PCBU
Person Conducting a Business or Undertaking; has the primary duty of care under WHS law to ensure health and safety so far as reasonably practicable, including for crane operations.
High risk work licence
A licence required to perform high risk work such as operating a self-erecting tower crane; must be carried or available and renewed before expiry.
SWMS
Safe Work Method Statement; a document that sets out high risk construction work activities, hazards, and control measures, required under WHS regulations.
Notifiable incident
A death, serious injury, or dangerous incident that must be reported to the regulator immediately; the site must not be disturbed except to assist or make safe.
Hierarchy of control
The order of risk controls: eliminate, substitute, isolate, engineering, administrative, then PPE; higher-order controls are preferred.
Exclusion zone
A defined area around the crane and lifting operation where unauthorized personnel are prohibited; size determined by load radius, fall zone, and site conditions.
Risk assessment
A systematic process of identifying hazards, evaluating likelihood and consequence, and implementing controls; must be reviewed when conditions change.
Emergency stop signal
One long whistle or a hand signal with arm extended horizontally and moving side to side; anyone may give it, and the operator must stop immediately.
Hoist signal
Two short whistle blasts or a hand signal with forearm vertical and finger pointing up; directs the operator to raise the load.
Radio communication protocol
Clear, concise messages identifying the crane and load, with read-back confirmation for critical moves; stop work if communication fails.
Load moment
The product of load and radius; it must not exceed the crane's rated load moment, which determines stability and tipping.
Slew centre
The vertical axis around which the crane's upper structure rotates; radius is measured from this centre to the load's centre of gravity.
Counterweight
A mass on the counter-jib that provides a resisting moment to balance the load moment and maintain crane stability.
Rated capacity
The maximum load a crane is designed to lift at a specified radius and configuration, as shown on the load chart.
Ground bearing pressure
The pressure exerted by the crane's foundation on the ground; must be assessed by a competent person to prevent settlement or collapse.
Outrigger
A stabilising arm extended from the crane base to increase the support base; must be fully extended and supported on stable material.
Rail track alignment
For rail-mounted cranes, the track must be laid to correct gauge and alignment on a properly prepared subgrade with drainage.
Climbing operation
The process of raising the crane mast using its own hydraulic system; must be done within wind limits and by competent persons.
Erection sequence
The documented order of assembling crane components; dismantling follows the reverse sequence, with controlled lowering and securing for transport.
Load chart
A table or graph showing the maximum safe lifting capacity for various radii and configurations; must be available and used for every lift.
Total load
The sum of the load weight, rigging, lifting accessories, and hook block; must be subtracted from the rated capacity.
Load estimation
Determining load weight by calculating volume times density or using a scale; never guess, and verify when unknown.
Dynamic load
Additional load due to wind, acceleration, or deceleration; increases the effective load and may require reducing capacity.
Pre-operational inspection
A daily check before first use, covering structure, ropes, hooks, limit switches, brakes, and safety devices; defects must be reported and rectified.
Defect reporting
The process of reporting any safety-related defect immediately; the crane must be tagged out and not used until repaired.
Maintenance schedule
The manufacturer's specified intervals and tasks for servicing the crane; must be followed by competent persons and records kept.
Working load limit
The maximum load a lifting accessory is designed to carry; must not be exceeded and is affected by sling angle.
Sling angle factor
A multiplier applied to the sling's capacity based on its angle from horizontal; capacity decreases as the angle decreases.
Tag line
A rope attached to a load to control rotation and movement during lifting; helps keep the load within the exclusion zone.
Slewing
The rotation of the crane's upper structure around the slew centre; must be controlled to avoid load swing and contact with structures.
Out-of-service wind
The wind speed at which the crane must be placed in a specified configuration (e.g., slewing free) to prevent damage; specified by the manufacturer.
Load placement
Landing the load on a stable surface and ensuring it is fully supported before releasing the rigging; never leave a suspended load unattended.