BPC/VBA Domestic Builder (Unlimited) Exam flashcards
BPC/VBA Domestic Builder (Unlimited) Exam · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Class 1a building
- A single dwelling such as a detached house, or one of a group of attached dwellings separated by fire-resisting walls, each with its own cooking, bathing and sleeping facilities.
- Class 10a structure
- A non-habitable building or structure such as a private garage, carport, shed or fence that is associated with a Class 1 building and appurtenant to it.
- Performance Solution
- A compliance pathway that satisfies the NCC Performance Requirements by analysis, testing or expert judgement rather than by following the prescriptive Deemed-to-Satisfy provisions.
- Deemed-to-Satisfy provisions
- Prescriptive NCC recipes, such as nominated dimensions and materials, that are accepted as automatically meeting the associated Performance Requirements without further analysis.
- Site classification class A
- A stable site of sand or rock with little ground movement due to moisture change, requiring only standard footing design under AS 2870 residential slabs and footings.
- Class P site
- A problem site where abnormal soil conditions such as soft clay, mine subsidence or landslip mean footings must be designed by a geotechnical engineer for that specific site.
- Habitable room ceiling height
- Generally 2.4 m minimum, with 2.1 m allowed over no more than one third of the floor area; kitchens, laundries, corridors and bathrooms may be 2.1 m.
- Habitable room natural light
- Window area to a compliant light source of at least 10 percent of the room floor area, with openable window area of at least 5 percent for ventilation.
- Stair riser and going
- For domestic stairs the riser is 190 to 220 mm and the going 240 to 355 mm, with a constant geometry and a 2 m head clearance above the nosing line.
- Balustrade 125 mm sphere
- A barrier must not have openings that allow a 125 mm sphere to pass through, preventing a young child from climbing or falling through the gap.
- Wet area upturn
- AS 3740 requires waterproofing turned up the wall at least 150 mm at junctions in wet areas, with full shower floor coverage and falls of about 1:80 to 1:100.
- Smoke alarm requirement
- Interconnected smoke alarms are required in Class 1a dwellings, located in each bedroom and in the path of travel between bedrooms and the rest of the dwelling.
- Energy rating requirement
- New domestic dwellings must meet the NCC energy efficiency provisions, commonly expressed as a star rating achieved through insulation, glazing, sealing and efficient services.
- Termite risk management
- AS 3660 requires a termite management system plus durable notices, and the system must be maintained and inspected for the life of the building.
- Footing depth to reactive clay
- Footings on reactive clay must extend to a depth where moisture variation is limited, typically 1.0 to 1.5 m depending on the site classification and tree influence.
- Damp-proof course
- A continuous moisture barrier in masonry at least 150 mm above finished ground level, preventing rising damp from entering the wall above.
- Progress payment schedule
- A contract term naming each stage and its payment amount; the builder may only claim a stage once that stage has actually been completed.
- Home warranty insurance
- Statutory insurance taken out before domestic work starts, covering structural defects typically for six years and non-structural defects for two years after completion.
- Written variation
- A signed document stating the change to the work, the resulting price adjustment and any time extension, agreed before the varied work is carried out.
- Retention
- A percentage, commonly 5 percent, withheld from progress payments and released at practical completion or on expiry of the defects liability period.
- Practical completion
- The stage when the works are complete except for minor omissions and defects that do not prevent the building being used for its intended purpose.
- Defects liability period
- A period, typically 12 months from practical completion, during which the owner notifies defects in writing and the builder must rectify them at no cost.
- Safe Work Method Statement
- A written document identifying high-risk construction work, the hazards, the control measures and how they will be implemented, monitored and reviewed on site.
- Critical path
- The longest sequence of dependent tasks through the programme; any delay on this path delays practical completion, so it carries zero float.
- Float in a programme
- The amount of time a non-critical task can be delayed without delaying the project completion date or breaching a dependent successor task.
- Statutory declaration on claims
- A sworn statement supporting a progress claim that subcontractors and suppliers have been paid, protecting the owner from later payment claims.
- Prime cost item
- An allowance in the contract for a material or fixture not yet selected, later adjusted to the actual cost plus the stated margin.
- Provisional sum
- An allowance for work that cannot be priced precisely at contract signing, adjusted to actual cost plus margin once the work is measured.
- Liquidated damages
- A pre-agreed genuine estimate of the owner's loss per day of delay, deducted from the contract sum if the builder fails to reach practical completion on time.
- Contract documents
- The signed contract, drawings, specification, schedules and any agreed variations that together define the scope, price, time and obligations of the parties.
- Site induction record
- A record showing each worker has been inducted on site hazards, emergency procedures and rules, kept as evidence of the builder's safety duty.
- Notice of practical completion
- Formal written notice from the builder to the owner stating the date practical completion is reached, triggering the defects liability period and final payment.