The Addendum Nobody Read: Bid Mistake and Withdrawal

AR General Contractor · Put your knowledge to work in context.

All case studies

The Addendum Nobody Read: Bid Mistake and Withdrawal

You are bidding a 60,000 sf single-story medical office building as a lump sum. Two weeks before bid day, Addendum 3 raises the slab from 5 inches to 6 inches over 8 inches of base and adds 4,000 sf of mezzanine framing. Your chief estimator, working from the pre-addendum set, prices neither change. You carry a $180,000 "site utilities - allow" line as a lump sum inside an otherwise unit-priced schedule of values. Your bid of $8.42M is 4% under the next competitor and you are the apparent low bidder. Two days after the bid opening your estimator finds a $310,000 omission: the mezzanine framing plus the added rebar. You posted 5% bid security of $421,000. The owner wants the contract signed Friday.

1. Can you withdraw the bid, or must you sign? Analyze the mistake.

Read the worked answer

The distinction that decides it: was this a clerical mistake or an error in judgment?

  • Clerical/transcription errors - a decimal point, a transposed quantity, a line omitted from the recap - are the classic ground for rescission, provided the mistake is material and the other party had no reason to rely on it being correct.
  • Errors in judgment - failing to read an addendum, estimating productivity wrong, missing a system entirely - are almost universally not relief grounds. The bidder owns its own estimating process.

Here you have a mixed case. Missing the addendum is squarely a judgment/process failure. The rebar quantity error may be clerical if the takeoff shows the quantity and the recap dropped it - go find out which it is before you call the lawyer, because the answer changes the strategy.

Factors a court or agency weighs: the magnitude of the error relative to bid size ($310,000 on $8.42M is about 3.7% - material but not absurd); whether the bid was unconscionably low; whether the error was palpable on the face of the bid (was it 15% under the field, or 4%?); whether the owner has changed position in reliance; and prompt notice.

Your facts cut against you: being only 4% under the next bidder means the error was not apparent on the face of the bid - the owner had no duty to inquire, which weakens a "mutual mistake" theory. Notice two days after opening is prompt, which helps.

Bottom line: you probably cannot walk away free, and you certainly cannot if the only defect is the unread addendum.

2. Assume you must perform. How do you recover the $310,000, and what does the bid security mean here?

Read the worked answer

Bid security: 5% of $8.42M is $421,000. If you refuse to sign, the owner's remedy is generally to keep the security - for $421,000 to save $310,000 is a losing trade, and they may also pursue the difference to the next bidder. So the security tilts the analysis toward performing.

Recovery paths, in order of realistic value:

  1. Value engineering before signing. Offer the owner an equivalent-cost substitution: reduce the mezzanine to a lighter steel/joist system, revise the slab mix and reinforcement to a design that meets 6-inch performance with less steel, or re-sequence to save general conditions. A $200,000 recovery through VE is better than a $310,000 claim you lose.
  2. Preserve the change-order channel. The added slab depth and mezzanine are in the contract documents via the addendum, so you cannot claim them as extra - you swallowed them at bid. Do not waste credibility trying.
  3. Look for genuine scope gaps. If the addendum language is ambiguous as to whether the 4,000 sf is structural framing or just a slab edge, an RFI before contract execution can convert ambiguity into a clarified quantity - and a clarified quantity is negotiable.
  4. Read the unit-price schedule carefully. Confirm the base scope items are not also underpriced in a way that lets a quantity variation bail you out. If actual quantities exceed estimated quantities by more than the contract's variation threshold, a unit-price adjustment may be available.

What not to do: sign, then claim a mistake. Once you sign, you have warranted that you examined the documents; the claim dies.

3. You also have a $180,000 "allow" in an otherwise unit-priced schedule of values. Is that a problem, and how should you handle it?

Read the worked answer

Yes - it is both a commercial and an integrity problem.

Why it matters:

  • It is not an allowance unless the contract makes it one. An owner-controlled allowance has defined rules (documented reconciliation, owner approval of expenditures, unused funds returned). A bidder-invented "allow" is just a thin estimate disguised as a placeholder, and disputes over it will be resolved against the party that wrote it.
  • It creates an unbalanced-bid suspicion. A lump sum buried in a unit-price schedule can be front-loaded or back-loaded. If the $180,000 is genuinely low relative to the work, you will be doing the work at a loss and will be tempted to claim it as a changed condition - which you will lose, because you wrote the number.
  • It distorts the schedule of values used for progress payments, which can look like overbilling later.

How to handle it now:

  1. Convert it to a scope-based number before signing. Do a real takeoff of the site utilities: pipe lengths by size and material, trench depths, structures, tie-ins. Even a rough quantity × unit price is defensible; a round allowance is not.
  2. If it stays lumpy, disclose it. "Site utilities are priced as a lump sum based on the drawings dated X; if the utility plan is revised, we will price the change by unit rate." Written into the contract, this converts a weak spot into a defined boundary.
  3. Fix the schedule of values so the utility line is broken out by segment and can be billed against installed quantities.

Judgment: an "allow" you invented is an admission that you did not estimate the work. Either estimate it or define its boundary in writing.