APM PMQ study materials
APM PMQ study resources

APM PMQ study plan

APM PMQ · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Project management and the project context & Scope, schedule and resource management

  • Map all ten PMQ domains to their exam weighting and write a one-sentence distinction between project, programme, portfolio and business-as-usual

  • Decompose a realistic scenario project into a three-level work breakdown structure and derive a dependency-linked activity list from it

  • Calculate the critical path, total float and free float for two hand-drawn network diagrams, verifying each with a forward and backward pass

  • Explain in writing how the business case, project mandate, success criteria and benefits profile shape the definition of scope

Your checkpoint

A two-page foundation pack: domain weighting map, three-level WBS with activity list, and two fully solved network diagrams annotated with critical path and float

Week 2

Scope, schedule and resource management & Budgeting and cost control

  • Assign durations and resources to the week-1 activity list and plot the resulting resource histogram

  • Resolve a deliberate over-allocation by resource levelling and record the trade-off in duration, cost and float

  • Compare bottom-up, analogous, parametric and three-point estimating on a single scope item and justify the selection

  • Build a cost baseline covering direct and indirect cost, contingency and management reserve, reconciled to the approved budget

Your checkpoint

A resourced schedule and a cost baseline spreadsheet for the same project, with every estimating assumption logged

Week 3

Budgeting and cost control & Risk and issue management

  • Calculate CV, SV, CPI, SPI, EAC and VAC from three periods of earned value data and write a 150-word interpretation of the trend

  • Identify twelve risks for the scenario using structured prompts and classify each in cause-event-effect form

  • Score and rank the twelve risks on a 5x5 matrix using probability and impact definitions applied consistently

  • Write responses for the six highest-ranked risks covering avoid, reduce, transfer and accept, each with owner, trigger and residual risk

Your checkpoint

A risk register of twelve scored risks with owners, responses and triggers, plus a one-page earned value analysis with CPI/SPI and a forecast narrative

Week 4

Project governance and organisation & Risk and issue management

  • Draw the governance structure for the scenario: sponsor, project board, PMO, project manager and workstream leads, with decision rights for each

  • Draft terms of reference for the project board including quorum, reporting cycle and escalation thresholds

  • Trace how risk appetite and tolerances flow from governance documents into the risk process and escalation route

  • Complete a timed 60-question half paper covering domains 1, 4, 5 and 6 and log every incorrect answer by root cause

Your checkpoint

A governance one-pager (structure, roles, decision rights, tolerances) plus a scored half paper with a categorised error log

Week 5

Project governance and organisation & Stakeholder engagement and communication

  • Plot stakeholders on a power/interest grid and match each quadrant to a tailored engagement approach

  • Write a communication plan specifying audience, message, channel, frequency and owner for six stakeholder groups

  • Draft three difficult communications (slippage, scope pushback, escalated bad news) in a structured message format

  • Contrast functional, matrix and project organisational structures and state the project manager's authority and reporting lines in each

Your checkpoint

A stakeholder grid and full communication plan for the scenario covering six groups with named owners and frequencies

Week 6

Quality management & Change control and configuration management

  • Distinguish quality planning, quality assurance and quality control, and position each activity in the project lifecycle

  • Write acceptance criteria for four deliverables and select an appropriate review technique for each (peer review, inspection, audit)

  • Design an end-to-end change control process: request, impact assessment, decision, implementation and closure

  • Explain configuration management components (configuration items, baselines, version control, status accounting) and how they underpin change control

Your checkpoint

A completed change request form, a configuration item list and a quality plan with acceptance criteria for four deliverables

Week 7

Leadership and team management & Procurement, contracts and benefits management

  • Compare three leadership styles and match each to a team maturity level using a situational leadership model

  • Plan team formation, a motivation approach and a conflict-handling route for a scenario team of six

  • Select fixed-price, cost-plus or target-cost contract for three procurement scenarios and justify the resulting risk allocation

  • Build a benefits profile with owner, measure, baseline and realisation timing, and separate outputs, outcomes and benefits

Your checkpoint

A team leadership plan plus a procurement and benefits pack containing three justified contract recommendations and a four-benefit profile

Week 8

Project management and the project context & Project governance and organisation & Stakeholder engagement and communication & Scope, schedule and resource management & Budgeting and cost control & Risk and issue management & Quality management & Change control and configuration management & Leadership and team management & Procurement, contracts and benefits management

  • Sit two full-length timed mock papers under exam conditions and mark them against command-word expectations

  • Rewrite the ten weakest answers using the correct command word (explain, evaluate, justify) and an explicit structure

  • Condense each domain onto a single page of trigger facts, formulas and model names for final revision

Your checkpoint

Two marked mock papers with a remediation log, plus a ten-page condensed revision set (one page per domain)

Milestones

Week 2: Resourced schedule and cost baseline are complete, with contingency and management reserve shown as separate lines and reconciling to the approved budget total

Week 4: Half paper scored at least 60% overall with no single domain below 50%, and the error log shows each wrong answer traced to a cause

Week 6: First full-length mock completed under time; score at least 55%, with every domain 7 and 8 answer written in full command-word structure

Week 8: Two full mocks average at least 65% with every domain at 55% or above, and no root cause repeats in the final error log