Bypassed Hold Point and Ambient Logging Gap

AMPP Nuclear Coatings · Put your knowledge to work in context.

All case studies

Bypassed Hold Point and Ambient Logging Gap

During final QA review of a safety-related coating package, the inspector finds that the stripe coat hold point was signed by the applicator's foreman, not the QC inspector. The final DFT and holiday test records are complete and acceptable. The batch records show the correct mix ratio, but the ambient logging sheet has a four-hour gap on the same shift. The coating is in a post-LOCA sump area, and the system is scheduled for turnover in 48 hours. The specification requires independent QC verification at all hold points and continuous ambient records during application and cure. The foreman states the stripe coat was visually checked and no defects were found.

1. Can QA accept the package as complete? Identify the nonconformances and their safety significance.

Read the worked answer

No, not as complete. Two nonconformances exist: the stripe-coat hold point was signed by the applicator rather than independent QC, and the ambient record has a four-hour gap. The first undermines verification of a critical coverage step; the second leaves a period of application and cure unverified against environmental limits. Passing final DFT and holiday tests does not prove the stripe coat was correctly applied or that conditions were compliant during the gap.

In a post-LOCA sump, coating failure could generate debris and affect sump performance, so the significance is high. The package should be held, a nonconformance report opened, and the hold point treated as not closed until objective evidence or re-verification is obtained. A 48-hour turnover target does not override the hold.

2. What investigation and disposition options are defensible?

Read the worked answer

Investigate by interviewing the foreman and QC inspector, reviewing the shift log and any data-logger record, checking whether a second inspector was present, and examining the stripe coat where accessible. If the ambient gap can be backfilled with calibrated data-logger readings showing compliance, and independent QC can verify stripe coverage now by visual, thickness, or holiday testing, a conditional release with documented engineering evaluation may be defensible. If not, the affected area should be reworked or re-verified.

Disposition must be approved by responsible engineering and QA and recorded with root cause and corrective action for hold-point accountability and logging alarms. The package should not be signed until closure evidence is attached. The decision turns on evidence, not on the foreman's verbal assurance.