Project management and the project context

  • APM defines a project as a unique, transient endeavour undertaken to achieve planned objectives; project management is the application of processes, methods, knowledge, skills and experience to achieve those objectives.

  • Project = unique, temporary output; programme = related projects plus change managed together for benefits; portfolio = the whole collection of projects and programmes grouped to meet strategic objectives.

  • Core life cycle phases are concept, definition, deployment and transition; the extended life cycle adds adoption and benefits realisation, which normally occur after project closure.

  • Success criteria are the measures used to judge the project (time, cost, quality, benefits); success factors are the management inputs that raise the likelihood of success, such as clear objectives and sponsor support.

  • PESTLE analysis (political, economic, social, technological, legal, environmental) is used to assess the external context in which the project will be delivered.

  • A project differs from business as usual: the project is temporary and creates a unique output, whereas business as usual is permanent, repetitive and adopts that output into normal operations.

  • The baseline is the approved scope, schedule and cost (plus quality) against which actual performance is measured and all changes are assessed.

  • Uncertainty and complexity increase with novelty of the output, project size, number of interfaces and rate of external change; these drive the choice of life cycle and controls.

  • Trade-off rule: scope, schedule, cost and quality are interdependent, so an agreed change to one normally requires a compensating change to at least one other.

Quick reference

Project governance and organisation

  • Governance is the framework of authority, accountability and decision-making by which the project is directed, controlled and held to account for its performance.

  • Accountability cannot be delegated: the sponsor holds single-point accountability for the business case and provides senior-level ownership throughout the project life.

  • Typical governance roles are sponsor, project manager, project board or steering group, senior user, senior supplier and the PMO; role boundaries are defined before the project starts.

  • Organisation structures: functional (specialist home, weak project focus), matrix (weak, balanced or strong; dual reporting), and projectised (project manager has full authority over resources).

  • PMO mandates fall into three types: supportive (templates, guidance, advice), controlling (compliance checks, gate reviews, reporting) and directive (project managers report to and are managed by the PMO).

  • APM's Directing Change principles include a single point of accountability, separation of stakeholder management from project decision-making, competent sponsorship and clearly defined approval authorities.

  • Gate or stage reviews are authorised checkpoints that compare actual performance and the business case against plan before further funds and resources are committed.

  • Delegated financial authority (for example the value of change a manager may approve) is defined in the governance documentation and cannot be exceeded without escalation.

  • The business case is owned by the sponsor and re-tested at each gate; where forecast benefits no longer justify the cost, the recommended decision is to stop or re-scope the project.

Quick reference

Stakeholder engagement and communication

  • A stakeholder is any individual, group or organisation with an interest in, or influence over, the project; identification begins at concept and is reviewed continuously.

  • Power/interest grid decision rule: high power and high interest = manage closely; high power and low interest = keep satisfied; low power and high interest = keep informed; low power and low interest = monitor.

  • Number of communication channels for n people = n(n − 1)/2; the count doubles roughly in proportion to team size, so large teams need structured communication routes.

  • Communication methods are classified as push (email, report, distribution), pull (repository, intranet) and interactive (meetings, workshops); richer interactive media suit complex or ambiguous messages.

  • A communication plan specifies audience, information content, format or channel, timing and frequency, the sender responsible and the feedback mechanism used to confirm understanding.

  • Engagement states run from unaware through resistant, neutral and supportive to leading; the plan aims to move key stakeholders towards support.

  • Communication barriers fall into physical (noise, distance, time zones), semantic (jargon, language, ambiguity) and psychological (perception, emotion, distrust) categories.

  • Communication is only complete when feedback confirms the message has been received and understood; one-way broadcast does not demonstrate understanding.

  • Confidential or commercially sensitive information requires a specific disclosure agreement with the relevant stakeholder before it is shared.

Quick reference

Scope, schedule and resource management

  • Scope baseline = scope statement + work breakdown structure + WBS dictionary; it may only be altered through approved change control.

  • The WBS is a deliverable-oriented hierarchy; its lowest level is the work package, commonly sized at roughly 8–80 hours so it can be estimated, assigned and controlled.

  • Critical path is the longest path through the network; it has zero total float and any delay on it delays the project completion date.

  • Float: total float = LS − ES or LF − EF; free float is the time an activity may slip without affecting the earliest start of its successor.

  • PERT expected duration = (O + 4M + P) / 6; standard deviation = (P − O) / 6, where O, M and P are optimistic, most likely and pessimistic estimates.

  • Dependency types are finish-to-start, start-to-start, finish-to-finish and start-to-finish; leads and lags modify the gap between dependent activities.

  • Resource smoothing is time-constrained and uses only available float, keeping the end date; resource levelling is resource-constrained and may extend the end date.

  • Scheduling tools: Gantt chart for communicating the plan, critical path method for network analysis of float and duration, critical chain for buffered, resource-focused scheduling.

  • Prioritisation and compression: MoSCoW ranks requirements must/should/could/won't; timeboxing fixes time and resource and flexes scope; crashing adds resource, fast-tracking overlaps activities and raises risk.

Quick reference

Budgeting and cost control

  • Estimating methods: analogous (top-down, based on similar historic work), parametric (cost per unit or rate), bottom-up (built from the WBS, most accurate and slowest) and three-point (optimistic, most likely, pessimistic).

  • Cost baseline = sum of the work package and activity costs plus contingency; management reserve is held above the baseline and is not part of it.

  • Contingency covers known unknowns (identified risks); management reserve covers unknown unknowns; both require authorised release and reserve release changes the baseline.

  • Earned value terms: EV = % complete × budget at completion (BAC); PV = planned value of work scheduled; AC = actual cost incurred to date.

  • Cost variance CV = EV − AC; schedule variance SV = EV − PV; a positive value indicates favourable performance in each case.

  • Cost performance index CPI = EV / AC; schedule performance index SPI = EV / PV; a value below 1.0 indicates performance worse than plan.

  • Forecasting: EAC = BAC / CPI where current cost efficiency continues; EAC = AC + ETC where the remaining work is re-estimated; VAC = BAC − EAC.

  • To-complete performance index TCPI = (BAC − EV) / (BAC − AC): the cost efficiency required on remaining work to finish within the budget.

  • Cash flow is forecast with an S-curve; cost commitment (order placed), cost accrual (goods or services received) and cash payment occur at different points in time.

Quick reference

Risk and issue management

  • A risk is an uncertain event that, if it occurs, affects objectives; an issue is a risk that has already occurred and now requires active management.

  • Risk process: identify, assess (probability and impact), plan responses, implement and review, with communication throughout; the cycle repeats across the life cycle.

  • Risk score = probability × impact; scores are compared with tolerances to decide which risks are escalated and which are managed locally.

  • Threat responses are avoid, reduce (mitigate), transfer and accept; opportunity responses are exploit, enhance, share and accept.

  • Risk appetite is the willingness to take risk; tolerance is the measurable limit of acceptable variation; breaching tolerance triggers escalation to the next governance level.

  • A risk register records ID, description using cause–event–effect, probability, impact, score, owner, response, residual risk and any secondary risks created by the response.

  • The risk owner is accountable for monitoring and managing the risk; the action owner implements the agreed response; the two roles may be held by different people.

  • Proximity (how soon the risk may occur) and RBS category are recorded alongside the score to inform timing and ownership of responses.

  • Issue management follows a defined path: log the issue, assess impact, escalate within agreed timescales, assign an owner, apply a workaround or contingency, then close and review.

Quick reference

Quality management

  • Quality means conformance to requirements and fitness for purpose; grade is a design or feature category and is not the same as quality level.

  • Quality planning defines standards, acceptance criteria and the control methods; quality assurance checks that processes are being followed; quality control checks that products conform.

  • Quality assurance is process-based and preventive (audits, process reviews, method compliance); quality control is product-based and detective (inspection, measurement, testing).

  • Cost of quality = prevention + appraisal + internal failure + external failure; prevention and appraisal are conformance costs, failures are non-conformance costs, and external failure is usually the most expensive.

  • Verification asks whether the product is being built correctly to its specification; validation asks whether the correct product is being built to meet the user's need.

  • Review types run from informal peer review and walkthrough to formal inspection, with audits used to examine process compliance rather than a single product.

  • The quality register records planned quality activities, owners and results; the quality management plan records standards, responsibilities, control methods and acceptance criteria.

  • Continuous improvement uses the PDCA cycle (plan, do, check, act); lessons learned are captured throughout the project, not only at closure.

  • Acceptance criteria must be measurable and agreed with the customer before work on the deliverable begins.

Quick reference

Change control and configuration management

  • Change control steps: raise and record the request, assess impact (time, cost, quality, benefit, risk), decide at the authorised level, implement, verify and update the baseline and records.

  • The change authority (individual or change board) approves or rejects changes within the delegated limits set in the governance documentation; above those limits the change escalates.

  • Impact assessment must cover knock-on effects across the whole project, including other deliverables, dependencies, the business case and the benefits profile.

  • Configuration management comprises planning, identification, control, status accounting and verification or audit.

  • A configuration item is any product placed under configuration control (document, software, hardware, drawing); each has a unique identifier, version and status.

  • Baselines progress from functional to allocated to product; any change to a baselined item requires an approved change request before implementation.

  • Status accounting answers what item exists, in which version, where it is held and what its current status is; it underpins handover and in-service support.

  • Emergency changes may be implemented before approval to protect safety or continuity, but must be retrospectively approved and fully recorded.

  • The change log records every request with its assessment, decision, implementation status and closure, and is retained for audit and lessons learned.

Quick reference

Leadership and team management

  • Management creates order and consistency through planning, organising and control; leadership creates direction and commitment through vision, influence and example.

  • Tuckman's stages are forming, storming, norming, performing and adjourning; the leader's style should shift from directing to delegating as the team matures.

  • Situational leadership (Hersey and Blanchard) matches style to follower readiness: telling, selling, participating and delegating.

  • Belbin's nine team roles are coordinator, shaper, plant, implementer, resource investigator, monitor-evaluator, teamworker, completer-finisher and specialist; balance of roles matters more than individual brilliance.

  • Maslow's hierarchy runs physiological, safety, social, esteem and self-actualisation; lower-level needs generally dominate until they are met.

  • Herzberg: hygiene factors (pay, conditions, policy, supervision) prevent dissatisfaction but do not motivate; motivators (achievement, recognition, responsibility, growth) create satisfaction.

  • McGregor Theory X assumes people dislike work and need close control; Theory Y assumes people seek responsibility and self-direction; the assumption shapes management style.

  • Sources of power are legitimate, reward, coercive, expert and referent; expert and referent power sustain influence when formal authority is limited.

  • Thomas–Kilmann conflict modes are competing, collaborating, compromising, avoiding and accommodating; collaborating suits long-term outcomes when time and trust allow.

Quick reference

Procurement, contracts and benefits management

  • Procurement cycle: define the need, develop the sourcing strategy (make or buy, single or multiple source), prepare requirements, select the supplier, manage the contract and close it out.

  • Contract type allocates risk: fixed price puts cost risk on the supplier, cost-plus puts it on the buyer, target cost shares it against a target, and time and materials puts quantity risk on the buyer.

  • Decision rule: use fixed price when scope is well defined and stable; use cost-plus or time and materials when scope is uncertain or speed to start matters more than price certainty.

  • Tender documents: ITT (invitation to tender), RFQ (request for quotation) and RFP (request for proposal); evaluation criteria and weightings should be published in advance.

  • Key contract terms to manage: specification, KPIs and service levels, payment terms, liquidated damages, retention, warranties, the change procedure and termination provisions.

  • A benefit is a measurable improvement perceived as advantageous by a stakeholder; a dis-benefit is a negative outcome accepted by one or more stakeholders.

  • Benefits management: identify, define (benefits profile with owner, metric, baseline, target and realisation date), plan, realise and review.

  • Benefits are usually realised after project closure in operations, so the benefits realisation plan assigns post-project ownership and review points.

  • A benefits map or dependency network links project outputs to outcomes and to strategic objectives, showing what must change for benefits to be achieved.