Testing a New Installation Before Energisation

NSW Electrical Licence · Put your knowledge to work in context.

All case studies

Testing a New Installation Before Energisation

You have completed a new single-phase domestic installation: a distribution board with a main switch, two 20 A RCDs, six final sub-circuits (lights, power, oven, hot water, shed, and a spa pump). The client wants it energised the same day. You have a multifunction tester, insulation resistance tester, loop impedance tester and RCD tester. One circuit - the shed - runs 45 m underground in conduit and you are unsure whether the conduit was damaged during backfilling.

1. List the verification tests you would perform, in a logical sequence, and explain why the order matters.

Read the worked answer

Sequence before energisation:

  1. Visual inspection first - it is a prerequisite for testing and may reveal the damaged conduit before any instrument is used.
  2. Continuity of protective conductors and main earthing - confirms the earth path exists before you rely on it.
  3. Insulation resistance on each circuit, with sensitive equipment disconnected, at the correct test voltage. This is where a damaged shed conduit would show up as low resistance to earth.
  4. Polarity checks - ensures active and neutral are not reversed, critical for safety.
  5. Earth fault loop impedance - confirms the fault path impedance allows the device to trip within the required time.
  6. RCD operation - trip time and current tests on both RCDs, including the spa and shed circuits.
  7. Functional testing of switches, outlets and equipment.

Order matters because each test builds on the last: you cannot trust loop impedance if the earth continuity is broken, and you should not energise a circuit whose insulation has failed.

2. The shed circuit insulation resistance reads 0.4 MΩ to earth. What is your decision, and how do you proceed?

Read the worked answer

0.4 MΩ is far below the acceptable minimum for a new installation, so the circuit must not be energised. The reading is consistent with a damaged conduit allowing moisture or soil contact with the cable.

Proceed by:

  • Isolating the cause - disconnect the cable at both ends and retest to confirm the low reading is in the cable, not the fittings.
  • Locating the damage - a time-domain reflectometer or sectional testing along the 45 m run can pinpoint the fault.
  • Excavating and inspecting the conduit at suspected points.
  • Repairing or replacing the damaged section, then retesting until insulation resistance is satisfactory.

Document the failed reading, the repair and the passing retest. Do not accept the client's request to energise 'just to test it' - energising a circuit with a low insulation resistance to earth is a shock and fire risk.