AR General Contractor study materials
AR General Contractor study resources

AR General Contractor cheat sheet

AR General Contractor · Keep the key ideas within reach.

Quick reference

Business and Law

  • The Arkansas Contractors Licensing Board (ACLB) licenses commercial contractors; a license is required to bid or contract for commercial construction projects of $20,000 or more.

  • License classifications set a maximum single-project dollar limit; contracting for work above the licensed classification is a violation subject to board discipline.

  • Contract types allocate risk: lump sum (contractor bears quantity and cost risk), unit price (owner bears quantity risk), cost-plus and GMP (owner bears most cost risk).

  • Federal Miller Act requires performance and payment bonds on federal construction contracts exceeding $150,000, protecting the government and unpaid subcontractors and suppliers.

  • Arkansas workers' compensation coverage is required for employers with three or more employees.

  • Change orders should be written, priced, and signed before the work is performed; unsigned field directives create disputes over scope and payment.

  • A licensed business entity holds its contractor license through a qualifying party who passes the required exam and meets experience requirements.

  • Mechanic's lien rights are purely statutory: required notices and filing deadlines must be met exactly or the lien right is lost.

Quick reference

Project Management

  • Total float = Late Start − Early Start = Late Finish − Early Finish; an activity with zero total float lies on the critical path.

  • The critical path is the longest continuous chain of dependent activities through the network; it determines the shortest possible project duration.

  • Crashing shortens duration by adding resources and cost; fast-tracking shortens duration by overlapping activities and increases coordination and rework risk.

  • Earned value: CV = EV − AC and SV = EV − PV; positive values are favorable, negative values are unfavorable.

  • CPI = EV ÷ AC (under 1.0 means over budget); SPI = EV ÷ PV (under 1.0 means behind schedule).

  • Three-point (PERT) estimate = (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6.

  • A designer's review of a shop drawing does not relieve the contractor of responsibility for complying with the contract documents.

  • Substantial completion is the point at which work is usable for its intended purpose; it typically starts warranties, ends liquidated damages, and triggers retainage release.

  • In finish-to-start logic, a successor activity cannot begin until its predecessor is complete.

Quick reference

Estimating and Plan Reading

  • At a scale of 1/4 inch = 1 foot, one inch on the drawing equals 4 feet; multiply a scaled measurement by 48 to convert to inches of actual size.

  • Board feet = (thickness in inches × width in inches × length in feet) ÷ 12.

  • Concrete volume in cubic yards = (length ft × width ft × depth ft) ÷ 27.

  • Order quantity = net quantity × (1 + waste factor); waste covers cutting, breakage, and overrun.

  • An 8 × 8 × 16 inch concrete masonry unit lays up at 1.125 blocks per square foot of wall face with 3/8 inch joints.

  • Modular brick with 3/8 inch mortar joints yields approximately 6.75 bricks per square foot of wall face.

  • A slope of 1/4 inch per foot equals about 2 percent grade (0.25 ÷ 12 × 100).

  • Plans are top-down views, sections are vertical cuts through the building, and elevations are flat exterior or interior wall views.

  • Labor hours = quantity × unit labor rate; duration in days = labor hours ÷ (crew size × hours worked per day).

Quick reference

Construction Methods and Materials

  • Concrete is specified and tested for compressive strength at 28 days; 7-day breaks typically reach about 75 percent of design strength.

  • Lower water-cement ratio increases strength and durability but reduces workability; typical structural mixes fall near 0.40 to 0.50.

  • Air entrainment of roughly 4 to 7 percent provides freeze-thaw durability in exterior concrete.

  • Field compaction is commonly specified as a percentage (often 95 percent) of maximum dry density from a Standard Proctor test, placed in 8 to 12 inch lifts.

  • Structural steel wide-flange shapes are commonly ASTM A992; high-strength structural bolts are A325 or A490.

  • Type X gypsum board has a specially formulated core that earns a fire-resistance rating when installed in a tested assembly.

  • Vapor retarders are placed on the warm side of the insulation in cold climates to prevent condensation within the assembly.

  • Nominal lumber dimensions differ from actual: a 2 × 4 measures 1-1/2 inches by 3-1/2 inches.

  • Reinforcing steel must maintain specified concrete cover to protect against corrosion and provide fire resistance.

Quick reference

Jobsite Safety and Environmental Compliance

  • OSHA construction fall protection is required at 6 feet, on scaffolds at 10 feet, and for general industry at 4 feet.

  • Excavations 5 feet deep or more require a protective system (sloping, shoring, or shielding) unless a competent person determines there is no cave-in hazard.

  • A competent person must inspect excavations daily and after rain or other hazard-increasing events before workers enter.

  • Spoil piles and equipment must be kept at least 2 feet back from the excavation edge to limit surcharge loading.

  • Trenches 4 feet or deeper require a ladder, stair, or ramp within 25 feet of lateral travel for every worker.

  • Scaffolds need a stable base with a height-to-base ratio no greater than 4:1, top rails 38 to 45 inches high, and fall protection above 10 feet.

  • Crane and equipment operations near power lines require at least 20 feet clearance for lines up to 350 kV under 29 CFR 1926.1408.

  • Construction disturbing 1 acre or more requires NPDES stormwater coverage and a Stormwater Pollution Prevention Plan with best management practices.

  • OSHA requires reporting a work-related fatality within 8 hours and an in-patient hospitalization, amputation, or loss of an eye within 24 hours.