 is scored at 80% or higher, with every missed item explained in the correction log.
Week 6: Domain 3 and domain 4 artifacts are complete; a cumulative 60-item self-test covering domains 1 through 4 is scored at 80% or higher, with corrective actions recorded for all misses.