AMPP CIP Level 2 study materials
AMPP CIP Level 2 study resources

AMPP CIP Level 2 cheat sheet

AMPP CIP Level 2 · Keep the key ideas within reach.

Quick reference

Advanced Coating Inspection and Role of the Inspector

  • An inspection plan defines hold points, witness points, and surveillance frequency before production work begins.

  • A hold point prevents further work until the inspector verifies the required characteristic and records acceptance.

  • A witness point is a notified inspection stage that work may pass if the inspector is absent, unless the contract states otherwise.

  • Inspector authority is normally limited to verifying conformance and reporting; approving specification deviations requires contract authority.

  • Stop-work authority exists only when granted by the contract or specification; otherwise the inspector documents and escalates the nonconformance.

  • Destructive tests require written approval and a repair procedure because they damage the applied coating system.

  • Instrument calibration status is verified and recorded before readings are accepted as inspection evidence.

  • Incoming coating materials are checked for batch number, shelf life, storage temperature, mixing ratio, and specification compliance.

  • A nonconformance report identifies the condition, location, requirement, objective evidence, disposition, and corrective action.

Quick reference

Coating Types, Formulation, and Selection

  • Epoxy coatings are two-component amine-cured systems with good chemical resistance; their recoat window is critical for intercoat adhesion.

  • Polyurethane topcoats are UV-stable and moisture-sensitive during cure; they are commonly applied over epoxy primers.

  • Zinc-rich primers protect steel cathodically; zinc dust content and binder type must match the specified product standard.

  • Coal tar epoxy is not UV-stable and is normally covered by a topcoat when exposed to sunlight.

  • Dry-film thickness equals wet-film thickness multiplied by the volume solids fraction of the coating.

  • Theoretical coverage in square metres per litre equals 1000 times volume solids divided by target dry-film thickness in micrometres.

  • Mixing ratio by volume must be followed; adding thinner beyond the product data sheet alters viscosity, VOC content, and cure.

  • Coating selection considers service environment, substrate, operating temperature, expected service life, and application constraints.

  • Exceeding the recoat window usually requires abrasion of the previous coat before applying the next coat.

Quick reference

Surface Preparation Methods and Standards

  • Solvent cleaning per SSPC-SP 1 removes oil, grease, dirt, and similar contaminants before abrasive blasting or power tool cleaning.

  • SSPC-SP 10 or ISO Sa 2½ is near-white blast cleaning; staining is limited to a small percentage of each unit area.

  • SSPC-SP 5 or ISO Sa 3 is white metal blast cleaning with no visible oil, grease, rust, mill scale, coating, or foreign matter.

  • ISO 8501-1 grades progress from Sa 1 light blast through Sa 2 thorough blast, Sa 2½ near-white blast, to Sa 3 white metal blast.

  • Abrasive blast profile improves mechanical adhesion; profile depth must fall within the coating manufacturer's specified range.

  • Soluble salts are measured by the Bresle method and reported as chloride concentration in micrograms per square centimetre.

  • Surface temperature must be at least 3°C or 5°F above dew point to prevent condensation during surface preparation and coating.

  • Relative humidity is commonly limited to 85% or less for solvent-borne coatings unless the product data sheet states otherwise.

  • Power tool cleaning per SSPC-SP 3 removes loose material; SSPC-SP 11 removes coatings to bare metal at specified areas.

Quick reference

Coating Application and Application Equipment

  • Airless spray atomizes coating by forcing it through a small tip at high hydraulic pressure.

  • Tip orifice size and fan angle are selected according to coating viscosity, desired film build, and surface geometry.

  • Applying a coat too soon after the previous coat can trap solvent; applying too late can cause intercoat adhesion failure.

  • Plural-component spray equipment meters and mixes base and catalyst at the specified ratio before delivery to the gun.

  • Stripe coats are applied by brush or roller to edges, welds, corners, and back of angles before full spray application.

  • Wet-film thickness is checked immediately after application; target wet-film thickness equals dry-film thickness divided by volume solids fraction.

  • Spray passes commonly overlap about 50% to produce uniform coverage without skips or heavy build.

  • Compressed air for conventional spray must be clean, dry, and oil-free; traps and filters are checked before use.

Quick reference

Inspection Instruments and Test Methods

  • Magnetic pull-off dry-film thickness gauges measure coatings on ferrous substrates and are verified with foil shims.

  • Eddy current dry-film thickness gauges measure coatings on nonferrous substrates and are not suitable for steel.

  • Holiday detectors locate pinholes, cracks, and thin spots; test voltage depends on coating thickness and the applicable standard.

  • Pull-off adhesion testing per ASTM D4541 records both the numerical result and the observed failure mode.

  • Cross-cut adhesion testing per ASTM D3359 uses a classification from 5B, no removal, to 0B, greater than 65% removal.

  • Surface profile is measured with comparator discs or replica tape; replica tape gives a more objective peak-to-valley reading.

  • Salt contamination is measured with a Bresle patch and conductivity meter, with chloride reported in micrograms per square centimetre.

  • Gloss is measured with a glossmeter at a specified angle, commonly 60 degrees or 85 degrees depending on gloss level.

  • Ambient relative humidity and surface temperature are measured with hygrometers and infrared thermometers before coating application.

Quick reference

Documentation, Reporting, and Inspection Records

  • Daily inspection records include date, time, location, weather, ambient conditions, surface temperature, dew point, readings, and inspector signature.

  • Nonconformance reports track description, cause, corrective action, disposition, and closure status.

  • Calibration records identify the instrument, calibration date, due date, and traceability to a recognized standard.

  • Test reports state the test method, acceptance criterion, measured result, pass or fail determination, location, date, and instrument used.

  • As-built coating records include the coating system, batch numbers, final dry-film thickness map, repairs, and acceptance status.

  • Records retention periods are defined by the contract and may extend beyond project completion.

  • Chain-of-custody records are required for samples sent to a laboratory for analysis.

  • Inspection records must be legible, dated, signed, and traceable to the specific area or component inspected.

Quick reference

Safety, Environment, and Jobsite Practices

  • Confined space entry requires a permit, atmospheric testing for oxygen, flammables, hydrogen sulfide, and carbon monoxide, plus ventilation and an attendant.

  • Abrasive blasting can generate respirable crystalline silica; controls include respiratory protection, ventilation, and dust suppression.

  • Solvent vapours and coating mists are flammable; ignition sources are controlled and equipment is bonded and grounded.

  • VOC content limits are regulated; compliance depends on product data, thinner addition, and application method.

  • Spill containment uses berms, absorbents, and proper disposal according to the safety data sheet and local hazardous waste rules.

  • Heat stress controls include monitoring wet-bulb globe temperature, hydration, and work-rest schedules.

  • Fall protection is required when working at height; harnesses, lanyards, and anchor points are inspected before use.

  • Used solvents, blast media, and paint containers are segregated and disposed of according to safety data sheets and local regulations.