Landscape Design and Planning

  • Bubble diagrams precede schematic plans: they map functional zones and circulation before any dimensional design is drawn.

  • The design process sequence is site inventory and analysis, program development, schematic design, design development, construction documents, then bidding and construction observation.

  • A site inventory records topography, soils, drainage patterns, sun and wind exposure, existing vegetation, views, and utilities before any design decision is made.

  • Scale ratios: 1:10 shows detail planting, 1:50 to 1:100 shows site plans, 1:500 and smaller shows master planning.

  • Human circulation clearances: 0.9 m minimum for a single pedestrian path, 1.5 m for two people passing, 1.2 m for a wheelchair turning space.

  • The rule of thirds and golden ratio (about 1.618) are proportion tools for locating focal points and dividing spaces.

  • Hierarchy in plan is expressed through path width, paving material change, and planting mass, not through signage alone.

  • A program statement lists required spaces, quantities, and performance criteria before form-making begins; it is the client brief translated into design criteria.

Quick reference

Plant Selection and Horticulture

  • Hardiness zones reflect average annual minimum temperature; heat zones reflect days above 30 C, and both must be satisfied for reliable plant performance.

  • Right plant, right place: match the plant's mature height, spread, root volume, light requirement, soil pH, and moisture regime to the actual site conditions.

  • Soil pH controls nutrient availability: iron and manganese become deficient above pH 7.5, and phosphorus locks up below pH 5.5.

  • Planting density rule: space plants at roughly half to two-thirds of their mature spread to allow canopy closure without overcrowding.

  • Nursery stock grades: bare root, container-grown, and balled-and-burlapped; B&B stock loses a substantial portion of its root system and needs establishment care.

  • Succession and layering: canopy trees, understory trees, shrubs, herbaceous perennials, and groundcover form a vertical structure that suppresses weeds and supports habitat.

  • Alleopathy example: juglone from Juglans nigra (black walnut) inhibits growth of many ornamentals within the root zone.

  • Xeriscape principles: appropriate zoning of turf, soil improvement, efficient irrigation, mulching, and limited turf area reduce water demand.

Quick reference

Landscape Construction and Materials

  • Concrete mix for paving is typically 1:2:4 (cement:sand:aggregate) by volume; a 28-day compressive strength of 20-25 MPa suits pedestrian paving.

  • Concrete expansion joints are spaced at 1.5-3 m and control joints at 1-1.5 times slab thickness to control cracking.

  • Base course for pedestrian paving is typically 100-150 mm of compacted granular material; vehicular paving needs 200-300 mm.

  • Compaction of granular base is specified as a percentage of maximum dry density (typically 95%) from a standard or modified Proctor test.

  • Mortar for stone and brick is typically 1:3 or 1:4 cement to sand; lime is added for workability and flexibility.

  • Decking joist spacing: 400-600 mm for timber decking boards, with board gaps of 5-8 mm for drainage and expansion.

  • Retaining walls above about 1 m height generally require engineering design, drainage behind the wall, and a geotextile-wrapped drainage aggregate.

  • Material takeoff formula: quantity = area x thickness x density; use bulk densities such as concrete 2400 kg/m3, sand 1600 kg/m3, topsoil 1300-1600 kg/m3.

Quick reference

Site Grading and Drainage

  • Grading rule: slope away from buildings at a minimum of 2% for the first 3 m to direct surface water away from foundations.

  • Typical surface drainage slopes: 1-2% for turf and lawn, 1.5-2% for paved walks, 1% minimum for paved surfaces, and 0.5-1% for drainage swales.

  • Contour lines connect points of equal elevation; contour interval is the vertical distance between adjacent contours, and closer spacing means steeper slope.

  • Slope formula: percent slope = (rise / run) x 100; a 1:20 slope equals 5%.

  • Cut and fill volumes are balanced to minimize earthwork cost; the balance point is where cut equals fill and haul distance is minimized.

  • A swale is a shallow vegetated channel that conveys and infiltrates runoff; a berm is a raised mound used to block views, noise, or water.

  • Stormwater detention stores runoff temporarily and releases it at a controlled rate; retention holds water permanently.

  • Runoff volume estimate uses the rational method: Q = C x i x A, where C is the runoff coefficient, i is rainfall intensity, and A is area.

Quick reference

Irrigation and Water Management

  • Sprinkler head spacing follows head-to-head coverage: spacing equals the throw diameter so each head reaches the adjacent head.

  • Application rate in mm/hr = (flow rate in L/hr) / (area in m2); it should not exceed the soil infiltration rate to avoid runoff.

  • Drip irrigation operates at 50-150 kPa and delivers 1-4 L/hr per emitter, applying water directly to the root zone.

  • Irrigation zones should group plants by water need, sun exposure, soil type, and sprinkler type; turf and shrubs belong on separate valves.

  • A rain sensor or soil moisture sensor overrides the controller and is required in many water-conservation codes.

  • Distribution uniformity measures how evenly water is applied; low uniformity means overwatering in wet spots and stress in dry spots.

  • Reference evapotranspiration (ETo) times a crop coefficient (Kc) gives plant water use: ETc = ETo x Kc.

  • Backflow prevention is mandatory on any irrigation system connected to a potable supply; an atmospheric vacuum breaker or reduced-pressure zone assembly is used.

Quick reference

Landscape Maintenance and Management

  • Mowing height rule: never remove more than one-third of the leaf blade in a single cut; mow higher in summer heat stress.

  • Pruning timing: prune spring-flowering shrubs after bloom, and summer-flowering shrubs in late winter or early spring before new growth.

  • Fertilizer application rate is expressed as kg of nitrogen per 100 m2 per year; the N-P-K label gives the percentage of each nutrient by weight.

  • Fertilizer calculation: kg of product = (desired kg N) / (percent N in product).

  • Mulch depth of 50-75 mm suppresses weeds, conserves moisture, and moderates soil temperature; keep mulch clear of trunks to prevent rot.

  • Integrated pest management (IPM) sequence: prevention and cultural controls first, then biological, then targeted chemical as a last resort.

  • Turf renovation includes aeration, dethatching, overseeding, and topdressing; core aeration relieves compaction and improves infiltration.

  • A maintenance schedule is organized by season and task frequency: weekly, monthly, seasonal, and annual.

Quick reference

Sustainability and Environmental Practices

  • The three pillars of sustainability are environmental, social, and economic; a sustainable design must satisfy all three.

  • Stormwater best management practices (BMPs) include rain gardens, bioswales, permeable paving, green roofs, and cisterns.

  • Low-impact development (LID) manages rainfall as close to its source as possible through infiltration, storage, and evapotranspiration.

  • Native and locally adapted plants reduce irrigation, fertilizer, and pesticide inputs and support local pollinators and wildlife.

  • Life cycle assessment (LCA) evaluates environmental impacts from material extraction through disposal; embodied carbon is the CO2 emitted in producing a material.

  • Soil organic matter improves water-holding capacity, structure, and nutrient cycling; compost amendment is a primary soil-health strategy.

  • Water conservation strategies include drought-tolerant planting, efficient irrigation, rainwater harvesting, and reducing turf area.

  • Green infrastructure provides ecosystem services such as cooling, air filtration, carbon sequestration, and habitat, which can be quantified and credited.

Quick reference

Business, Estimating, and Project Management

  • Overhead is indirect cost (office, insurance, equipment) not tied to a specific project; profit is a separate markup above cost.

  • Markup is applied to cost; margin is profit as a percentage of the selling price. Margin = markup / (1 + markup) and markup = margin / (1 - margin).

  • Labor cost = crew hours x hourly wage x a labor burden factor (typically 1.3-1.6 for taxes, insurance, and benefits).

  • Quantity takeoff: measure lengths, areas, and volumes from drawings, then apply unit costs to obtain a cost estimate.

  • Contingency of 5-10% is added to estimates to cover unknowns; larger for early-stage or high-risk work.

  • A change order documents scope changes, their cost, and their schedule impact, and must be approved before work proceeds.

  • A critical path is the longest sequence of dependent tasks; any delay on the critical path delays the whole project.

  • Cash flow management tracks when money is received versus spent; progress payments and retainage affect project liquidity.