- Sling angle factor
- A multiplier equal to one divided by the cosine of the sling's angle from horizontal, applied to the load share to find tension in each leg.
- Center of gravity
- The point where the entire weight of an object is considered concentrated; a load hangs level only when this point lies directly below the hook.
- Overturning moment
- The product of a horizontal force and its perpendicular height above a tipping point; tipping occurs when it exceeds the restoring moment from the load's weight.
- Asymmetric load share
- In a two-point pick, each leg carries a share proportional to its distance from the center of gravity, so the leg nearer the center carries more.
- Shackle side loading
- Loading a shackle at an angle to its pin-to-bowl axis reduces capacity and requires the manufacturer's rating, not the vertical working load limit.
- Choker hitch reduction
- A choker hitch typically reduces a synthetic web sling's capacity to about eighty percent of its vertical rating, as stated on the sling tag.
- Spreader beam function
- A below-the-hook device that holds attachment points apart and carries compressive load, preventing horizontal squeeze on the lifted object.
- Screw-pin shackle check
- Before use, confirm the pin is fully threaded home and secured; a partially engaged or unsecured pin is a removal-from-service condition.
- Stop signal authority
- Anyone on the site may give a stop signal, and the crane operator must obey it regardless of who the designated signalperson is.
- Load moment
- The product of the suspended load and the working radius; it must stay within the crane's rated capacity chart for the actual configuration.
- Anti-two-block device
- A safety device that prevents the hook block from contacting the boom tip; it must be functional before lifting and must never be bypassed.
- Tag line purpose
- A rope used to control rotation and swing of a suspended load; it is held from outside the fall zone and never wrapped around a worker's body.
- Lang lay wire rope
- A rope in which strand wires and strands are twisted in the same direction, giving greater abrasion resistance but less resistance to rotation.
- Regular lay wire rope
- A rope in which strand wires are twisted opposite to the strand direction, providing better resistance to crushing and less tendency to rotate.
- Bowline knot efficiency
- A bowline can reduce synthetic rope strength by roughly forty to sixty percent, so a proper splice is preferred for load-bearing terminations.
- Wire rope clip placement
- The U-bolt is placed on the dead end and the saddle on the live end, spaced at about six rope diameters with the first clip near the thimble.
- Jack base preparation
- A jack must sit plumb on a firm, level pad sized to spread load; an unstable base can let the jack tip or the piston bend.
- Cribbing stack stability
- Cribbing is stacked with alternating grain and a low height-to-base ratio so the stack stays stable and resists toppling under load.
- Roller skidding friction
- Rollers reduce the pull force needed to move a load; the required force approximates the load times the coefficient of rolling friction plus grade resistance.
- Multiple jack lifting
- When lifting with several jacks, raise in small increments and crib or block the load as it rises; never rely on a jack alone to hold it.
- Critical lift plan
- A documented plan covering load weight and center of gravity, rigging arrangement, crane capacity, ground bearing, and contingency for a dropped load.
- Trial lift
- Raising the load slightly before the full lift to verify the center of gravity, rigging geometry, and stability of the arrangement.
- Shock loading
- Sudden stops or rapid slack removal can multiply the static load several times, so lift plans specify slow, controlled movement.
- Wind load scaling
- Wind force on a suspended load increases with the square of wind speed, so lift plans state a wind limit at which lifting stops.
- Red warning thread
- A red core thread visible through a cut or worn synthetic web sling indicates damage; the sling is removed from service immediately.
- Chain sling stretch
- A chain sling is removed from service when links are stretched beyond the manufacturer's limit or worn more than ten percent of the original dimension.
- Periodic inspection interval
- Rigging in normal service receives a documented periodic inspection at least annually, more often in severe service or after a shock load.
- Overload inspection rule
- Any rigging that has been overloaded, shock-loaded, or involved in an accident must be inspected before it returns to service.
- OSHA sling standard
- OSHA 29 CFR 1910.184 sets requirements for slings, including marking, inspection, and removal-from-service criteria for wire rope, chain, and synthetic slings.
- Rated capacity marking
- Rigging hardware must be marked with its rated capacity; unmarked or illegible gear is removed from service and must not be used.
- Power line clearance
- Crane and rigging operations near energized lines must maintain the required minimum clearance, using a spotter or proximity alarm where required.
- Stop-work authority
- Every worker has the authority to stop a lift they believe is unsafe; accident prevention depends on hazard analysis and exclusion zones under loads.