High Risk Work Licence - Slewing Mobile Crane C0 (over 100t) flashcards
High Risk Work Licence - Slewing Mobile Crane C0 (over 100t) · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Primary duty of care
- The PCBU must ensure, so far as is reasonably practicable, the health and safety of workers and others affected by the business, including crane operations and lift planning.
- Hierarchy of control
- A ranked order of controls from most to least effective: elimination, substitution, isolation, engineering, administrative, and PPE. Higher-order controls are preferred for crane hazards.
- Notifiable incident
- An incident such as death, serious injury or illness, or a dangerous event like plant collapse or load drop, which must be reported to the regulator as required by WHS law.
- Safe work method statement
- A written document that sets out the high risk construction work, the hazards, the controls, and how controls will be implemented, monitored and reviewed before work starts.
- Risk score formula
- Risk is assessed as likelihood multiplied by consequence. Controls are applied in hierarchy order, and residual risk is re-assessed after each control is implemented.
- Exclusion zone
- A barricaded area around the crane sized to the greater of the swing radius, the load fall zone, or the calculated drop radius, keeping people clear of crush and drop hazards.
- Powerline approach limits
- Minimum safe distances from energised lines that increase with voltage. The voltage must be identified, the line isolated where possible, and a spotter used.
- Wind limit
- The maximum wind speed specified by the manufacturer in the load chart. Capacity reductions apply above it, and loads with large sail area increase wind loading.
- Radius measurement
- The horizontal distance from the crane's slewing centre to the centre of gravity of the load, not to the hook or boom tip. Radius increases with boom deflection.
- Rated capacity
- The charted capacity for the current configuration and radius, reduced by deductions for hook block, slings, spreader beams, and any jib or fly section attached.
- Structural versus stability limit
- Two separate limits govern capacity. Structural limits concern boom and component strength; stability limits concern overturning. The chart reflects the lesser of the two.
- Configuration-specific chart
- A load chart valid only for a specific boom length, counterweight, outrigger spread, and jib setup. A chart for another configuration must not be used.
- Sling tension formula
- Tension per leg equals load divided by the number of legs multiplied by the cosine of the angle from vertical. Wider included angles increase tension in each leg.
- Working load limit
- The maximum mass a sling or fitting may lift in a specified configuration. The assembly's WLL is the lowest-rated component in the rigging system.
- Centre of gravity
- The point through which the load's weight acts. The hook must be directly above it so the load stays level and sling tensions remain equal.
- Mass estimation formula
- Mass equals volume multiplied by density. Reference densities: steel about 7,850 kg/m³, concrete about 2,400 kg/m³, water 1,000 kg/m³.
- Ground bearing pressure
- The load on an outrigger divided by the effective pad area. The pad must spread the load to below the verified ground bearing capacity of the soil.
- Outrigger load distribution
- Outrigger loads are unequal. The outrigger nearest the load carries the greatest load, often several times the average, and governs pad size selection.
- Set-up level tolerance
- The crane must be level within the manufacturer's tolerance, with outriggers fully extended and pinned and pads bearing on verified stable ground.
- Underground voids
- Basements, drains, services and backfilled excavations under outrigger pads can collapse under load. They must be identified and assessed before the crane is set up.
- Critical lift
- A lift with high consequence or complexity, such as a load near capacity, a multi-crane lift, a lift over live plant, or an unusual or unstable load.
- Multi-crane load share
- Load share between cranes depends on geometry, rigging and relative hook height, not equal division. Each crane must stay within its charted capacity at its radius.
- Two-crane capacity rule
- In a two-crane lift, the load on each crane must not exceed 75 percent of its charted capacity at the working radius, and the load must be kept level.
- Lift director role
- The single authority for the lift. All signals and decisions pass through the lift director and the designated signal person, who directs the operator.
- Single signal person
- Only one signal person directs the operator at a time. Any change of signal person must be communicated to the operator before control passes.
- Emergency stop signal
- A single sharp movement of the hand or arm across the body, or the word stop by radio. The operator must obey it immediately without question.
- Blind lift communication
- When the operator cannot see the load, a signal person must be positioned to see both load and operator, or a documented alternative such as cameras or radio relays used.
- Load moment indicator test
- The load moment indicator and rated capacity limiter must be tested and functional before each lift. A faulty unit puts the crane out of service.
- Defect tagging
- A defect affecting safe operation must be reported, the crane tagged out and removed from service, and the defect rectified and verified before return to service.
- Wire rope discard criteria
- Inspection for broken wires, corrosion, kinks, bird-caging and diameter reduction. Discard limits are set by the manufacturer and the applicable standard.
- Powerline contact response
- The operator stays in the cab and warns others clear. If evacuation is essential, jump clear and shuffle away without touching crane and ground at the same time.
- Crane instability response
- If the crane becomes unstable or an outrigger sinks, stop the lift, lower the load if possible, evacuate the area, and do not slew or travel.
- Smooth control inputs
- Gradual starts and stops reduce load swing and dynamic amplification, lowering the effective load on the crane, rigging and ground compared with abrupt movements.