- D1.1 preheat minimum
- For Group I and II steels, minimum preheat is 32 °F (0 °C) for thickness up to 1/4 in, 50 °F (10 °C) above 1/4 to 3/4 in, and 150 °F (65 °C) above 3/4 in.
- D1.1 undercut limit
- Undercut shall not exceed 0.01 in depth plus 0.07 in width for any length, or 1/32 in depth for lengths up to 2 in in 12 in; cumulative undercut not to exceed 1/16 in in any 12 in.
- D1.1 groove reinforcement
- For groove welds, face reinforcement shall not exceed 1/8 in; the weld shall blend smoothly into the base metal without abrupt transitions.
- D1.1 welder requalification
- Welder performance qualification remains valid unless the welder has not welded with the process for 6 months or there is a specific reason to question the welder's ability.
- D1.2 oxide removal
- Aluminum oxide melts at a much higher temperature than the base metal; mechanical or chemical cleaning of the joint area is required before welding to prevent oxide inclusions.
- D1.2 preheat limit
- Preheat for aluminum is generally not required but may be used to remove moisture; preheat temperature shall not exceed 250 °F (120 °C) unless qualified by procedure testing.
- D1.2 filler selection
- Filler metal selection follows the base metal group in Table 3.2; the filler must be compatible with the alloy and temper to achieve the required joint properties.
- D1.5 FCM toughness
- Fracture-critical member welds require Charpy V-notch toughness testing of procedure qualification coupons and production weldments per Clause 12 of D1.5.
- D1.5 FCM NDT
- FCM groove welds require 100% volumetric examination (RT or UT) and 100% magnetic particle or penetrant testing of weld toes and roots where specified.
- D1.5 preheat
- Preheat requirements in D1.5 are generally higher than D1.1; minimum preheat for Group I/II steels is 50 °F (10 °C) and increases with thickness and carbon equivalent.
- D15.1 welder requalification
- Welder performance qualification under D15.1 is specific to process, position, and joint type; requalification is required after 6 months of inactivity or a specific reason to question ability.
- D15.1 repair procedure
- Repair welding requires removal of the defect by grinding or gouging, verification of the excavation, and re-welding per a qualified WPS followed by re-inspection.
- D15.1 safety components
- Safety-critical components such as trucks, bolsters, and draft gear require stricter acceptance and may require 100% NDT per the applicable specification.
- D17.1 quality classes
- D17.1 defines weld quality classes A, B, and C with different acceptance criteria for porosity, undercut, and reinforcement; the class must be specified by the drawing.
- D17.1 procedure qualification
- Procedure qualification requires mechanical testing (tensile, bend, and where applicable fatigue or hardness) of test coupons representing production welds.
- D17.1 cleanliness
- Pre-weld cleaning, inert gas shielding, and interpass cleaning are specified; contamination such as oil, oxide, or moisture causes rejectable defects.
- API 1104 requalification
- A welder must requalify after 6 months of inactivity with the process or a change in essential variables, or when there is a specific reason to question ability.
- API 1104 girth acceptance
- Cracks, incomplete fusion, and incomplete penetration are rejectable; porosity limits depend on maximum dimension and distribution per Section 9.
- API 1104 preheat
- Preheat and interpass temperature requirements are specified in the WPS; for high-strength pipe, preheat is typically 200-300 °F (93-149 °C).
- MT applicability
- MT detects surface and near-surface discontinuities in ferromagnetic materials; it is not applicable to austenitic stainless steel, aluminum, or copper alloys.
- MT field strength
- A pie gauge or field indicator confirms adequate magnetization; the required field is typically 30-40 gauss at the surface for continuous methods.
- MT black light
- Fluorescent MT requires black light intensity of at least 1000 µW/cm² at the surface; visible light background should be less than 20 lux.
- PT process sequence
- Pre-clean, apply penetrant, dwell, remove excess penetrant, apply developer, inspect, and post-clean; each step must follow the qualified procedure.
- PT temperature limits
- Standard PT is performed between 50 °F and 125 °F (10-52 °C); outside this range, qualification of the technique is required.
- PT black light
- Fluorescent PT requires black light intensity of at least 1000 µW/cm² at the inspection surface; visible light background should not exceed 20 lux.
- Section IX PQR
- A procedure qualification record documents test results; the WPS is written from the PQR and must address essential and nonessential variables per QW-250.
- B31.3 RT extent
- B31.3 requires 5% random RT for normal fluid service; severe and cyclic services may require 100% RT depending on the category.
- Section IX essential variables
- Essential variables include base metal P-number, filler metal F-number, position, preheat, and post-weld heat treatment; changes require requalification.
- ISO 9606-1 validity
- Welder qualification per ISO 9606-1 remains valid for 6 months of inactivity; requalification is required after that period or a change in essential variables.
- ISO 5817 quality levels
- ISO 5817 defines weld quality levels B, C, and D for steel; it is used as a reference for acceptance criteria for steel welds.
- ISO 9712 levels
- NDT personnel qualification per ISO 9712 has Level 1, 2, and 3 certification; Level 2 is typically required to perform and interpret testing.
- NDT inspection sequence
- NDT is performed after all welding and heat treatment are complete unless the procedure specifies otherwise; records must be traceable to the weld and welder.