AMPP Bridge Coatings · Give each week a clear focus.

8 weeks · About 8 hours per week

Week 1

Surface Preparation and Substrate Condition

  • Identify and rank rust and mill-scale grades using visual reference criteria, from fully rusted through blast-cleaned surfaces.

  • Compare abrasive blasting media and specify the surface profile range each produces on steel.

  • Translate cleanliness and profile requirements into pass/fail field criteria an inspector can apply without ambiguity.

  • Explain how substrate defects - laminations, weld spatter, sharp edges, soluble salts, and residual coatings - degrade coating performance.

Your checkpoint

A one-page substrate condition decision matrix mapping six substrate conditions to required preparation method and acceptance criteria, plus 25 self-written flashcards passed at 90% recall.

Week 2

Surface Preparation and Substrate Condition & Coating Materials, Selection, and Specification

  • Differentiate abrasive blasting, power-tool cleaning, water jetting, and hand cleaning by achievable cleanliness, profile, and production rate.

  • Select appropriate preparation methods for concrete, galvanized, and previously coated bridge substrates.

  • Outline the building blocks of a coating system - primer, intermediate, and topcoat - and state the function of each.

  • Connect surface preparation quality to adhesion and long-term performance by tracing common failure mechanisms back to preparation faults.

Your checkpoint

A comparison table of five preparation methods listing standard reference, achievable cleanliness and profile, production rate, and limitations, plus a 20-question self-quiz scored at 80% or better.

Week 3

Coating Materials, Selection, and Specification

  • Classify binder chemistries - epoxy, polyurethane, polysiloxane, zinc-rich, and alkyd - by cure mechanism, strengths, and service limitations.

  • Calculate volume solids, wet film thickness, dry film thickness, and theoretical coverage for a given coating and area.

  • Match candidate coating systems to bridge exposure zones: atmospheric, splash, immersion, and buried.

  • Interpret a specification for DFT per coat, recoat windows, stripe coat requirements, and VOC limits.

Your checkpoint

A written mock coating specification for one bridge exposure zone covering surface preparation, full system, DFT per coat, and acceptance criteria, scored against a 10-point self-built rubric.

Week 4

Coating Materials, Selection, and Specification & Coating Application and Environmental Conditions

  • Explain airless spray, conventional spray, brush, and roller application and the defects characteristic of each.

  • Identify environmental limits that govern application: ambient temperature, steel temperature, dew point spread, relative humidity, and wind.

  • Describe recoat windows and explain the consequences of exceeding them.

  • Summarize specification requirements that link material selection to application method.

Your checkpoint

A 40-question cumulative quiz covering Domains 1 and 2 scored at 80% or better, with a written error log giving a corrected explanation for every missed item.

Week 5

Coating Application and Environmental Conditions

  • Calculate dew point and steel temperature margin from given psychrometric data and determine go/no-go for application.

  • Sequence a bridge coating job from preparation through stripe coat, primer, intermediate, and topcoat, naming the hold points at each stage.

  • Diagnose common application defects - sagging, orange peel, dry spray, pinholing, and mud cracking - and trace each to its root cause.

  • Apply stripe coating and edge-retention requirements to difficult geometries such as welds, bolts, and cut edges.

Your checkpoint

A field-ready environmental conditions worksheet and go/no-go checklist containing five worked dew-point calculations, all correct, plus a defect-cause lookup table of at least ten defects.

Week 6

Inspection, Testing, and Quality Control

  • Select and properly use DFT gauges, holiday detectors, and adhesion test methods, including calibration and measurement-count rules.

  • Apply visual standards and acceptance criteria to both surface preparation and finished coating appearance.

  • Design inspection stages and hold points spanning preparation, application, cure, and final acceptance.

  • Interpret test data - chloride and salt contamination, cure checks, and adhesion results - against specification limits.

Your checkpoint

An inspection and test plan for a steel bridge coating project containing at least eight numbered hold points, each with its test method, frequency, and acceptance criterion.

Week 7

Inspection, Testing, and Quality Control & Safety, Regulations, and Project Documentation

  • Evaluate QA/QC records - daily reports, batch and lot records, calibration logs, and nonconformance reports - for completeness and traceability.

  • Identify the principal hazards of abrasive blasting and coating application and select controls using the hierarchy of controls.

  • Summarize regulatory requirements governing VOC content, lead-based paint disturbance, containment, and waste disposal.

  • Distinguish the roles and responsibilities of inspector, applicator, and owner across a coating project.

Your checkpoint

A job hazard analysis for a blast-and-coat operation plus a one-page regulatory compliance summary covering VOC, lead, containment, and waste handling.

Week 8

Safety, Regulations, and Project Documentation & Inspection, Testing, and Quality Control

  • Complete a full-length 100-question mock exam under timed conditions spanning all five domains.

  • Analyze missed items by domain and re-study the two weakest areas until each reaches 80%.

  • Recite documentation and recordkeeping requirements needed for project closeout and turnover.

  • Verify that safety, regulatory, and documentation content is recalled at the same level as technical coating content.

Your checkpoint

A timed 100-question mock exam scored at 85% or better, accompanied by a written remediation plan for any domain scoring below 80%.

Milestones

Week 2: Explain, without notes, the difference between cleanliness standard and surface profile, and pass the 20-question preparation self-quiz at 80% or better.

Week 4: Score at least 80% on the 40-question cumulative quiz for Domains 1 and 2, with every missed item resolved in the error log.

Week 6: Produce a complete inspection and test plan with eight or more hold points and correctly perform five dew-point and DFT calculations in a row.

Week 8: Score at least 85% on the timed 100-question mock exam, with no single domain below 80%.