ACLB license threshold
Arkansas Contractors Licensing Board requires a commercial contractor license for projects of $20,000 or more; below that threshold only local licenses or registrations may apply.
Mechanic's lien
A statutory claim against real property filed by a contractor, subcontractor, or supplier who furnished labor or materials and was not paid for them.
Lump-sum contract
The contractor agrees to a fixed total price for the entire defined scope, so the contractor bears the risk of quantity errors and cost overruns.
Cost-plus-fee contract
The owner reimburses actual job costs plus a fixed fee or percentage; the owner carries cost risk while the contractor's fee is protected.
Qualifying party
The individual who passes the licensing examination and meets experience requirements, through whom a construction business entity holds its contractor license.
Miller Act bond
Federal law requiring performance and payment bonds on federal construction contracts over $150,000, protecting the government and unpaid subcontractors and suppliers.
Retainage
A percentage of each progress payment withheld by the owner until substantial completion or another contract milestone, securing completion and correction of deficiencies.
Critical path
The longest continuous chain of dependent activities through the schedule network; it has zero total float and sets the shortest possible project duration.
Total float formula
Total float equals late start minus early start, or late finish minus early finish; an activity with zero float is on the critical path.
Cost Performance Index
CPI equals earned value divided by actual cost; a result below 1.0 means the work performed is costing more than the budget allowed.
Schedule Performance Index
SPI equals earned value divided by planned value; a result below 1.0 indicates the project has completed less work than scheduled at that point.
Fast-tracking
Overlapping design or construction activities that were planned to run sequentially in order to shorten duration; it increases coordination risk and rework exposure.
Substantial completion
The stage when work is sufficiently complete for its intended use, typically triggering owner occupancy, warranty start, and release of retainage under the contract.
Request for Information
A formal written question from the contractor to the designer seeking clarification of drawings or specifications; the answer becomes part of the contract documents.
Scale conversion
A scale of 1/4 inch equals 1 foot means a quarter inch on the drawing represents twelve inches of actual construction, a 1:48 ratio.
Board foot formula
One board foot equals thickness in inches times width in inches times length in feet, with the product divided by twelve.
Concrete volume formula
Cubic yards of concrete equal length times width times depth, all in feet, divided by twenty-seven for a rectangular placement.
Waste factor
A multiplier added to a net quantity to cover cutting, breakage, and overrun; order quantity equals net quantity times one plus the waste percentage.
Roof slope percentage
Slope percentage equals rise divided by run times one hundred; a 4:12 pitch is a rise of four over a run of twelve, about 33 percent.
Contour lines
Lines on a site or grading plan connecting points of equal elevation; closely spaced contours show steep terrain and widely spaced contours show flat ground.
Water-cement ratio
The ratio of water weight to cementitious material weight in a concrete mix; lower ratios raise strength and durability but reduce workability.
Air entrainment
Deliberate microscopic air bubbles in a concrete mix that provide freeze-thaw durability; exterior concrete typically contains about 4 to 7 percent entrained air.
Rebar concrete cover
The minimum distance from the surface of reinforcing steel to the concrete surface, protecting the steel from corrosion and providing fire resistance.
Standard Proctor test
A laboratory test that establishes a soil's maximum dry density and optimum moisture content; field compaction is specified as a percentage of that density.
Type X gypsum board
A gypsum panel with special core additives that earns a one-hour fire-resistance rating when installed as part of a tested assembly.
Lift thickness
The depth of one soil layer placed and compacted before the next layer is added; common maximum is eight to twelve inches.
Fall protection trigger
OSHA requires fall protection for construction workers exposed to falls of six feet or more, or who could fall into hazardous equipment or substances.
Excavation protective system
Required for trenches five feet deep or deeper unless a competent person finds no cave-in hazard; options are sloping, shoring, or shielding.
Trench ladder rule
In trenches four feet or deeper, a ladder, stair, or ramp must be provided and placed so no worker travels more than twenty-five feet laterally.
Spoil pile setback
Excavated material and equipment must be kept at least two feet from the edge of an excavation to reduce surcharge loading and collapse risk.
NPDES construction permit
Required for construction that disturbs one acre or more; the permit requires a stormwater pollution prevention plan and installed best management practices.
OSHA fatality reporting
Employers must report a work-related fatality within eight hours and an in-patient hospitalization, amputation, or loss of an eye within twenty-four hours.