Question 1Building legislation, regulations and practitioner obligations

Under the Building Act 1993 (Vic), which person is legally responsible for ensuring that building work complies with the building permit and the Building Regulations?

  1. The registered building surveyor who issued the permit
  2. The architect who prepared the design drawings
  3. The owner of the land and the builder carrying out the work Correct answer.
  4. The local council's municipal building surveyor

Explanation

The Act places the duty of ensuring building work complies with the permit and regulations on the owner and the builder. The surveyor's role is to assess and enforce compliance, not to guarantee it, and designers are responsible only for the documents they prepare. Responsibility is therefore shared between owner and builder.

Question 2Building legislation, regulations and practitioner obligations

What is the primary purpose of a building permit?

  1. To authorise specified building work before it begins Correct answer.
  2. To certify that the finished building is fit for occupation
  3. To transfer liability for defects to the insurer
  4. To record the property's title and ownership details

Explanation

A building permit is an approval authorising the specified building work to proceed before construction starts. It is not an occupancy certificate, which is issued after completion, and it does not deal with title or insurance. The permit ensures the work is assessed against the regulations in advance.

Question 3Building legislation, regulations and practitioner obligations

Which document must generally be obtained before a completed building can be occupied?

  1. An occupancy permit Correct answer.
  2. A building permit amendment
  3. A planning permit
  4. A certificate of final inspection

Explanation

An occupancy permit certifies that a building is suitable for occupation and must be issued before occupation in the circumstances the Act specifies. A certificate of final inspection applies to work that does not require an occupancy permit. Planning permits govern land use and development approval, not occupancy.

Question 4Building legislation, regulations and practitioner obligations

Which body maintains the register of building practitioners in Victoria?

  1. The Victorian Building Authority Correct answer.
  2. The Planning Panels Victoria
  3. The Municipal Association of Victoria
  4. The Building Appeals Board

Explanation

The Victorian Building Authority is the regulator that registers and oversees building practitioners in Victoria. The Building Appeals Board hears appeals and determinations rather than maintaining the register. The other bodies have planning or local government functions unrelated to practitioner registration.

Question 5Building legislation, regulations and practitioner obligations

What is the key distinction between a building permit and a planning permit?

  1. A planning permit is required only for commercial buildings
  2. A building permit addresses construction standards, while a planning permit addresses land use and development Correct answer.
  3. A building permit is optional, while a planning permit is always mandatory
  4. A planning permit is issued only by the state government

Explanation

Building permits concern compliance with construction and safety standards, while planning permits concern land use, development and amenity. The two approvals come from different regulatory frameworks and may both be needed. Neither is inherently optional or limited to commercial buildings.

Question 6Building legislation, regulations and practitioner obligations

Which of the following is a core obligation of a registered building practitioner?

  1. To carry out work competently and in accordance with the regulations Correct answer.
  2. To personally inspect every other trade's work daily
  3. To obtain planning approval on the owner's behalf in all cases
  4. To guarantee the building will be free of defects for its lifetime

Explanation

Registered practitioners must carry out their work competently and in accordance with the Building Act and regulations. They do not provide lifetime guarantees against defects and are not automatically responsible for daily inspection of other trades. Obtaining planning approval is generally the owner's responsibility unless separately engaged.

Question 7Building legislation, regulations and practitioner obligations

What does the term 'domestic building work' generally describe?

  1. Construction of public infrastructure near residences
  2. Any building work performed inside a home
  3. Building work on a home or associated structure for residential purposes Correct answer.
  4. Work carried out by the homeowner without a permit

Explanation

Domestic building work refers to building work on a home or associated residential structures covered by domestic building legislation. It is defined by the nature and purpose of the work, not by its location inside a building. Public infrastructure and permit exemptions are governed by different rules.

Question 8Building legislation, regulations and practitioner obligations

A building surveyor is engaged to assess a permit application. Which principle best describes the surveyor's decision-making role?

  1. The surveyor acts as an advocate for the applicant
  2. The surveyor must follow the builder's preferred construction method
  3. The surveyor must approve any application supported by an engineer
  4. The surveyor exercises independent professional judgement on compliance Correct answer.

Explanation

A building surveyor must exercise independent professional judgement when assessing compliance with the regulations. Approval is not automatic because an engineer supports it, and the surveyor is not an advocate for the applicant. This independence protects the integrity of the approval process.

Question 9Building legislation, regulations and practitioner obligations

A builder proposes to vary the design after the building permit has been issued. What is the correct regulatory step?

  1. Seek an amendment to the building permit before carrying out the varied work Correct answer.
  2. Rely on the original permit because the change is minor
  3. Notify the council only after the work is finished
  4. Proceed with the change and note it in the handover documents

Explanation

Where building work will differ from the approved permit documents, an amendment to the building permit must be obtained before the varied work proceeds. Recording the change later or notifying after completion does not satisfy the requirement. The original permit does not authorise work outside its approved scope, even if the change seems minor.

Question 10Building legislation, regulations and practitioner obligations

Which statement best describes the role of the National Construction Code (NCC) in Victorian building regulation?

  1. It replaces the need for any building permit
  2. It applies only to government-owned buildings
  3. It is a voluntary guide with no legal effect
  4. It is given legal effect through adoption by the Building Regulations Correct answer.

Explanation

The NCC contains performance requirements and deemed-to-satisfy provisions that become legally enforceable when adopted by the Building Regulations. It is not merely a voluntary guide and does not remove the need for permits. Its application is general, not limited to government buildings.

Question 11Building legislation, regulations and practitioner obligations

A building surveyor identifies that work on site departs from the approved plans in a way that affects safety. What is the most appropriate immediate action?

  1. Issue a building notice or building order to require the matter to be addressed Correct answer.
  2. Refer the matter to the planning department for a planning permit
  3. Ignore the departure because the owner has accepted the risk
  4. Approve the departure retrospectively without inspection

Explanation

Where work does not comply with the permit or regulations, the surveyor may issue a building notice and, if needed, a building order requiring the matter to be rectified. Simply accepting the owner's risk acceptance does not discharge the surveyor's enforcement role. Retrospective approval without proper assessment and planning referral are not appropriate responses.

Question 12Building legislation, regulations and practitioner obligations

Which of the following best explains the purpose of mandatory notification stages during construction?

  1. To enable the surveyor to inspect critical stages before work is covered up Correct answer.
  2. To satisfy the lender's valuation requirements
  3. To record the number of tradespeople on site
  4. To allow the builder to claim progress payments

Explanation

Mandatory notification stages require the builder to notify the surveyor so that critical elements can be inspected before they are concealed. This supports verification of compliance at key points. Progress payments, lender valuations and workforce records are commercial or administrative matters, not the regulatory purpose.

Question 13Building legislation, regulations and practitioner obligations

A registered builder is asked to sign a contract that excludes all statutory warranties. How should the builder respond?

  1. Decline to rely on the exclusion, because statutory warranties cannot be excluded in that way Correct answer.
  2. Sign it, because parties can contract out of statutory warranties freely
  3. Sign it, because warranties only apply to commercial projects
  4. Sign it, provided the owner initials each exclusion clause

Explanation

Domestic building statutory warranties are imposed by legislation and cannot be excluded by agreement in the manner described. A clause purporting to exclude them does not override the statutory protections. Owners' initials do not make an invalid exclusion effective, and the warranties are not limited to commercial projects.

Question 14Building legislation, regulations and practitioner obligations

What does 'owner-builder' mean in the building regulatory context?

  1. An owner who takes responsibility for carrying out domestic building work on their own land Correct answer.
  2. An owner who engages a registered builder to manage the project
  3. A builder who owns the company performing the work
  4. A surveyor who also owns the property being built

Explanation

An owner-builder is an owner who undertakes domestic building work on their own land and assumes the responsibilities that go with it, including permit and insurance requirements where applicable. Engaging a registered builder describes the ordinary owner arrangement, not an owner-builder. Company ownership and surveyor property interests are unrelated concepts.

Question 15Building legislation, regulations and practitioner obligations

Which of these matters is most likely to require a building permit?

  1. Laying new carpet in a bedroom
  2. Repainting the interior walls of a house
  3. Replacing a tap washer in a kitchen
  4. Constructing a new carport attached to a dwelling Correct answer.

Explanation

Structural additions such as an attached carport generally require a building permit because they involve construction and structural work. Minor maintenance and cosmetic tasks like repainting, replacing tap washers or laying carpet do not involve building work requiring a permit. The regulations list exemptions, but these maintenance items fall outside permit-triggering work.

Question 16Building legislation, regulations and practitioner obligations

What is the function of the Building Appeals Board?

  1. To hear appeals and determine disputes about building matters Correct answer.
  2. To issue building permits for large projects
  3. To draft the National Construction Code
  4. To prosecute unregistered builders in court

Explanation

The Building Appeals Board hears appeals and determines certain disputes and applications under building legislation. It does not issue building permits, which is the role of building surveyors, nor does it prosecute offenders or draft the NCC. Its function is independent review and determination.

Question 17Building legislation, regulations and practitioner obligations

A builder completes work that differs from the approved permit but the surveyor considers it compliant in performance terms. What is the proper course?

  1. Document the alternative solution and amend the permit so it reflects the approved work Correct answer.
  2. Leave the permit unchanged because performance is satisfactory
  3. Ask the owner to sign a waiver of the permit conditions
  4. Report the builder to the regulator without further assessment

Explanation

Where an alternative solution is accepted as compliant, the approval documentation should reflect it, typically through a permit amendment. Leaving the permit inconsistent with the built work creates ongoing compliance problems. Owner waivers cannot override permit requirements, and immediate reporting without assessment is premature.

Question 18Building legislation, regulations and practitioner obligations

Which obligation applies to a builder regarding the display of registration or licensing information?

  1. Registration may be kept confidential from clients
  2. Registration must be displayed only at the building site
  3. Registration details must be displayed as required on advertising and contractual documents Correct answer.
  4. Registration need only be displayed on the builder's website

Explanation

Registered practitioners are required to display or state their registration details on specified documents such as advertising and contracts. Clients are entitled to know the registration status of the practitioner they engage. Keeping it confidential or limiting display to a website or site alone does not meet the requirement.

Question 19Building legislation, regulations and practitioner obligations

A homeowner wants to build a small shed. Which factor most directly determines whether a building permit is required?

  1. The distance from the nearest neighbour's fence only
  2. The size, height and classification of the structure under the regulations Correct answer.
  3. Whether the owner is a registered builder
  4. The colour and material of the shed

Explanation

Whether a structure needs a permit depends on criteria such as its size, height, classification and use as set out in the regulations. Colour and materials do not determine permit requirements, and the owner's registration status is irrelevant. Distance from a boundary may be a siting consideration but is not the sole determinant.

Question 20Building legislation, regulations and practitioner obligations

Which statement about the duty to report unsafe or non-compliant building work is most accurate?

  1. Any person may notify the regulator of suspected non-compliant building work Correct answer.
  2. Reports must be made through the Building Appeals Board
  3. Only the owner may report non-compliance to the regulator
  4. Reporting is restricted to registered practitioners

Explanation

The regulatory framework allows any person to notify the regulator about suspected non-compliant or unsafe building work. Reporting is not restricted to owners or registered practitioners. The Building Appeals Board is not the intake point for such notifications.

Question 21Building legislation, regulations and practitioner obligations

A private building surveyor is engaged for a project but later becomes unavailable. What is the most appropriate regulatory consideration?

  1. The permit automatically lapses and all work must stop permanently
  2. Arrangements must be made for another surveyor or the relevant authority to carry out the remaining functions Correct answer.
  3. The builder may self-certify the remaining stages
  4. The owner must recommence the entire application process

Explanation

Where a surveyor cannot continue, arrangements must be made for another surveyor or the relevant authority to perform the remaining statutory functions. Builders cannot self-certify to fill the gap, and the permit does not automatically lapse permanently. A full restart is not the standard consequence.

Question 22Building legislation, regulations and practitioner obligations

Which principle underlies the requirement that a building surveyor not have a conflict of interest in relation to a project?

  1. Conflicts are acceptable if disclosed to the owner only
  2. Surveyors should maximise the number of permits they issue
  3. Decisions must be impartial and free from financial or personal influence Correct answer.
  4. Surveyors must prioritise the builder's commercial interests

Explanation

The conflict of interest rules exist to protect the impartiality and integrity of compliance decisions. A surveyor influenced by financial or personal interests cannot make objective assessments. Maximising permit numbers or prioritising commercial interests undermines the regulatory purpose, and disclosure to the owner alone does not resolve the conflict.

Question 23Building legislation, regulations and practitioner obligations

A building notice has been issued. What is the recipient's usual opportunity before a building order is made?

  1. The recipient may ignore the notice until an order is served
  2. The recipient must appeal directly to the Supreme Court
  3. The recipient may respond to the notice and show cause why an order should not be made Correct answer.
  4. The recipient must immediately demolish the work

Explanation

A building notice gives the recipient an opportunity to respond and show cause why a building order should not be made. Ignoring the notice can lead to an order being issued, and immediate demolition is not the automatic requirement. Appeal rights arise through the Building Appeals Board rather than directly to the Supreme Court.

Question 24Building legislation, regulations and practitioner obligations

Which of the following best describes the relationship between performance requirements and deemed-to-satisfy provisions in the NCC?

  1. Deemed-to-satisfy provisions override the performance requirements
  2. Compliance with deemed-to-satisfy provisions is one way to satisfy the performance requirements Correct answer.
  3. Both are optional guidance with no regulatory effect
  4. Performance requirements apply only when no deemed-to-satisfy provision exists

Explanation

The NCC sets performance requirements, and the deemed-to-satisfy provisions are prescriptive solutions that are accepted as meeting them. An alternative solution may also demonstrate compliance with the performance requirements. Deemed-to-satisfy provisions do not override performance requirements, and both have regulatory effect once adopted.

Question 25Building legislation, regulations and practitioner obligations

A practitioner suspects that a client's proposed design will not comply with the regulations but the client insists on proceeding. What is the practitioner's most appropriate professional response?

  1. Alter the drawings after submission without telling anyone
  2. Refer the client to another practitioner without comment
  3. Proceed and rely on the client's written instruction as a defence
  4. Advise the client of the non-compliance and decline to certify or proceed with non-compliant work Correct answer.

Explanation

Practitioners must not certify or carry out work they know to be non-compliant, and they should clearly advise the client of the issue. A client's written instruction does not provide a defence against professional obligations. Silent alteration of drawings or unexplained referral does not meet the practitioner's duty.

Question 26Building legislation, regulations and practitioner obligations

Which Act is the primary legislation governing building regulation in Victoria?

  1. Planning and Environment Act 1987
  2. Occupational Health and Safety Act 2004
  3. Building and Construction Industry Security of Payment Act 2002
  4. Building Act 1993 Correct answer.

Explanation

The Building Act 1993 is the principal statute for building control in Victoria, establishing the building permit system, practitioner registration, and enforcement powers. The other Acts address planning, security of payment, and workplace safety respectively, not the core building regulatory framework.

Question 27Building legislation, regulations and practitioner obligations

Under Victorian building law, what is the maximum period for which a building permit remains in force if the work has not commenced?

  1. 12 months from the date of issue
  2. 36 months from the date of issue
  3. No time limit applies until work starts
  4. 24 months from the date of issue Correct answer.

Explanation

A building permit lapses if the building work is not commenced within 24 months of the permit being issued, unless the relevant authority grants an extension. This ensures that approved projects are not left indefinitely without construction, which could lead to outdated designs or site conditions.

Question 28Building legislation, regulations and practitioner obligations

A registered building practitioner is required to maintain professional indemnity insurance in certain circumstances. Which statement best describes this requirement?

  1. All registered builders must hold professional indemnity insurance at all times.
  2. Professional indemnity insurance is required for building surveyors and may be required for other practitioners depending on the work and registration category. Correct answer.
  3. Professional indemnity insurance is optional for all practitioners but recommended.
  4. Only building surveyors are required to hold professional indemnity insurance.

Explanation

The Building Act and regulations impose mandatory professional indemnity insurance on building surveyors, while for other categories such as builders, the requirement may depend on the type of work or registration. This reflects the higher risk and public interest involved in surveyor decisions.

Question 29Building legislation, regulations and practitioner obligations

Which of the following is a key function of the Victorian Building Authority (VBA)?

  1. Registering building practitioners and monitoring their conduct Correct answer.
  2. Resolving contractual disputes between builders and clients
  3. Setting local council rates and charges
  4. Issuing planning permits for development projects

Explanation

The VBA is the regulator for building and plumbing in Victoria, responsible for registering practitioners, auditing their work, and taking disciplinary action where necessary. It does not issue planning permits, set council rates, or adjudicate contract disputes.

Question 30Building legislation, regulations and practitioner obligations

A builder is issued with a building notice alleging non-compliant work. What is the builder's primary right in response to the notice?

  1. To appeal directly to the Building Appeals Board without responding to the notice
  2. To ignore the notice until a building order is issued
  3. To request that the VBA immediately suspend the surveyor's registration
  4. To provide a written response to the relevant building surveyor explaining why the work complies or outlining proposed rectification Correct answer.

Explanation

A building notice gives the recipient an opportunity to respond in writing to the issuing building surveyor, either by demonstrating compliance or by proposing remedial action. This is a procedural fairness step before a building order may be made.

Question 31Building legislation, regulations and practitioner obligations

Which of the following best describes the concept of 'building work' under the Building Act 1993 (Vic)?

  1. Only work that requires a building permit
  2. Only work performed by a registered building practitioner
  3. Any work involved in constructing, altering, repairing, or demolishing a building or structure, including site preparation Correct answer.
  4. Only the construction of a new building from the ground up

Explanation

The definition of building work is broad and covers construction, alteration, repair, demolition, and associated activities such as site preparation, regardless of whether a permit is required or who performs it. This broad scope ensures that safety and compliance obligations attach to a wide range of activities.

Question 32Building legislation, regulations and practitioner obligations

A registered building surveyor is appointed for a project. Which of the following is a statutory duty of the surveyor regarding the issuance of a building permit?

  1. To ensure the applicant has obtained planning approval before issuing the permit
  2. To obtain the consent of adjoining property owners before issuing the permit
  3. To assess the application against the National Construction Code and relevant regulations Correct answer.
  4. To guarantee that the builder will complete the work on time and within budget

Explanation

The building surveyor must assess the proposed work for compliance with the NCC and other applicable regulations before issuing a building permit. Planning approval and neighbour consent are separate matters, and the surveyor does not guarantee construction outcomes.

Question 33Building legislation, regulations and practitioner obligations

What is the purpose of the Building Regulations 2018 (Vic) in relation to the Building Act 1993?

  1. They are advisory guidelines with no legal force.
  2. They override the Act where there is a conflict.
  3. They apply only to commercial buildings, not residential.
  4. They provide detailed requirements and procedures to implement the Act. Correct answer.

Explanation

Regulations are made under the Act and provide the detailed technical and procedural rules needed to give effect to the Act's framework. They are legally binding and apply across building types unless specified otherwise.

Question 34Building legislation, regulations and practitioner obligations

A builder is required to provide a compliance certificate for certain work. Who is authorised to issue a compliance certificate for plumbing work?

  1. The builder who performed the work
  2. The building surveyor who issued the building permit
  3. The owner of the property
  4. A registered plumbing practitioner Correct answer.

Explanation

Compliance certificates for plumbing work must be issued by a registered plumbing practitioner, who certifies that the work complies with the relevant standards. Builders, surveyors, and owners are not authorised to issue plumbing compliance certificates.

Question 35Building legislation, regulations and practitioner obligations

Which of the following is a consequence for a registered building practitioner who fails to comply with the practitioner's statutory obligations?

  1. No consequences, as registration is permanent
  2. Automatic loss of registration without any hearing
  3. Disciplinary action by the VBA, which may include suspension or cancellation of registration Correct answer.
  4. Immediate criminal prosecution without the possibility of a fine

Explanation

The VBA has disciplinary powers to investigate and take action against practitioners who breach their obligations, which can include suspension, cancellation, or conditions on registration. These actions follow a formal process and are not automatic without a hearing.

Question 36Building legislation, regulations and practitioner obligations

A building surveyor is asked to approve a design that uses an alternative solution not covered by the deemed-to-satisfy provisions. What must the surveyor do?

  1. Approve the design without further assessment because the builder is registered
  2. Assess whether the alternative solution satisfies the relevant performance requirements Correct answer.
  3. Reject the design outright because it does not use deemed-to-satisfy provisions
  4. Refer the matter to the local council for a planning decision

Explanation

The NCC allows alternative solutions provided they meet the performance requirements. The surveyor must evaluate the evidence and reasoning to determine if the alternative solution is compliant, rather than rejecting it solely for not using deemed-to-satisfy provisions.

Question 37Building legislation, regulations and practitioner obligations

Under the Building Act 1993, what is the role of the Minister for Planning in relation to building regulations?

  1. To directly supervise all building surveyors
  2. To adjudicate disputes between builders and owners
  3. To issue building permits for major projects
  4. To recommend the making of building regulations Correct answer.

Explanation

The Minister for Planning is responsible for recommending building regulations to the Governor in Council, who makes them. The Minister does not issue permits, supervise surveyors directly, or adjudicate disputes.

Question 38Building legislation, regulations and practitioner obligations

A building practitioner is required to keep records of building work. Which statement best describes the record-keeping obligation?

  1. There is no requirement to keep records if the work was inspected by a surveyor.
  2. Records must be kept for 12 months after completion of the work.
  3. Records need only be kept if the work is valued over $10,000.
  4. Records must be kept for 10 years after completion of the work. Correct answer.

Explanation

Building practitioners are required to keep records related to building work for at least 10 years after completion, which aligns with the limitation period for certain legal actions. This supports accountability and allows for investigations or disputes to be resolved.

Question 39Building legislation, regulations and practitioner obligations

Which of the following best describes the application of the National Construction Code (NCC) in Victoria?

  1. The NCC applies only to government-owned buildings.
  2. The NCC is superseded by local council by-laws in all cases.
  3. The NCC is given legal effect through the Building Regulations 2018 and applies to all building work unless exempted. Correct answer.
  4. The NCC is a voluntary code that builders may choose to follow.

Explanation

The NCC is not itself a law; it is applied through the Building Regulations 2018, which adopt it with legal effect. It applies broadly to building work unless a specific exemption exists, and local by-laws cannot override it.

Question 40Building legislation, regulations and practitioner obligations

A registered building surveyor is considering whether to issue a building permit for a project that involves a performance solution. What is the most appropriate action for the surveyor to take?

  1. Request evidence that the performance solution complies with the performance requirements and assess it before deciding. Correct answer.
  2. Issue the permit without reviewing the performance solution because the builder is registered.
  3. Refuse the permit because performance solutions are not permitted in Victoria.
  4. Refer the decision to the local council because performance solutions require planning approval.

Explanation

The surveyor must be satisfied that the performance solution meets the performance requirements, which typically requires supporting evidence such as test data or expert reports. Issuing a permit without assessment would breach the surveyor's duty, while refusing solely because it is a performance solution is incorrect.

Question 41Building permits, approvals and the role of the building surveyor

Under a typical building regulatory framework, which person is legally responsible for issuing a building permit for a proposed new dwelling?

  1. The appointed building surveyor acting for the permit authority Correct answer.
  2. The licensed builder who will carry out the work
  3. The architect who prepared the construction drawings
  4. The local planning authority's elected council members

Explanation

A building permit is issued by a building surveyor or other officer authorised under the building legislation, who assesses the application against the applicable building code and regulations. The designer and builder prepare and perform the work but do not hold the statutory power to grant the permit. Elected council members set policy rather than deciding individual permit applications.

Question 42Building permits, approvals and the role of the building surveyor

A person wants to construct a small detached carport on their property. What is the usual first step in the building approval process?

  1. Paying the builder's deposit and signing the contract
  2. Applying for an occupancy certificate for the structure
  3. Lodging a building permit application with the relevant permit authority Correct answer.
  4. Requesting a final inspection from the building surveyor

Explanation

Building work generally requires an application to the permit authority before construction begins, supported by plans, specifications and other prescribed information. Inspections and occupancy certificates occur later in the process, after approval and construction. Signing a building contract does not itself authorise construction.

Question 43Building permits, approvals and the role of the building surveyor

What is the principal purpose of a building permit?

  1. To transfer ownership of the land to the builder
  2. To guarantee that the finished building will have no defects
  3. To confirm that proposed building work complies with the applicable building regulations before it starts Correct answer.
  4. To set the market value of the completed dwelling

Explanation

A building permit is a statutory authorisation confirming that the proposed work, as documented, is assessed as complying with the building code and related requirements. It does not warrant workmanship quality or insure against defects. It has no effect on land title or property valuation.

Question 44Building permits, approvals and the role of the building surveyor

Which document typically sets out the conditions that must be satisfied before building work may lawfully commence?

  1. The manufacturer's product warranty card
  2. The real estate agent's sales appraisal
  3. The building permit and its attached conditions Correct answer.
  4. The builder's public liability insurance policy

Explanation

The building permit, together with any conditions attached to it, authorises the work and states what must be done before and during construction. Insurance policies, sales appraisals and warranties are commercial or consumer documents with no role in authorising construction.

Question 45Building permits, approvals and the role of the building surveyor

During construction, the building surveyor carries out inspections primarily to:

  1. Certify the builder's tax obligations are up to date
  2. Negotiate a lower contract price on behalf of the owner
  3. Verify that the work complies with the approved plans and relevant regulatory requirements Correct answer.
  4. Confirm the owner has paid all subcontractor invoices

Explanation

Statutory inspections allow the building surveyor to check that construction matches the approved documentation and meets the performance requirements of the building code. Commercial and taxation matters fall outside the surveyor's regulatory role. Payment of invoices is a contractual issue between the parties.

Question 46Building permits, approvals and the role of the building surveyor

What is an occupancy certificate generally used for?

  1. Confirming that a completed building may be lawfully occupied Correct answer.
  2. Authorising the demolition of an existing structure
  3. Approving the builder's site safety plan
  4. Recording the sale price of the property

Explanation

An occupancy certificate (or equivalent) is issued after completion and inspection to confirm the building is suitable and lawful for occupation. Demolition, sale price and site safety are governed by other processes. It is a post-construction approval rather than a construction authorisation.

Question 47Building permits, approvals and the role of the building surveyor

Which of the following best describes the role of a building surveyor when assessing a permit application?

  1. A marketing agent who promotes the completed building
  2. An advocate who must approve any application lodged by a paying client
  3. An independent statutory reviewer who assesses compliance against the building regulations Correct answer.
  4. A construction supervisor who directs the builder's daily work

Explanation

The building surveyor acts as an independent statutory decision-maker, assessing the application against the building code and regulations. The role requires impartiality, so the surveyor cannot simply approve whatever a client lodges. Surveyors do not supervise trades or market buildings.

Question 48Building permits, approvals and the role of the building surveyor

A builder begins construction before a building permit has been issued. How is this best characterised?

  1. It is unlawful building work that may attract enforcement action Correct answer.
  2. It is acceptable provided the plans were lodged with the authority
  3. It is allowed for single-storey residential work only
  4. It is permitted if the builder is licensed and insured

Explanation

Building work that requires a permit must not start until the permit is granted and any pre-commencement conditions are met. Lodging an application does not authorise construction. Licensing and insurance do not substitute for the permit, and no exemption applies merely because the building is single-storey residential.

Question 49Building permits, approvals and the role of the building surveyor

An applicant submits plans for a garage that encroaches on a required side boundary setback. What is the most appropriate response from the building surveyor?

  1. Refuse the application or request amended plans that satisfy the setback requirement Correct answer.
  2. Approve the plans because a garage is a minor structure
  3. Approve the plans and note the encroachment for the builder to resolve
  4. Forward the plans to the builder and take no further action

Explanation

Where documentation shows non-compliance with a regulatory requirement such as a boundary setback, the surveyor should refuse the application or request amended plans demonstrating compliance. Minor structures are not automatically exempt, and the surveyor cannot delegate the compliance decision to the builder. Taking no action would leave the assessment incomplete.

Question 50Building permits, approvals and the role of the building surveyor

A developer wants to change the approved design to add a second storey after the permit has been granted. What is the correct process?

  1. Proceed with the change and advise the surveyor at the final inspection
  2. Ask the builder to record the change in the site diary only
  3. Proceed because the original permit already authorises residential work
  4. Apply to amend the permit before the changed work proceeds Correct answer.

Explanation

Work that departs from the approved documentation requires an amendment to the permit, assessed before the changed work is carried out. A permit authorises only the work described in the approved plans. Recording a change on site or disclosing it at final inspection does not provide lawful authorisation.