- Primary duty of care
- The PCBU must ensure, so far as is reasonably practicable, the health and safety of workers and others affected by the business or undertaking.
- Class CD licence
- A high risk work licence authorising the holder to operate a derrick crane; it is personal, non-transferable, and limited to the endorsed class and conditions.
- Notifiable incident
- An incident such as death, serious injury or illness, or a dangerous event like a crane collapse or uncontrolled load, which must be reported to the regulator.
- Hierarchy of control
- A ranked order of risk controls: eliminate, substitute, engineer, administrate, then PPE as the last defence, applied until residual risk is ALARP.
- Exclusion zone
- A barricaded no-go area beneath and around the load path, sized to the load radius and swing, keeping people clear of suspended loads and crush zones.
- Shock loading
- A dynamic load caused by sudden starts, stops, snatching or release, which can multiply the static load several times and exceed the rated capacity.
- Guy derrick
- A derrick crane whose mast is held upright by multiple tensioned guy ropes anchored to fixed points, with a boom for lifting.
- Stiff-leg derrick
- A derrick crane whose mast is supported by rigid structural legs rather than flexible guys, giving a fixed and more rigid support arrangement.
- Load moment
- The turning effect of the load about the mast base, equal to load multiplied by radius; it increases with radius and governs stability and rated capacity.
- Ground bearing pressure
- The imposed load divided by the effective bearing area of the footing, which must not exceed the allowable bearing capacity of the ground.
- Guy anchor capacity
- The maximum tension an anchorage can safely resist, including dynamic and wind effects, verified by a competent person before guys are attached.
- Guy tensioning
- All guys must be equally tensioned with turnbuckles or similar devices; slack or uneven guys cause mast sway and unequal loading.
- Pre-start inspection
- A daily check of foundation, guy tension, structure, ropes, sheaves, hooks, limit switches and the load chart before the crane is operated.
- Rope discard criteria
- Limits on broken wires, kinks, birdcaging, corrosion and abrasion set by the applicable standard; ropes exceeding them must be removed from service.
- Logbook
- A record of inspections, defects, repairs, alterations and maintenance, retained with the crane and available for audit or investigation.
- Net capacity
- The rated capacity minus the mass of hook block, slings and other lifting gear, giving the maximum load mass that may be lifted.
- Sling angle factor
- The multiplier applied to load share per leg as the angle to horizontal decreases; at 30 degrees each leg carries the full load.
- Centre of gravity
- The point through which the load's mass acts; it must sit below or directly under the hook to prevent tilt and unequal sling loading.
- Working load limit
- The maximum mass a sling, shackle or fitting is rated to carry in service, marked on the item and reduced by configuration and angle.
- Rated capacity
- The maximum load the crane may lift at a given radius and configuration, as stated in the manufacturer's load chart.
- Load chart reading
- Select the row for the actual boom length, radius and ballast configuration; never interpolate beyond listed values or assume unlisted capacities.
- Radius increase effect
- As the boom radius increases, the load moment rises and the rated capacity falls, so the load must be checked at every radius in the lift.
- Designated signal person
- The single dogger authorised to give signals to the operator, preventing conflicting commands from multiple sources during the lift.
- Emergency stop signal
- A recognised signal that must be obeyed immediately by the operator, regardless of who gives it, stopping all crane motion.
- Radio communication protocol
- A dedicated channel with clear call signs and read-back confirmation of critical commands; loss of communication requires the lift to stop.
- Suspended load procedure
- If a load cannot be landed, barricade the area beneath it, keep people clear, and seek competent advice before attempting recovery.
- Powerline contact response
- Keep clear, do not touch the crane or load, and have the supply isolated by the utility before anyone approaches the equipment.
- Post-incident actions
- Provide first aid, secure the scene, notify the regulator as required, preserve evidence, and complete an incident report before resuming work.
- Dismantling sequence
- A documented procedure in reverse of erection: unload, remove rigging, release guys in the specified order, then lower boom and mast.
- Component tagging
- Marking inspected items as serviceable or defective during dismantling, quarantining damaged gear so it cannot be returned to service.
- Lifting gear storage
- Ropes, slings and fittings kept off the ground, dry and ventilated, protected from UV, chemicals and corrosion, with small parts in labelled containers.
- Shutdown checklist
- A post-operational record of the crane's condition, defects found, configuration and handover details, completed before leaving site.